Arizona Administrative Code
Title 12 - NATURAL RESOURCES
Chapter 15 - DEPARTMENT OF WATER RESOURCES
Article 7 - ASSURED AND ADEQUATE WATER SUPPLY
Section R12-15-706 - Assignment of Type B Certificate of Assured Water Supply

Universal Citation: AZ Admin Code R 12-15-706

Current through Register Vol. 30, No. 38, September 20, 2024

A. The certificate holder of a Type B certificate or a certificate issued before the effective date of this Section that has not been classified pursuant to R12-15-707 and the assignee may apply for approval of an assignment of the certificate to another person within the time allowed by A.R.S. § 45-579(A). The assignee may file the application if there is no certificate holder. The application shall be submitted on a form prescribed by the Director with the initial fee required by R12-15-103(C), and the applicant shall provide the following:

1. One of the following forms of proof of ownership for each assignee:
a. A title report, condition of title report, limited search title report, or recorded deed, dated within 90 days of the date the application is submitted to the Director and demonstrating that the assignee is the owner of the land that is the subject of the proposed assignment; or

b. If the assignee is a potential purchaser, evidence of a purchase agreement;

2. A current plat of the subdivision;

3. An estimate of the 100-year water demand for the subdivision, based on the current plat;

4. Evidence that all necessary water rights, permits, licenses, contracts, and easements have been or will be assigned to the assignee of the certificate;

5. Evidence that the assignee has the financial capability to construct adequate delivery, storage, and treatment works for the subdivision according to the criteria in R12-15-720;

6. Evidence that all water supplies listed on the current certificate are physically, continuously, and legally available to meet the estimated water demand of the subdivision after the assignment;

7. Evidence that the proposed municipal provider has not changed and has agreed to serve the subdivision after the assignment;

8. If the applicant requests that the Director classify the certificate pursuant to subsection (E) of this Section, evidence that the requirements of R12-15-704(H)(1) are satisfied;

9. Any other information that the Director reasonably deems necessary to determine whether the application meets the criteria of A.R.S. § 45-579.

B. Each applicant shall sign the application for an assignment of a certificate. If an applicant is not a natural person, the entity's authorized officer, managing member, partner, trust officer, trustee, or other person who performs similar decision-making functions for the applicant shall sign the application. If an applicant submits a letter, signed by the applicant and dated within 90 days of the date the application is submitted, authorizing a representative to submit applications for permits regarding the land to be included in the certificate, the authorized representative may sign the application on the applicant's behalf.

C. Upon receiving an application for an assignment, the Director shall post the notice required by A.R.S. § 45-579(E).

D. Except as provided in subsection (E) of this Section, if the Director determines that the application meets the criteria of A.R.S. § 45-579(A), the Director shall issue a Type B certificate to each applicant. A Type B certificate issued under this subsection shall retain the issue date, the number of lots, and the estimated water demand shown on the original certificate, except as provided in subsection (F) of this Section. The Director shall determine that the application meets the criteria of A.R.S. § 45-579(A) if all of the following apply:

1. The application is submitted within the time allowed by A.R.S. § 45-579(A);

2. The assignee is the owner or potential purchaser of the portion of the subdivision that is the subject of the assignment;

3. There have been no material changes to the plat for which the original certificate was issued, according to the criteria in R12-15-708;

4. The applicant demonstrates the financial capability to construct adequate delivery, storage, and treatment works for the subdivision according to the criteria in R12-15-720;

5. All necessary water rights, permits, licenses, contracts, and easements have been or will be assigned to the assignee of the certificate;

6. All water supplies listed on the current certificate are physically, continuously, and legally available to meet the estimated water demand of the subdivision after the assignment;

7. Neither the applicant nor a predecessor in interest has impaired the manner in which consistency with management goal requirements were satisfied when the original certificate was issued; and

8. The proposed municipal provider has agreed to serve the subdivision after the assignment.

E. The applicant may include in the application a request to classify the certificate as a Type A certificate. If the Director determines that the request meets the requirements of R12-15-704(H)(1), the Director shall classify the certificate as a Type A certificate.

F. In the case of a partial assignment, the Director shall determine whether changes to the plat are material according to R12-15-708. The Director shall issue a Type B certificate to the assignee for the portion of the subdivision that is the subject of the assignment and for the number of lots and the estimated water demand of the current plat of the portion of the subdivision that is the subject of the assignment. The Director shall issue a Type B certificate to the certificate holder for the portion of the subdivision retained by the certificate holder and for the remainder of the number of lots and the remainder of the estimated water demand. The sum of the number of lots and the sum of the amount of the estimated water demand shown on each certificate shall equal the total number of lots and the total estimated water demand shown on the certificate that is being assigned.

G. The Director shall review an application for an assignment of a Type B certificate pursuant to the licensing time-frame provisions in R12-15-401.

Disclaimer: These regulations may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.