Arizona Administrative Code
Title 14 - PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION
Chapter 5 - CORPORATION COMMISSION - TRANSPORTATION
Article 2 - PIPELINE SAFETY
Section R14-5-202 - Construction and Safety Standards for Gas, LNG, and Hazardous Liquid Pipeline Systems
Current through Register Vol. 30, No. 38, September 20, 2024
A. Applicability: This Section applies to the construction, reconstruction, repair, operation, and maintenance of each intrastate gas, LNG, or hazardous liquid pipeline system, pursuant to A.R.S. § 40-441.
B. Subject to the definitional changes in R14-5-201 and the modifications noted in this Section, the Commission adopts, incorporates, and approves as its own 49 CFR 40; 191; 192, except (I)(A)(2) and (3) of Appendix D to Part 192; 193; 195, except 195.1(b)(2), (3), and (4); and 199 (October 1, 2022), including no future editions or amendments, which are incorporated by reference; on file with the Arizona Office of Pipeline Safety (AZOPS); and published by and available from the Government Bookstore at https://bookstore.gpo.gov and online at ecfr.gov. For purposes of 49 CFR 192, "Business District" means an area where the public congregate for economic, industrial, religious, educational, health, or recreational purposes and two or more buildings used for these purposes are located within 100 yards of each other.
C. The above mentioned incorporated Parts of 49 CFR, except 49 CFR 191 ; 49 CFR 192.727(g)(1), 192.913(b)(1)(vii), 192.943(a), 192.949(a)-(b), and 192.951; 49 CFR 193 Subpart A; and 49 CFR 195 Subparts A and B, are revised as follows:
D. An operator of an intrastate pipeline shall file with the AZOPS an Operation and Maintenance Plan, including an emergency plan, at least 30 days before placing a pipeline system into operation. Any changes in an existing Operation and Maintenance Plan shall be filed within 30 days after the effective date of the change.
E. An operator of an intrastate pipeline transporting sour gas or sour oil shall comply with the following industry standards addressing facilities handling hydrogen sulfide (H2S), which are incorporated by reference, including no future editions or amendments:
F. An operator of an intrastate pipeline transporting LNG, hazardous liquid, or gas shall not construct any part of a hazardous liquid, LNG, or gas pipeline system under a building. If a building encroaches over a pipeline system, the operator may require the property owner to remove the building from over the pipeline or to reimburse the operator the cost associated with relocating the pipeline system. The operator shall determine, within 90 days after discovering the encroachment, whether the encroachment can be resolved within 180 days. If the operator determines that the encroachment cannot be resolved within 180 days, the operator shall, within 90 days of discovery, submit to the AZOPS a written plan to resolve the encroachment within a period longer than 180 days. The AZOPS may then extend the 180-day requirement to allow the property owner and the operator to implement the written plan to resolve the encroachment. If the operator does not submit a written plan, and the encroachment is not resolved within 180 days of discovery, the operator shall discontinue service to the pipeline system. This modifies 49 CFR 192.361 and 195.210.
G. An operator of an intrastate distribution pipeline transporting gas shall not construct any part of a pipeline system less than 8 inches away from any other underground structure. If the 8-inch clearance cannot be maintained, a sleeve, casing, or shielding shall be used. This modifies 49 CFR 192.361.
H. An operator of an intrastate pipeline transporting gas that has regulators, meters, or regulation meter sets that have been out of service for 36 months shall disconnect the pipeline from all sources and supplies of gas or hazardous liquids, purge the gas or hazardous liquids from the pipeline being disconnected, and cap all ends within six months after the 36 months have passed. This modifies 49 CFR 192.727.
I. An operator of an intrastate pipeline shall not install or operate a gas regulator that might release gas within 3 feet of a source of ignition, an opening into a building, an air intake into a building, or any electrical source that is not intrinsically safe. The 3 -foot clearance from a source of ignition shall be measured from the vent or source of release (discharge port), not from the physical location of the meter set assembly. This subsection does not apply to building permits issued and subdivisions platted before October 1, 2000. If an encroachment into the required 3 -foot clearance is caused by an action of the property owner, an occupant, or a provider after the effective date of this rule, the operator may require the property owner to resolve the encroachment or to reimburse the operator the cost associated with relocating the pipeline system. The operator shall determine, within 90 days after discovering the encroachment, whether the encroachment can be resolved within 180 days. If the operator determines that the encroachment cannot be resolved within 180 days, the operator shall, within 90 days of discovery, submit to the AZOPS a written plan to resolve the encroachment within a period longer than 180 days. The AZOPS may then extend the 180-day requirement to allow the property owner and the operator to implement the written plan to resolve the encroachment. If the operator does not submit a written plan, and the encroachment is not resolved within 180 days of discovery, the operator shall discontinue service to the affected pipeline system. This modifies 49 CFR 192.357 and 192.361.
