Alaska Administrative Code
Title 8 - Labor and Workforce Development
Part 4 - Occupational Safety and Health Division
Chapter 80 - Boiler and Pressure Vessel Construction Code
Article 2 - Operation Controls
8 AAC 80.090 - Blowdown tanks

Universal Citation: 8 AK Admin Code 80.090
Current through February 27, 2024

Vented blowdown tanks must be designed for a minimum working pressure of 50 psi and be built in accordance with Section VIII of the ASME Code.If a blowdown tank is not vented, it must meet the requirements of the ASME Code,be manufactured to the maximum allowable working pressure of the boiler, and be equipped with a safety relief valve of capacity equal to that of the attached boiler.

Authority:AS 18.60.180

Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.