Arizona Administrative Code
Title 12 - NATURAL RESOURCES
Chapter 7 - OIL AND GAS CONSERVATION COMMISSION
Article 1 - OIL, GAS, HELIUM, AND GEOTHERMAL RESOURCES
Section R12-7-121 - Well Completion and Filing Requirements
Current through Register Vol. 30, No. 38, September 20, 2024
A. An operator shall file a completion report with the Commission within 30 days after a well is completed. The completion report shall contain a description of the well and lease, the casing, tubing, liner, perforation, stimulation, and cement squeeze records, and data on the initial production. The operator shall submit other well data to the Commission within 30 days of the date the work is done, including any:
B. An operator shall furnish samples of drilled cuttings, at a maximum interval of 10 feet, to the Commission within 30 days after drilling is completed. The operator may furnish samples of continuous core in chips at 1-foot intervals. The operator shall:
Oil and Gas Administrator
Arizona Geological Survey
416 W. Congress, Ste. 100
Tucson, AZ 85701
C. Confidential records: