17 AAC 15.101 - Permits for utility service connections

Universal Citation: 17 AK Admin Code 17 AAC 15.101

Current through November 28, 2024

(a) The department will require an amendment to an existing utility permit or new permit for all utility service connections subsequent to the issuance of the original permit for the distribution, collection, or feeder line facility.

(b) The department may allow a permittee to install additional service connections within a department right-of-way where a longitudinal underground, surface, or overhead distribution or feeder line has been installed under a utility permit. The department will amend the utility permit to include the additional service connections.

(c) New permits are required for underground utility service connections which cross a department right-of-way and which originate from distribution lines located outside the right-of-way.

Authority:AS 02.15.020

AS 02.15.102

AS 02.15.106

AS 19.05.020

AS 19.05.040

AS 19.25.010

AS 19.25.200

AS 19.30.121

AS 19.40.065

AS 35.05.020

AS 35.10.210

AS 35.10.230

AS 44.42.020

AS 44.42.030

Disclaimer: These regulations may not be the most recent version. Alaska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.