11 AAC 93.173 - Certificates of approval
Current through February 24, 2025
(a) The department will issue a certificate of approval if it determines that the action for which approval is sought may be conducted without unreasonable risk to life or property, and for a certificate of approval
(b) The department will deny a certificate of approval if the owner fails to submit a complete application under 11 AAC 93.167, 11 AAC 93.171, or 11 AAC 93.172, or the department determines that the proposed construction, modification, repair, operation, removal, or abandonment of the dam would present an unreasonable risk to life or property.
(c) After the issuance of a certificate of approval for construction, repair, modification, removal, or abandonment of a dam, the owner may begin the construction, repair, modification, removal, or abandonment. During the construction, repair, modification, removal, or abandonment, and until it is completed,
(d) Water may not be impounded behind a newly constructed dam, and additional water may not be impounded behind a repaired or modified dam, until the department issues, under (a) of this section, a certificate of approval to operate a dam.
(e) A certificate of approval is valid only for the period of time specified in the certificate. An action allowed under the certificate may not continue beyond the certificate's expiration date.
(f) The department will extend the expiration date of a certificate of approval to operate a dam by up to 90 days if the
(g) In order to renew a certificate of approval to operate a dam, the owner must submit the following information to the department before the expiration date of the certificate of approval:
(h) The department will renew a certificate of approval to operate a dam if the department determines that the action for which approval is sought may be conducted without unreasonable risk to life or property, and after reviewing the information and documents submitted under (g) of this section.
(i) As the department considers necessary to protect life and property, the department will specify terms and conditions for a certificate of approval, including
(j) An owner may not assign or otherwise transfer a certificate of approval issued under 11 AAC 93.167, 11 AAC 93.171, or this section. To request that the department transfer a certificate of approval issued under 11 AAC 93.167, 11 AAC 93.171, or this section, the transferor and the transferee must submit a joint application on a form provided by the department and pay the applicable fees provided in 11 AAC 05.260(c)(3). The department may approve the transfer and issue a new certificate of approval including any terms and conditions that the department determines are necessary to ensure that the dam will be operated and maintained in a safe manner.
(k) department may revoke a certificate of approval for construction, modification, repair, removal, or abandonment of a dam or a certificate of approval to operate a dam if
Authority:AS 38.05.035
AS 46.17.010
AS 46.17.030
AS 46.17.040
AS 46.17.050
AS 46.17.060
AS 46.17.070