UP Property 2, LLC, Unique Places, LLC; Notice of Transfer of Exemption, 24398 [2025-10494]

Download as PDF 24398 Federal Register / Vol. 90, No. 110 / Tuesday, June 10, 2025 / Notices of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, community organization, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ferc.gov. Dated: June 4, 2025. Carlos D. Clay, Deputy Secretary. [FR Doc. 2025–10482 Filed 6–9–25; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER22–2466–000; ER22–2466– 001] ddrumheller on DSK120RN23PROD with NOTICES1 Cube Yadkin Transmission LLC; Notice of Motion To Withdraw Compliance Filing and Motion for Extension of Time To Comply On May 30, 2025, Cube Yadkin Transmission LLC (Cube Yadkin), filed a motion to withdraw its November 12, 2024 filing to comply with Order Nos. 881 and 881–A 1 and a motion for extension of time to comply with Order Nos. 881 and 881–A until July 12, 2027. Cube Yadkin states that the current effective date for compliance, July 12, 2025, does not provide Cube Yadkin with adequate time to develop and update processes, procedures and software to implement the requirements of Order No. 881 on Cube Yadkin’s 1 Managing Transmission Line Ratings, Order No. 881, 177 FERC ¶ 61,179 (2021), order addressing arguments raised on reh’g, Order No. 881–A, 179 FERC ¶ 61,125 (2022). VerDate Sep<11>2014 17:53 Jun 09, 2025 Jkt 265001 limited and discrete facilities. According to Cube Yadkin, the requested extension will provide Cube Yadkin with ‘‘time to develop and implement processes tailored for the Yadkin Transmission Facilities that comply with Order No. 881 and to train [Cube Yadkin’s] personnel to ensure continued operational reliability of the Yadkin Transmission Facilities.’’ 2 Answers to the motion must be filed by 5:00 p.m. Eastern Time on June 9, 2025. Dated: June 4, 2025. Debbie-Anne A. Reese, Secretary. [FR Doc. 2025–10493 Filed 6–9–25; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 7987–016] UP Property 2, LLC, Unique Places, LLC; Notice of Transfer of Exemption 1. By letter filed May 8, 2025, Jeff Fischer, Manager, UP Property 2, LLC, exemptee informed the Commission that the exemption from licensing for the High Falls Hydroelectric Project No. 7987, originally issued September 12, 1984 1 has been transferred to Unique Places, LLC. The project is located on the Deep River in Moore County, North Carolina. The transfer of an exemption does not require Commission approval. Unique Places, LLC is now the exemptee of the High Falls Hydroelectric Project No. 7987. All correspondence should be forwarded to: Mr. Jeffrey A. Fisher, Manager, Unique Places, LLC, 5014 Hollow Rock Road, Durham, NC 27707, Phone: 919–632– 0161, Email: jeff@uniqueplacesllc.com. Dated: June 4, 2025. Debbie-Anne A. Reese, Secretary. [FR Doc. 2025–10494 Filed 6–9–25; 8:45 am] BILLING CODE 6717–01–P 2 Cube Yadkin May 30, 2025 Motion to Withdraw Compliance Filing and Motion for Extension to Comply at 4. 1 Order Granting Exemption from Licensing of a Small Hydroelectric Project of 5 Megawatts or Less. Cook Industries, Inc., 28 FERC ¶ 62,352 (1984). PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 15401–000] Molitor, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On April 28, 2025, GeoSense, LLC, on behalf of Molitor, LLC (the applicant), filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Molitor Hydroelectric Project (or Project) to be located on Deep Creek, tributary of the Snake River, in Twin falls County, Idaho. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) a 90-foot-long, 9.5 foot-high, 2-foot-wide concrete embankment; (2) a 0.5-acre impoundment with a normal surface elevation of approximately 3,310 feet above sea level; (3) a 3,500-foot-long concrete canal; (4) a 750-foot-long, 55inch-diamater buried steel penstock; (5) a 40-foot-long, 25-foot-wide concrete and steel powerhouse containing a 714 kilowatt horizontal-Francis turbinegenerator unit; (6) a 4,800-foot-long transmission line extending from powerhouse to the point of interconnection with Idaho Power facilities; and (7) appurtenant facilities. The estimated annual generation of the Project would be 4,376 megawatt-hours. Applicants Contact: Peter Josten, GeoSense, LLC, 2742 Saint Charles Ave., Idaho Falls, ID 83404, (208) 339– 3542, peter.gsense@gmail.com. FERC Contact: Maryam Zavareh at Maryam.zavareh@ferc.gov. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: by 5:00 p.m. Eastern Time on August 4, 2025. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. E:\FR\FM\10JNN1.SGM 10JNN1

Agencies

[Federal Register Volume 90, Number 110 (Tuesday, June 10, 2025)]
[Notices]
[Page 24398]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-10494]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 7987-016]


UP Property 2, LLC, Unique Places, LLC; Notice of Transfer of 
Exemption

    1. By letter filed May 8, 2025, Jeff Fischer, Manager, UP Property 
2, LLC, exemptee informed the Commission that the exemption from 
licensing for the High Falls Hydroelectric Project No. 7987, originally 
issued September 12, 1984 \1\ has been transferred to Unique Places, 
LLC. The project is located on the Deep River in Moore County, North 
Carolina. The transfer of an exemption does not require Commission 
approval.
---------------------------------------------------------------------------

    \1\ Order Granting Exemption from Licensing of a Small 
Hydroelectric Project of 5 Megawatts or Less. Cook Industries, Inc., 
28 FERC ] 62,352 (1984).
---------------------------------------------------------------------------

    Unique Places, LLC is now the exemptee of the High Falls 
Hydroelectric Project No. 7987. All correspondence should be forwarded 
to: Mr. Jeffrey A. Fisher, Manager, Unique Places, LLC, 5014 Hollow 
Rock Road, Durham, NC 27707, Phone: 919-632-0161, Email: 
[email protected].

    Dated: June 4, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-10494 Filed 6-9-25; 8:45 am]
BILLING CODE 6717-01-P