Arizona Administrative Code
Title 14 - PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION
Chapter 2 - CORPORATION COMMISSION - FIXED UTILITIES
Article 26 - INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES
Section R14-2-2614 - Application and Generating Facility General Requirements

Universal Citation: AZ Admin Code R 14-2-2614

Current through Register Vol. 30, No. 38, September 20, 2024

A. A Customer desiring to interconnect to the Distribution System a Generating Facility that is not a Non-Exporting inverter-based energy storage Generating Facility or an Inadvertent Export Generating Facility with a Maximum Capacity of 20 kW or less shall apply to the Utility for Interconnection as provided in this Section.

B. An Applicant shall submit an Application on a form provided by the Utility, or according to a format provided by the Utility, along with the following:

1. All supplemental information and documents required by the Utility, which shall be noted on the Utility's Application or Application instructions;

2. An executed Interconnection Agreement, if required by the Utility; and

3. An initial Application or processing fee, if a tariff containing such a fee is approved for the Utility by the Commission.

C. Upon request, a Utility shall provide an Applicant with sample diagrams that indicate the preferred level of detail and type of information required for a typical inverter-based system.

D. Within seven calendar days after receiving an Application, a Utility shall review the Application and provide the Applicant notice:

1. That the Application satisfies all requirements under subsection (B); or

2. That the Application does not satisfy one or more requirements under subsection (B), in which case:
a. The Utility shall specify the additional information or documents required;

b. The Applicant shall submit the specified information or documents; and

c. The Application may be deemed withdrawn if the Applicant does not submit the required information or documents within 30 calendar days.

E. A Generating Facility shall comply with the following general requirements:

1. If inverter based, each inverter shall meet the shutdown protective functions (under/over voltage, under/over frequency, and anti-Islanding) specified in IEEE 1547-2018 - IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces (April 6, 2018), with no future editions or amendments, which is incorporated by reference; on file with the Commission; and published by and available from IEEE, 3 Park Avenue, 17th Floor, New York, New York 10016, and through http://ieeexplore.ieee.org;

2. The Generating Facility shall meet all applicable codes and standards required by this Article and referenced in the Utility Interconnection Manual; and

3. The Generating Facility shall comply with the Utility's Interconnection Manual and Interconnection Agreement requirements.

Disclaimer: These regulations may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.