Section R7-2-1100 - Construction Project Delivery Methods
Current through Register Vol. 30, No. 38, September 20, 2024
A. For the design-bid-build project delivery method, the school district shall procure:
B. For construction-manager-at-risk, design-build and job-order-contracting project delivery methods, the school district shall procure construction services pursuant to R7-2-1102 through R7-2-1115.
C. For construction-manager-at-risk project delivery method, the school district shall purchase design services pursuant to R7-2-1117 through R7-2-1123.
D. For job-order-contracting project delivery method, the school district may include design services in the job-order-contracting construction services contract, but if the school district does not include design services in the contract, the school district shall procure any design services relating to construction services projects under the contract pursuant to R7-2-1117 through R7-2-1123.