Alabama Administrative Code
Title 400 - STATE OIL AND GAS BOARD OF ALABAMA
GOVERNING COALBED METHANE GAS OPERATIONS
Chapter 400-3-4 - DRILLING
Section 400-3-4-.14 - Plugging And Abandonment Of Wells
Current through Register Vol. 43, No. 02, November 27, 2024
Any nonproductive well shall be plugged within thirty (30) days of completion unless said well has been classified as temporarily abandoned or shut in pursuant to Rule 400-3-4-.17. Any productive well that has not produced in six (6) months or any Class II injection well that has ceased operation for six (6) months shall be plugged within thirty (30) days unless said well has been classified as temporarily abandoned or shut in pursuant to Rule 400-3-4-.17. Before any work is commenced to plug and abandon any well drilled in search of oil and gas or utilized as a Class II injection well the operator shall provide the Supervisor with the proposed method and procedure to plug and abandon such well. Such method and procedure may be required in writing by the Supervisor. Also, the Supervisor may require that well records, including logs, be made available to determine if the proposed depths and lengths of plugs are adequate. Operations to plug and abandon a well shall not begin until approval of procedures has been obtained from the Supervisor. Unless otherwise allowed by the Supervisor, the operator shall notify the Supervisor at least twenty-four (24) hours prior to the commencement of plugging operations so that said operation may be witnessed by an agent of the Board. The cement in all plugs shall be standard cement and shall be mixed with water of adequate quality so as not to degrade the setting properties. Unless specified otherwise by the Supervisor, the operator shall comply with the following requirements which apply to all wells drilled in search of coalbed methane gas or utilized as Class II injection wells.
(1) Open Hole Completions.
(2) Cased Hole Completions.
(3) When the base of fresh water is penetrated, a cement, concrete, or grout plug at least two hundred (200) feet in length shall be placed at least fifty (50) feet below and shall extend to at least one hundred fifty (150) feet above the base of fresh water. A cement, concrete, or grout plug may be required in the casing-borehole annulus if fresh water is not adequately protected by casing and cement, concrete, or grout.
(4) A cement, concrete, or grout plug at least twenty-five (25) feet in length shall be placed inside the smallest string of casing and in all annular spaces near the surface of the ground in each hole plugged, and casing(s) cut in such a manner so as not to interfere with soil cultivation, and a steel plate at least one-quarter (1/4) inch in thickness shall be welded to the casing stub(s).
(5) The Supervisor may require verification of plugs by tagging and pressure testing.
(6) The interval between plugs shall be filled with an approved fluid.
(7) Other plugging methods and procedures may be required by the Supervisor.
(8) Restoration of location shall be done in accordance with Rule 400-3-4-.16.
Author: State Oil and Gas Board
Statutory Authority: Code of Ala. 1975, §§ 9-17-1, et seq.