Alaska Administrative Code
Title 18 - Environmental Conservation
Chapter 15 - Administrative Procedures
Article 2 - Permit Procedures
18 AAC 15.020 - Permit applications
Universal Citation: 18 AK Admin Code 18 AAC 15.020
Current through February 24, 2025
(a) Except as provided in 18 AAC 15.130 - 18 AAC 15.140, an applicant for a permit or written approval subject to 18 AAC 15.020 - 18 AAC 15.100 must serve a complete application on the department.
(b) An applicant must serve a complete application under (a) of this section for the department's review at least
(1) five days before the proposed
commencement of the operation, for applications for surface oiling
permits;
(2) 30 days before the
proposed commencement of construction, installation, modification, or
improvement, for applications for plan approvals or permits for a sewerage
system treatment works, or public water system;
(3) 60 days before the proposed commencement
of construction, installation, modification, or improvement, for applications
for plan approvals or permits for a municipal sewerage system, treatment works,
or public water system project that involves state or federal monetary
assistance;
(4) 60 days before the
proposed commencement of the operation, for an application for a solid waste
disposal permit, short-term variance form water quality standards, or
wastewater disposal permit; and
(5)
100 days before the proposed commencement of a pesticide use that requires a
permit under 18 AAC 90.
Authority:AS 46.03.020
AS 46.03.100
AS 46.03.110
AS 46.03.320
AS 46.03.330
AS 46.03.720
AS 46.03.730
Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.