Arizona Administrative Code
Title 12 - NATURAL RESOURCES
Chapter 15 - DEPARTMENT OF WATER RESOURCES
Article 12 - DAM SAFETY PROCEDURES
Section R12-15-1209 - Application to Breach or Remove a High or Significant Hazard Potential Dam
Current through Register Vol. 30, No. 38, September 20, 2024
A. An applicant shall excavate the dam down to the level of the natural ground at the maximum section. Upon approval of the Director, additional breaches may be made. This provision shall not be construed to require more than total removal of the dam regardless of the flood magnitude. The breach or breaches shall be of sufficient width to pass the greater of:
B. The sides of each breach shall be excavated to a slope ratio that is stable and not steeper than 1 horizontal to 1 vertical.
C. Each breach shall be designed to prevent silt that has previously been deposited on the reservoir bottom and the excavated material from the breach from washing downstream.
D. Before breaching the dam, the reservoir shall be emptied in a controlled manner that will not endanger lives or damage downstream property. The applicant shall obtain approval from the Director for the method of breaching or removal.
E. An application package to breach or remove a high or significant hazard potential dam shall include the following prepared by or under the supervision of an engineer as defined in R12-15-1202(11).
F. Reduction of a high or significant downstream hazard potential dam to nonjurisdictional size may be approved by letter under the following circumstances: