Section R7-2-1103 - Contract Performance and Payment Bond
Current through Register Vol. 30, No. 38, September 20, 2024
A. The following bonds or security is required and is binding on the parties to the contract if the value of a construction or construction services award exceeds the amount established by R7-2-1002(A):
B. For design-bid-build construction, the bonds prescribed in subsection (A) shall be provided on and at the same time as execution of the construction contract. For construction-manager-at-risk, design-build and job-order-contracting construction services, the bonds prescribed in subsection (A) shall be provided only on and at the same time as execution of a contract or contract modification that commits the contractor to provide construction for a fixed price, guaranteed maximum price or other fixed amount within a designated time frame.
C. If the prime contract or specifications require any persons supplying labor or materials in the prosecution of the work to furnish payment or performance bonds, these bonds shall be executed solely by a surety company or companies holding a certificate of authority to transact surety business in this state issued by the director of the Department of Insurance pursuant to Arizona Revised Statutes Title 20, Chapter 2, Article 1. Notwithstanding the provisions of any other statute, the bonds shall not be executed by an individual surety or sureties, even if the requirements of A.R.S. § 7-101 are satisfied.
D. If a contractor fails to deliver the required performance bond or payment bond, the contractor's bid shall be rejected, its bid security shall be enforced, and award of the contract shall be made pursuant to Articles 10 and 11.
E. This Section shall not be construed to limit the authority of the school district to require a performance bond or other security in addition to those bonds or in circumstances other than specified in subsection (A).
F. Any person who furnishes labor or material to the contractor or its subcontractors for the work provided in the contract, in respect of which a payment bond is furnished under this Section, and who has not been paid in full within 90 days from the date on which the last of the labor was performed or material was supplied by the person for whom the claim is made has the right to sue on the payment bond for any amount unpaid at the time the suit is instituted and to prosecute the action for the amount due the person. However, any person who has a contract with a subcontractor of the contractor, but no express or implied contract with the contractor furnishing the payment bond, has a right of action on the payment bond on giving the contractor, only, a written preliminary 20-day notice as provided for in A.R.S. § 33-992.01, subsection (C)(1), (2), (3), and (4) and subsections (D), (E), and (H), and upon giving written notice to the contractor within 90 days from the date on which the last of the labor was performed or material was supplied by the person for whom the claim is made. The person shall state in the notice the amount claimed and the name of the party for whom the labor was performed or to whom the material was supplied. The notice shall be personally served or sent by registered mail, postage prepaid, in an envelope addressed to the contractor at any place the contractor maintains an office or conducts business.