Arizona Administrative Code
Title 14 - PUBLIC SERVICE CORPORATIONS; CORPORATIONS AND ASSOCIATIONS; SECURITIES REGULATION
Chapter 2 - CORPORATION COMMISSION - FIXED UTILITIES
Article 26 - INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES
Section R14-2-2614 - Application and Generating Facility General Requirements
Current through Register Vol. 30, No. 38, September 20, 2024
A. A Customer desiring to interconnect to the Distribution System a Generating Facility that is not a Non-Exporting inverter-based energy storage Generating Facility or an Inadvertent Export Generating Facility with a Maximum Capacity of 20 kW or less shall apply to the Utility for Interconnection as provided in this Section.
B. An Applicant shall submit an Application on a form provided by the Utility, or according to a format provided by the Utility, along with the following:
C. Upon request, a Utility shall provide an Applicant with sample diagrams that indicate the preferred level of detail and type of information required for a typical inverter-based system.
D. Within seven calendar days after receiving an Application, a Utility shall review the Application and provide the Applicant notice:
E. A Generating Facility shall comply with the following general requirements: