Section R14-3-209 - Extensions of time

Universal Citation: AZ Admin Code R 14-3-209
Current through Register Vol. 30, No. 38, September 20, 2024

For good cause shown, continuances and extensions of time will be granted in the discretion of the Presiding Officer, provided however, that when such continuance or extension is provided to an applicant, the running of the 180-day period specified in R14-3-213(A) shall be deemed to be tolled and shall cease to run during such continuance or extension. No such continuance or extension shall be granted to an applicant until such applicant has waived its right to "immediately proceed with construction of the planned facilities" as provided in A.R.S. § 40-360.08(B) for a period of time equal to the applicable time period under these regulations; plus such continuance or extension.

Effective 2-70.

Disclaimer: These regulations may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.