Western Area Power Administration October 2007 – Federal Register Recent Federal Regulation Documents

Big Stone II Power Plant and Transmission Project Supplemental Draft Environmental Impact Statement (DOE/EIS-0377)
Document Number: E7-21088
Type: Notice
Date: 2007-10-26
Agency: Department of Energy, Western Area Power Administration
Western Area Power Administration (Western) announces the availability of the Supplemental Draft Big Stone II Power Plant and Transmission Project (Project) Environmental Impact Statement (Supplemental Draft EIS) for public review and comment. The U.S. Department of Agriculture Rural Utilities Service (RUS) and U.S. Department of Defense, U.S. Army Corps of Engineers (USACE), are participating as cooperating agencies in the EIS process. The Supplemental Draft EIS addresses the environmental impacts of a different back-up water supply plan that uses groundwater instead of surface water along with associated cooling alternatives for the proposed Big Stone II power plant's back-up water supply. The National Environmental Policy Act (NEPA) requires Western to make the Supplemental Draft EIS available to interested members of the public, groups, and Federal, State, local, and tribal agencies for review and comment to assure they have an opportunity to provide input to the Federal decision making process. Comments on the Supplemental Draft EIS may be provided in writing or at the hearing scheduled during the review period.
San Luis Rio Colorado Project (DOE/EIS-0395)
Document Number: E7-20179
Type: Notice
Date: 2007-10-12
Agency: Department of Energy, Western Area Power Administration
The Department of Energy (DOE) received applications from North Branch Resources, LLC (NBR) and Generadora del Desierto, S.A. de C.V. (GDD) to construct the proposed San Luis Rio Colorado Project in Yuma County, Arizona. NBR and GDD (collectively termed the Applicants) are each wholly owned subsidiaries of North Branch Holding, LLC. GDD applied to Office of Electricity Delivery and Energy Reliability (OE), an organizational unit within DOE, for a Presidential permit to construct, connect, operate, and maintain a double-circuit 500,000-volt (500-kilovolt [kV]) electric transmission line across the United States-Mexico international border. NBR submitted a request to Western Area Power Administration (Western), another organizational unit within DOE, to interconnect the double-circuit 500-kV electric transmission line to Western's existing Gila Substation. The Applicants proposed that Western construct, own, operate, and maintain the transmission components within the United States at the Applicants' expense. Western's decision is to allow the Applicants to interconnect with its transmission system at Gila Substation, and to construct the Agency Preferred Alternative upon completion of Western's Large Generator Interconnection Procedures (LGIP) process. Accordingly, Western intends to enter into interconnection and construction agreements with NBR, and to construct, own, operate, and maintain the transmission system additions in the United States that would allow the interconnection.
Pacific Northwest-Pacific Southwest Intertie Project-Rate Order No. WAPA-130
Document Number: E7-19914
Type: Notice
Date: 2007-10-10
Agency: Department of Energy, Western Area Power Administration
The Deputy Secretary of Energy confirmed and approved Rate Order No. WAPA-130 and Rate Schedules INT-FT4 and INT-NFT3, placing firm and nonfirm transmission service rates for the Pacific Northwest- Pacific Southwest Intertie Project (Intertie) of the Western Area Power Administration (Western) into effect on an interim basis. The provisional rates will be in effect until the Federal Energy Regulatory Commission (FERC) confirms, approves, and places them into effect on a final basis, or until they are replaced by other rates. The provisional rates will provide sufficient revenue to pay all annual costs, including interest expense, and repay required investment within the allowable periods.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.