A Utility shall not reject or declare incomplete and require resubmission of a submitted Application if minor modifications must be made to the design of the Generating Facility or to other information on the Application (including ownership of Generating Facility) while the Application is being reviewed by the Utility or prior to completing the Interconnection of the Generating Facility.

Disclaimer: These regulations may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.