17 AAC 45.318 - Nonresponsive bids

Universal Citation: 17 AK Admin Code 17 AAC 45.318

Current through August 30, 2024

The department will reject as nonresponsive each of multiple bids submitted under the same name or under different names, if the bidding entities are owned or controlled by the same person, or if the bid

(1) is submitted late or to the wrong place, unless the department determines that the bid was received before the last date and time set for bid opening and that the delay or incorrect place of bid submission was due to an error of the department;

(2) does not include the required bid deposit;

(3) is not validly signed;

(4) is illegible;

(5) is not submitted in a sealed package;

(6) fails to acknowledge all material addenda the department has issued;

(7) offers an alternative compensation formula that the bid documents do not allow;

(8) does not conform in all material respects to the bid documents; or

(9) is conditional.

Authority:AS 02.15.020

AS 02.15.060

AS 02.15.070

AS 02.15.090

Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.