Arizona Administrative Code
Title 14 - PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION
Chapter 2 - CORPORATION COMMISSION - FIXED UTILITIES
Article 26 - INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES
Section R14-2-2621 - Utility Site Inspection; Approval for Parallel Operation
Current through Register Vol. 30, No. 38, September 20, 2024
A. Once an Application is approved for Interconnection:
B. Within seven calendar days after a site inspection is deemed necessary by the Utility, or requested by the Customer, the Utility shall perform a site inspection for which it may charge a fee, if a tariff containing such a fee is approved for the Utility by the Commission. During a site inspection, the Utility shall verify at least the following:
C. The Utility shall install appropriate metering equipment, if required. The Utility may require the Customer to pay for the metering equipment, if a tariff containing such a fee is approved for the Utility by the Commission.
D. Within three calendar days of the completion of the site inspection and the receipt of all final applicable signed Interconnection documents, the Utility shall determine whether the Generating Facility meets all applicable requirements and shall notify the Customer that:
E. If the Generating Facility fails the initial Utility site inspection:
F. A Utility may take any reasonable actions, including locking open a Disconnect Switch, to prevent Parallel Operation for:
G. If a Customer does not interconnect a Generating Facility within 180 calendar days after Application approval, the Customer's Application may be considered withdrawn.