Arizona Administrative Code
Title 14 - PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION
Chapter 2 - CORPORATION COMMISSION - FIXED UTILITIES
Article 7 - RESOURCE PLANNING AND PROCUREMENT
Section R14-2-702 - Applicability
Current through Register Vol. 30, No. 38, September 20, 2024
A. This Article applies to each load-serving entity, whether the power generated is for sale to end users or is for resale.
B. An electricity public service corporation that becomes a load-serving entity by increasing its generating capacity to at least 50 megawatts combined shall provide written notice to the Commission within 30 days after the increase and shall comply with the filing requirements in this Article within two years after the notice is filed.
C. The Commission may, by Order, exempt a load-serving entity from complying with any provision in this Article, or the Article as a whole, upon determining that:
D. A load-serving entity that desires an exemption shall submit to Docket Control an application that includes, at a minimum:
E. A load-serving entity shall file with Docket Control, within 120 days after the effective date of these rules, the documents that would have been due on April 1, 2010, under R14-2-703(C), (D), (E), (F), and (H) had the revisions to those subsections been effective at that time.