(a) The watthour meter test must consist of a light load test, a full load test, and 50 percent power factor as follows:
(b) The meter disk must complete at least
(c) A meter may not creep.
(d) Maximum tolerances for watthour meter are as follows:
(e) The director will accept a manufacturer's certificate of accuracy for new single phase, single stator meters when the following conditions are met:
(f) The division may test selected meters that are received by the utilities from the manufacturers to determine whether the meters meet the requirements of this section. Acceptance or rejection of a meter lot based on the sample test procedures will be determined by the division.
(g) The procedure in (e) of this section does not relieve the utility company of its responsibility for testing and assurance of accuracy as stated in 17 AAC 90.500, but will be accepted as a substitute by the division, if the utility desires to use the manufacturer's services and the manufacturer can meet the division's conditions.
(h) The division will provide testing assistance to utilities that do not have test equipment to ensure the accuracy of meters.
Authority:AS 45.75.040
AS 45.75.050
AS 45.75.070
AS 45.75.080