A. Notice of the need for construction services shall be given by the school district pursuant to R7-2-1022 and R7-2-1024(C). Such notice shall be issued not less than 14 days in advance of when responses shall be received. The notice shall:
1.
Contain a statement of the construction services required that adequately
describes the procurement and specifies how a request for qualifications
containing specific information on the procurement may be obtained;
2. Specify whether the procurement is for a
single contract or, for job-order-contracting construction services only, for
multiple contracts; and
3. If the
procurement is for multiple job-order-contracting construction services
contracts:
a. Specify that multiple contracts
may or will be awarded;
b. Specify
the number of contracts that may or will be awarded; and
c. Describe the construction services to be
performed under each contract.
B. The request for qualifications shall include the following:
1. Instructions and
information to persons concerning the statement of qualifications submission
requirements, including the due date and time for receipt of statements of
qualifications, the address of the office at which the statements of
qualifications are to be received, and any other special information.
2. In a procurement of
construction-manager-at-risk construction services or design-build construction
services to be performed at multiple locations, include:
a. A brief description of the construction
services to be performed at each location;
b. The estimated budget for the construction
services to be performed at each location; and
c. A schedule for the construction services
to be performed at each location that shows the school district's intent to
commence all construction at each location within thirty months after execution
of the first contract for preconstruction services or other construction
services at any of the locations.
3. General information on the project site,
scope of work, schedule, selection criteria, project design and construction
budget, or life cycle budget for a procurement that includes maintenance,
operations, and finance services.
4. The criteria and the weight prescribed by
the school district for each of the criteria to be used in making the
evaluation.
a. All selection criteria shall be
factors that demonstrate competence and qualifications for the type of
construction services included in the procurement.
b. One of the criteria shall be the person's
subcontractor selection plan or procedures to implement the school district's
subcontractor selection plan.
c. If
interviews will be held, state the selection criteria and relative weights to
be used in selecting the persons to be interviewed. The request for
qualifications may state the selection criteria and relative weights to be used
in selecting the persons on the final list and in determining their order on
the final list. The final list selection criteria and relative weights may be
different than the selection criteria and relative weights used to determine
the persons to be interviewed. The request for qualifications also shall state
whether the school district will select the persons on the final list and their
order on the final list solely through the results of the interview process or
through the combined results of both the interview process and the evaluation
of statements of qualifications and performance data submitted in response to
the school district's request for qualifications.
d. If interviews will not be held, state the
selection criteria and relative weights to be used in selecting the persons on
the final list and in determining their order on the final list.
5. Whether one contract or
multiple contracts may or will be awarded.
a.
For design-build construction services, construction-manager-at-risk
construction services, and a single contract for job-order-contracting
construction services, state that one person may or will be awarded the
contract.
b. For multiple contracts
for similar job-order-contracting construction services, state the number of
contracts that may or will be awarded, the job-order-contracting construction
services to be performed under each of the contracts, and that each of the
multiple contracts will be awarded to a separate person.
6. In a procurement where the contract is to
be negotiated under
R7-2-1110(D):
a. State that there will be a single final
list of at least three and not more than five persons for a design-build,
construction-manager-at-risk, or single job-order-contracting construction
services award.
b. In a procurement
for multiple contracts for similar job-order-contracting construction services
to be awarded to separate persons, state that there will be a single final list
and the number of persons on the final list, which shall be the sum of the
number of contracts that may or will be awarded, plus another number that is
determined by the school district and that is not more than
five.
7. In a procurement
in which the contract will be awarded under
R7-2-1111:
a. State that there will be a single final
list and that the number of persons on the final list will be three for a
design-build or single job-order-contracting construction services
award.
b. In a procurement for
multiple contracts for similar job-order-contracting construction services to
be awarded to separate persons, state that there will be a single final list
and the number of persons on the final list, which shall be the sum of the
number of contracts that may or will be awarded, plus another number that is
determined by the school district and that is not more than
five.
8. The type of
contract to be used.
9. The name of
the district representative or district representatives and the publicly
available location of the school district's protest policy and
procedures.
10. If the school
district will hold interviews as part of the selection process:
a. State that interviews will be held and
that the interviews will be with at least three and not more than five persons
for a design-build, construction-manager-at-risk, or single
job-order-contracting construction services procurement.
b. In a procurement for multiple contracts
for similar job-order-contracting construction services to be awarded to
separate persons, state that interviews will be held and that the interviews
will be with a specified number of persons. The specified number shall be
stated in the request for qualifications, shall be determined by the school
district and shall be the sum of the number of contracts that may or will be
awarded, plus another number that is determined by the school district and that
is not more than five.
11. The manner in which subcontractors shall
be selected, either:
a. A requirement that
each person submit a proposed subcontractor selection plan and a requirement
that the proposed subcontractor selection plan shall select subcontractors
based on qualifications alone or on a combination of qualifications and price
and shall not select subcontractors based on price alone; or
b. A subcontractor selection plan adopted by
the school district that applies to the person that is selected to perform the
construction services and that requires subcontractors to be selected based on
qualifications alone or on a combination of qualifications and price and not
based on price alone and a requirement that each person shall submit a
description of the procedures it proposes to use to implement the school
district's subcontractor selection plan.
12. Notice that all information and
statements of qualifications submitted by persons will be made available for
public inspection after the school district has entered into a single contract
or all of the multiple contracts.
C. A copy of the request for qualifications shall be made available for public inspection at the school district office.
Disclaimer: These regulations may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.