Section R12-7-127 - Plugging Methods and Procedures
Current through Register Vol. 30, No. 38, September 20, 2024
A. Before abandoning any well, the operator shall submit an application to plug and abandon to the Commission for approval as required in R12-7-126. All down-hole plugging shall be conducted through drill pipe or tubing, unless otherwise approved by the Commission.
B. Open hole
C. Cased hole
D. Plugging mud having the proper weight and consistency to prevent movement of other fluids into or within the bore hole shall be placed across all intervals not plugged with cement. In the absence of other information at the time plugging is approved, plugging mud shall be made up with a minimum of 15 pounds per barrel of sodium bentonite and a nonfermenting polymer, have a minimum consistency of 9 pounds per gallon, a minimum viscosity of 50 seconds per quart, and mixed with fresh water.
E. A cement surface plug of at least 50 feet shall be placed in the smallest casing which extends to the surface. The top of this plug shall be placed as near the eventual casing cut-off point as possible.
F. The abandoned well shall be marked by a piece of metal pipe not less than 4 inches in diameter securely set in cement and extending at least 4 feet above the general ground level. The well location and identity shall be permanently inscribed as required in R12-7-106(A). An abandoned well location on tilled or otherwise unique land shall be marked in a manner approved by the Commission.
G. The drill site of an abandoned well shall be restored as nearly as possible to its natural state, to the satisfaction of the Commission. All pits shall be filled and all equipment and debris shall be removed from the location.
H. The operator shall notify the Commission at least 48 hours before starting abandonment operations to allow a representative of the Commission to witness the operations required in this Section. To ensure the integrity or placement of any plug, the representative may order the plug to be tested.
I. Within 15 days after the plugging of any well, the operator shall file with the Commission a plugging record setting forth in detail the method used in plugging the well, including the casing record; the size, kind, and depth of plugs used; and the name and depth interval of each formation containing fresh water, oil, gas, or geothermal resources.
J. Seismic shot holes