Alaska Administrative Code
Title 17 - Transportation and Public Facilities
Chapter 97 - Naturally Occurring Asbestos
17 AAC 97.050 - Responsibilities
Universal Citation: 17 AK Admin Code 17 AAC 97.050
Current through August 30, 2024
The project owner and each contractor are responsible for fulfilling their respective requirements of the site-specific plan approved under 17 AAC 97.040. The contractor shall ensure that each party involved with the project, including each subcontractor, complies with the approved site-specific plan.
Authority:AS 44.42.030
AS 44.42.420
AS 44.42.430
Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.