J. An operator of an intrastate pipeline transporting LNG, gas, or a hazardous liquid shall use a cathodic protection system designed to protect the metallic pipeline in its entirety, in accordance with 49 CFR 192, Subpart I, as incorporated by reference in subsection (B). Sections (I)(A)(2) and (3) of Appendix D to Part 192 shall not be utilized. This modifies 49 CFR 192.463(a), 193.2629, and 195.571.
K. An operator of an intrastate pipeline transporting hazardous liquid or gas shall not install Acrylonitrile-Butadiene-Styrene (ABS) or aluminum pipe in a pipeline system. This modifies 49 CFR 192.53 and 192.59.
L. An operator of an intrastate pipeline transporting hazardous liquid or gas shall not install plastic pipe aboveground unless the plastic pipeline is protected by a metal casing, or equivalent, and the installation is approved by the AZOPS. An operator may use a temporary aboveground plastic pipeline bypass for up to 60 days, provided that the plastic pipeline is under the direct supervision of the operator and protected at all times. This modifies 49 CFR 192.321 and 195.254.
M. An operator of an intrastate pipeline transporting hazardous liquid or gas that constructs a pipeline system or any portion thereof using plastic pipe shall install, at a minimum, a 14-gauge coated or corrosion resistant, electrically conductive wire as a means of locating the pipe while it is underground. Tracer wire shall not be wrapped around the plastic pipe. Tracer wire may be taped, or attached to the pipe in another manner, provided that the adhesive or attachment is not detrimental to the integrity of the pipe wall. This modifies 49 CFR 192.321 and 195.246.
N. An operator of an intrastate pipeline transporting gas or hazardous liquid that constructs an underground pipeline system using plastic pipe shall bury the installed pipe with at least 6 inches of sandy type soil, free of any rock or debris, surrounding the pipe for bedding and shading, unless the pipe is otherwise protected as approved by the AZOPS. Steel pipe shall be installed with at least 6 inches of sandy type soil, free of any debris or materials injurious to the pipe coating, surrounding the pipe for bedding and shading, unless the pipe is otherwise protected as approved by the AZOPS. This modifies 49 CFR 192.321, 192.329, 192.361, and 195.246.
O. An operator of an intrastate pipeline transporting gas that constructs an underground pipeline system using plastic pipe shall install the pipe with sufficient slack to allow for thermal expansion and contraction. In addition, all plastic pipe and fittings for use in an area with service temperatures above 100º F shall be tested and marked CD, CE, CF, or CG as required by ASTM D2513 (2018-a), including no future editions or amendments, which is incorporated by reference, on file with the AZOPS, and published by and available from ASTM International, 100 Barr Harbor Dr., P.O. Box C700, W. Conshohocken, PA 19428-2959 and through http://www.astm.org. This modifies 49 CFR 192.63.
P. An operator of an intrastate pipeline system transporting hazardous liquid or gas shall qualify welding procedures and shall ensure that welding of steel pipelines is performed in accordance with API Standard 1104, as incorporated by reference in 49 CFR 192.7, by welders qualified pursuant to API Standard 1104, except that welders qualified as delineated in 49 CFR 192, Appendix C may be used for low stress level pipe. This modifies 49 CFR 192.225, 192.227, 195.214, and 195.222.
Q. An operator of an intrastate pipeline transporting gas shall survey and grade all detected leakage according to the standards provided below, which modify 49 CFR 192.706 and 192.723:
R. An operator of an intrastate transmission pipeline transporting gas shall conduct a leakage survey at least twice each calendar year, at an interval not exceeding 7 1/2 months, independent of class location, and shall repair each underground leak classified as grade two or three either upon discovery or within one year after discovery. This modifies 49 CFR 192.706 and 192.711.
S. An operator of an intrastate transmission pipeline transporting gas and operating at or above 20 percent of Specified Minimum Yield Strength shall ensure that nondestructive testing is completed for each weld performed on newly installed, replaced, or repaired pipeline or an appurtenance. The nondestructive testing shall be completed before the newly welded area of the pipeline or appurtenance is used for service. This modifies 49 CFR 192.241.
T. An operator of an LNG facility shall ensure that nondestructive testing is completed for each weld performed on newly installed, replaced, or repaired pipeline or an appurtenance. This modifies 49 CFR 193.2303.
U. In the event of an unknown failure of a gas, LNG, or hazardous liquid pipeline, resulting in the operator's being required to provide a telephonic or written report under R14-5-203(B) or (C) and in the operator's removing a portion of the failed pipeline, the following shall occur:
V. An operator shall ensure that all repair work performed on an existing intrastate pipeline transporting LNG, hazardous liquid, or gas complies with this Article.
W. The Commission may waive compliance with any of the requirements of this Section upon a finding that such a waiver is in the interest of public and pipeline safety.
X. To ensure compliance with the provisions of this Article, the Commission or an authorized representative thereof may enter the premises of an operator of an intrastate pipeline to inspect and investigate the property, books, papers, electronic files, business methods, and affairs that pertain to the pipeline system operation.