(a) Each permittee shall give the department written notice not less than 10 days before the start of construction on any utility facility.
(b) A copy of the permit must be at the work site during construction and installation operations and must be shown, upon request, to any department representative, Alaska state trooper, or other enforcement officer of the state.
(c) The department will, in its discretion, require inspection of the facility during construction and installation operations. The inspection must be sufficient to ensure full compliance with the provisions of the permit.
Authority:AS 02.15.020
AS 02.15.102
AS 02.15.106
AS 19.05.020
AS 19.05.040
AS 19.25.200
AS 19.30.051
AS 19.30.121
AS 19.40.065
AS 35.05.020
AS 35.10.210
AS 35.10.230