Cube Yadkin Transmission LLC; Notice of Motion To Withdraw Compliance Filing and Motion for Extension of Time To Comply, 24398 [2025-10493]
Download as PDF
24398
Federal Register / Vol. 90, No. 110 / Tuesday, June 10, 2025 / Notices
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, community organization,
Tribal members and others, access
publicly available information and
navigate Commission processes. For
public inquiries and assistance with
making filings such as interventions,
comments, or requests for rehearing, the
public is encouraged to contact OPP at
(202) 502–6595 or OPP@ferc.gov.
Dated: June 4, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025–10482 Filed 6–9–25; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER22–2466–000; ER22–2466–
001]
ddrumheller on DSK120RN23PROD with NOTICES1
Cube Yadkin Transmission LLC;
Notice of Motion To Withdraw
Compliance Filing and Motion for
Extension of Time To Comply
On May 30, 2025, Cube Yadkin
Transmission LLC (Cube Yadkin), filed
a motion to withdraw its November 12,
2024 filing to comply with Order Nos.
881 and 881–A 1 and a motion for
extension of time to comply with Order
Nos. 881 and 881–A until July 12, 2027.
Cube Yadkin states that the current
effective date for compliance, July 12,
2025, does not provide Cube Yadkin
with adequate time to develop and
update processes, procedures and
software to implement the requirements
of Order No. 881 on Cube Yadkin’s
1 Managing Transmission Line Ratings, Order No.
881, 177 FERC ¶ 61,179 (2021), order addressing
arguments raised on reh’g, Order No. 881–A, 179
FERC ¶ 61,125 (2022).
VerDate Sep<11>2014
17:53 Jun 09, 2025
Jkt 265001
limited and discrete facilities.
According to Cube Yadkin, the
requested extension will provide Cube
Yadkin with ‘‘time to develop and
implement processes tailored for the
Yadkin Transmission Facilities that
comply with Order No. 881 and to train
[Cube Yadkin’s] personnel to ensure
continued operational reliability of the
Yadkin Transmission Facilities.’’ 2
Answers to the motion must be filed
by 5:00 p.m. Eastern Time on June 9,
2025.
Dated: June 4, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025–10493 Filed 6–9–25; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7987–016]
UP Property 2, LLC, Unique Places,
LLC; Notice of Transfer of Exemption
1. By letter filed May 8, 2025, Jeff
Fischer, Manager, UP Property 2, LLC,
exemptee informed the Commission that
the exemption from licensing for the
High Falls Hydroelectric Project No.
7987, originally issued September 12,
1984 1 has been transferred to Unique
Places, LLC. The project is located on
the Deep River in Moore County, North
Carolina. The transfer of an exemption
does not require Commission approval.
Unique Places, LLC is now the
exemptee of the High Falls
Hydroelectric Project No. 7987. All
correspondence should be forwarded to:
Mr. Jeffrey A. Fisher, Manager, Unique
Places, LLC, 5014 Hollow Rock Road,
Durham, NC 27707, Phone: 919–632–
0161, Email: jeff@uniqueplacesllc.com.
Dated: June 4, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025–10494 Filed 6–9–25; 8:45 am]
BILLING CODE 6717–01–P
2 Cube Yadkin May 30, 2025 Motion to Withdraw
Compliance Filing and Motion for Extension to
Comply at 4.
1 Order Granting Exemption from Licensing of a
Small Hydroelectric Project of 5 Megawatts or Less.
Cook Industries, Inc., 28 FERC ¶ 62,352 (1984).
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15401–000]
Molitor, LLC; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On April 28, 2025, GeoSense, LLC, on
behalf of Molitor, LLC (the applicant),
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of the Molitor
Hydroelectric Project (or Project) to be
located on Deep Creek, tributary of the
Snake River, in Twin falls County,
Idaho. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) a 90-foot-long, 9.5
foot-high, 2-foot-wide concrete
embankment; (2) a 0.5-acre
impoundment with a normal surface
elevation of approximately 3,310 feet
above sea level; (3) a 3,500-foot-long
concrete canal; (4) a 750-foot-long, 55inch-diamater buried steel penstock; (5)
a 40-foot-long, 25-foot-wide concrete
and steel powerhouse containing a 714
kilowatt horizontal-Francis turbinegenerator unit; (6) a 4,800-foot-long
transmission line extending from
powerhouse to the point of
interconnection with Idaho Power
facilities; and (7) appurtenant facilities.
The estimated annual generation of the
Project would be 4,376 megawatt-hours.
Applicants Contact: Peter Josten,
GeoSense, LLC, 2742 Saint Charles
Ave., Idaho Falls, ID 83404, (208) 339–
3542, peter.gsense@gmail.com.
FERC Contact: Maryam Zavareh at
Maryam.zavareh@ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: by
5:00 p.m. Eastern Time on August 4,
2025. Competing applications and
notices of intent must meet the
requirements of 18 CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
E:\FR\FM\10JNN1.SGM
10JNN1
Agencies
[Federal Register Volume 90, Number 110 (Tuesday, June 10, 2025)]
[Notices]
[Page 24398]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-10493]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER22-2466-000; ER22-2466-001]
Cube Yadkin Transmission LLC; Notice of Motion To Withdraw
Compliance Filing and Motion for Extension of Time To Comply
On May 30, 2025, Cube Yadkin Transmission LLC (Cube Yadkin), filed
a motion to withdraw its November 12, 2024 filing to comply with Order
Nos. 881 and 881-A \1\ and a motion for extension of time to comply
with Order Nos. 881 and 881-A until July 12, 2027. Cube Yadkin states
that the current effective date for compliance, July 12, 2025, does not
provide Cube Yadkin with adequate time to develop and update processes,
procedures and software to implement the requirements of Order No. 881
on Cube Yadkin's limited and discrete facilities. According to Cube
Yadkin, the requested extension will provide Cube Yadkin with ``time to
develop and implement processes tailored for the Yadkin Transmission
Facilities that comply with Order No. 881 and to train [Cube Yadkin's]
personnel to ensure continued operational reliability of the Yadkin
Transmission Facilities.'' \2\
---------------------------------------------------------------------------
\1\ Managing Transmission Line Ratings, Order No. 881, 177 FERC
] 61,179 (2021), order addressing arguments raised on reh'g, Order
No. 881-A, 179 FERC ] 61,125 (2022).
\2\ Cube Yadkin May 30, 2025 Motion to Withdraw Compliance
Filing and Motion for Extension to Comply at 4.
---------------------------------------------------------------------------
Answers to the motion must be filed by 5:00 p.m. Eastern Time on
June 9, 2025.
Dated: June 4, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-10493 Filed 6-9-25; 8:45 am]