Nuclear Regulatory Commission January 12, 2023 – Federal Register Recent Federal Regulation Documents

Southern California Edison; San Onofre Nuclear Generating Station, Unit Nos. 1, 2 and 3
Document Number: 2023-00428
Type: Notice
Date: 2023-01-12
Agency: Nuclear Regulatory Commission, Agencies and Commissions
The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption in response to a December 16, 2021, request from Southern California Edison, as supplemented on February 28 and September 29, 2022, that would allow the licensee to establish the Controlled Area Boundary (CAB) for the San Onofre Nuclear Generating Station (SONGS) independent spent fuel storage installation (ISFSI) at a distance less than 100 meters from the ISFSI as required by NRC regulation.