B.F. Sisk Dam Corrective Action Project, Merced County, CA
Document Number: E9-21723
Type: Notice
Date: 2009-09-09
Agency: Department of the Interior, Bureau of Reclamation, Reclamation Bureau
The Bureau of Reclamation (Reclamation), as the lead federal agency, and the State of California Department of Water Resources (DWR), as the lead state agency, are preparing a joint EIS/EIR, pursuant to the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA), respectively, for the B.F. Sisk Dam Corrective Action Project (proposed action). The purpose of the proposed action is to improve public safety by modifying B.F. Sisk Dam to mitigate potential safety concerns identified in the ongoing Corrective Action Study (CAS). Engineering and economic studies are currently being conducted by Reclamation and DWR to determine
Reach 4B, Eastside Bypass and Mariposa Bypass Low Flow Channel and Structural Improvements Project Under the San Joaquin River Restoration Program, Merced County, California
Document Number: E9-21717
Type: Notice
Date: 2009-09-09
Agency: Department of the Interior, Bureau of Reclamation, Reclamation Bureau
The Bureau of Reclamation and the California Department of Water Resources (DWR) are proposing to prepare a joint EIS/EIR, pursuant to the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA), to evaluate effects of the proposed Reach 4B, Eastside Bypass and Mariposa Bypass Low Flow Channel and Structural Improvements Project (Proposed Action) under the San Joaquin River Restoration Program (SJRRP or Program). The Proposed Action includes the construction, operation, and maintenance of a low flow channel in Reach 4B of the San Joaquin River and in the Eastside and Mariposa bypasses and improvements to facilities in the Eastside and Mariposa bypasses to allow for fish passage. The purpose of the Proposed Action is to comply with the San Joaquin River Settlement by improving conveyance capacity in Reach 4B of the San Joaquin River to ensure conveyance of at least 475 cubic feet per second (cfs), modifying the Eastside and Mariposa bypass channels to establish a low flow channel, and modifying structures in the Eastside and Mariposa bypasses to provide for fish passage. The Proposed Action is a component of the San Joaquin River Settlement.