Arizona Administrative Code
Title 12 - NATURAL RESOURCES
Chapter 7 - OIL AND GAS CONSERVATION COMMISSION
Article 1 - OIL, GAS, HELIUM, AND GEOTHERMAL RESOURCES
Section R12-7-116 - Multiple Zone Completions
Current through Register Vol. 30, No. 38, September 20, 2024
A. Completions to include production from more than one common source of supply from a single well are prohibited except as authorized by the Commission after notice and hearing. After notice and hearing, the Commission shall maintain a list of zones or reservoirs, by fields, for which multiple completions have been authorized.
B. Operators shall file an application for multiple completion with the Commission and shall demonstrate the method to be used to keep the production streams separate. The application shall be accompanied by:
C. The Commission may approve subsequent applications for multiple completion of the same zones or reservoirs in a field administratively without a hearing, provided that:
D. Within 15 days of setting the final packer or packers, the operator shall file a report with the Commission identifying the well and its location showing the make, type, and depth set of each packer and the signature of the supervisor of the work. This report shall include the results of a packer leakage test and detail for each separate common source of supply, its stabilized shut-in pressure, producing pressure, and the simultaneous shut-in pressure on each other separate common source of supply. The operator shall notify the Commission at least 48 hours in advance of performing the tests required in this subsection.
E. Every operator of a multi-completed well shall operate, produce, and maintain the well to prevent commingling of production from the separate sources of supply. The Commission may require any multi-completed well to be tested at any time to demonstrate the effectiveness of the separation of sources of supply. These tests may be witnessed by representatives of the Commission and by offset operators.