Granby Pumping Plant-Windy Gap Transmission Line Rebuild Project, Grand County, CO
The Western Area Power Administration (Western), U.S. Department of Energy (DOE), intends to prepare an Environmental Impact Statement (EIS) for rebuilding the Granby Pumping Plant-Windy Gap transmission line in Grand County, Colorado. The U.S. Forest Service (USFS) will participate in the preparation of the EIS, which will address the proposed removal of about 12 miles of 69-kilovolt (kV) transmission line, the construction and operation of about 12 miles of new 138-kV double-circuit transmission line (operated at 69/138-kV), and adding a second power transformer. Input for the scope of the EIS may be provided in writing or at an open-house scoping meeting in the project area.