Department of the Army, Corps of Engineers March 31, 2006 – Federal Register Recent Federal Regulation Documents

Intent To Prepare a Draft Supplement to the Environmental Impact Statement To Evaluate Construction of Authorized Improvements to the Federal Gulfport Harbor Navigation Project in Harrison County, MS
Document Number: 06-3146
Type: Notice
Date: 2006-03-31
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The Mobile District, U.S. Army Corps of Engineers (Corps), intends to prepare a Draft Supplement to the Environmental Impact Statement (DSEIS) to address the potential impacts associated with construction of authorized improvements to the Federal Gulfport Harbor Navigation Project in Harrison County, MS. The DSEIS will be used as a basis for ensuring compliance with the National Environmental Policy Act (NEPA) and evaluating the following two alternative plans: ``No Action'' and widening to the authorized project dimensions. Gulfport Harbor is authorized to (a) A channel 38 feet deep by 400 feet wide and about 8 miles long across Ship Island Bar; (b) a channel 36 feet deep by 300 feet wide and about 12 miles long through Mississippi Sound; and (c) a stepped anchorage basin at Gulfport Harbor 32 to 36 feet deep by 1,120 feet wide and 2,640 feet long.
Availability of a Draft Environmental Impact Statement To Consider Issuance of a Department of the Army Permit Pursuant to Section 404 of the Clean Water Act for Mingo Logan Coal Company's (Mingo Logan) Proposal To Construct and Operate Spruce No. 1 Mine, Near Blair in Logan County, WV
Document Number: 06-3144
Type: Notice
Date: 2006-03-31
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
In accordance with the requirements of the National Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers (USACE) Huntington District, in cooperation with U.S. Environmental Protection Agency, the U.S. Fish and Wildlife Service, the Office of Surface Mining and the West Virginia Department of Environmental Protection, has prepared a Draft Environmental Impact Statement (DEIS). This DEIS evaluates potential impacts to the natural, physical and human environment as a result of the proposed mining activities associated with Mingo Logan Coal Company's (Mingo Logan) Spruce No. 1 Mine. The USACE regulates this proposed project pursuant to Section 404 of the Clean Water Act. The proposed activity would involve the discharge of dredged and fill material into waters of the United States associated with the proosed construction and operation of a surface bituminous coal mine.
Notice of Intent To Prepare a Joint Environmental Impact Statement/Environmental Impact Report for the Proposed BNSF Cajon Subdivision Third Main Track Project Keenbrook to Summit, San Bernardino County, CA
Document Number: 06-3143
Type: Notice
Date: 2006-03-31
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
The Los Angeles District intends to prepare a joint Environmental Impact Statement/Environmental Impact Report (EIS/EIR) to analyze the environmental effects of, and support the permit decision related to, the proposed construction of a third main track through a 15.9 mile section of the Cajon Subdivision, between Keenbrook (the southerly entrance to Cajon Pass) and Summit. The third track would be constructed on either the east or the west side of the existing tracks, depending on constraints at any given location, and would parallel the western/northern track alignment (Main Track 1), between Cajon and Summit. The purpose of the EIS/EIR is to evaluate alternative approaches to increase sustainable daily capacity of train movement along the portion of the mainline through Cajon Pass to meet demand for freight movement for the present and the future. The benefits of the additional third main track include increasing operational flexibility, increasing operational efficiency, reducing severe congestion during peak travel periods, and allowing for sufficiently frequent movements of trains and goods through the Cajon Pass. Alternatives include the addition of a third main track adjacent to the existing BNSF Main 1 through Cajon Pass with the installation of retaining walls and improvements to culverts and wildlife linkages; construction of a third main track within the existing BNSF right-of-way without environmentally sensitive design features; and the No Action/No Federal Action Alternative. The EIS/EIR will analyze the potential direct, indirect and cumulative impacts of the environmental range of alternatives, including the proposed project.
Intent To Prepare a Draft Environmental Impact Statement for Elliott Bay Seawall, WA
Document Number: 06-3140
Type: Notice
Date: 2006-03-31
Agency: Department of Defense, Department of the Army, Corps of Engineers, Engineers Corps, Army Department
Pursuant to section 102(2)(C) of the National Environmental Policy Act (NEPA) of 1969, as amended, the U.S. Army Corps of Engineers (Corps) will prepare an environmental impact statement (EIS) for a proposed seawall rehabilitation project along the Elliott Bay shoreline in Seattle, WA. The seawall, known as the Alaskan Way Seawall, is experiencing significant decay and deterioration, leading to structural instability along the Seattle waterfront and central business district. Seawall structural instability is putting a tremendous amount of public and private infrastructure, development, and transportation linkages at risk of damage due to wave and tidal erosion, and hence potential for undermining and collapse. In addition, the failure of the seawall would result in a high risk to public safety and substantial environmental degradation. The purpose of the proposed rehabilitation effort is to protect the public facilities and economic activities along the Elliott Bay shoreline from storm damages associated with failure of the existing seawall.