Arizona Administrative Code
Title 4 - PROFESSIONS AND OCCUPATIONS
Chapter 34 - BOARD OF MANUFACTURED HOUSING
Article 7 - PLAN APPROVALS
Section R4-34-701 - General
Current through Register Vol. 30, No. 38, September 20, 2024
A. Before construction of a manufactured home or an FBB, a manufacturer shall submit to the office:
B. Before performing one of the following, a person shall obtain plan approval:
C. Within 20 business days after receiving a plan submitted under subsection (B), the Department shall perform an administrative review of the plan submittal and if incomplete, require the licensee to provide a complete plan submittal. Within 20 business days after receiving a complete plan submittal, the Department shall approve or disapprove the plan submittal.
D. A person that submits a plan under subsection (B) shall ensure the plan conforms to the following standards: