Constellation Energy Generation, LLC; Peach Bottom Atomic Power Station Units 2 and 3; Independent Spent Fuel Storage Installation; Exemption, 13503-13506 [2025-04921]
Download as PDF
Federal Register / Vol. 90, No. 55 / Monday, March 24, 2025 / Notices
Comments submitted in response to
this notice will be summarized in the
request for Office of Management and
Budget approval of the proposed
information collection request; they will
become a matter of public record and
will be available at https://
www.reginfo.gov.
(Authority: 44 U.S.C. 3506(c)(2)(A))
Anjanette Suggs,
Certifying Officer.
[FR Doc. 2025–04933 Filed 3–21–25; 8:45 am]
BILLING CODE 4510–CF–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 72–29, 50–277, and 50–278;
NRC–2025–0033]
Constellation Energy Generation, LLC;
Peach Bottom Atomic Power Station
Units 2 and 3; Independent Spent Fuel
Storage Installation; Exemption
Nuclear Regulatory
Commission.
ACTION: Notice; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) issued an exemption
to Constellation Energy Generation,
LLC, permitting Peach Bottom Atomic
Power Station (PB) Units 2 and 3 to use
the Holtec HI–STORM Flood/Wind
(FW) Multi-Purpose Canister (MPC)
Storage System, including the use of the
HI–TRAC VW transfer cask during
loading and transport operations, at the
PB independent spent fuel storage
installation, for seven 89 multi-purpose
canisters, in a near-term loading
campaign beginning in June 2025,
where the terms, conditions, and
specifications in Certificate of
Compliance No. 1032, Amendment No.
1, Revision No. 1, are not met.
DATES: The exemption was issued on
March 6, 2025.
ADDRESSES: Please refer to Docket ID
NRC–2025–0033 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2025–0033. Address
questions about Docket IDs in
Regulations.gov to Bridget Curran;
telephone: 301–415–1003; email:
Bridget.Curran@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
lotter on DSK11XQN23PROD with NOTICES1
SUMMARY:
VerDate Sep<11>2014
17:28 Mar 21, 2025
Jkt 265001
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, at
301–415–4737, or by email to
PDR.Resource@nrc.gov. The ADAMS
accession number for each document
referenced (if it is available in ADAMS)
is provided the first time that it is
mentioned in this document.
• NRC’s PDR: The PDR, where you
may examine and order copies of
publicly available documents, is open
by appointment. To make an
appointment to visit the PDR, please
send an email to PDR.Resource@nrc.gov
or call 1–800–397–4209 or 301–415–
4737, between 8 a.m. and 4 p.m. eastern
time (ET), Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: YenJu Chen, Office of Nuclear Material
Safety and Safeguards, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555; telephone: 301–415–1018;
email: Yen-Ju.Chen@nrc.gov.
SUPPLEMENTARY INFORMATION: The text of
the exemption is attached.
Dated: March 19, 2025.
For the Nuclear Regulatory Commission.
Yoira Diaz-Sanabria,
Chief, Storage and Transportation Licensing
Branch, Division of Fuel Management, Office
of Nuclear Material Safety, and Safeguards.
Attachment—Exemption
Nuclear Regulatory Commission
Docket Nos. 72–29, 50–277, and 50–278
Constellation Energy Generation, LLC;
Peach Bottom Atomic Power Station
Units 2 and 3; Independent Spent Fuel
Storage Installation
I. Background
Constellation Energy Generation, LLC
(CEG) is the holder of renewed facility
operating license Nos. DPR–44 and
DPR–56, which authorize operation of
the Peach Bottom Atomic Power Station
(PB) Units 2 and 3 in Delta,
Pennsylvania, under Title 10 of the
Code of Federal Regulations (10 CFR)
Part 50, ‘‘Domestic Licensing of
Production and Utilization Facilities.’’
The licenses provide, among other
things, that the facility is subject to all
rules, regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC)
now or hereafter in effect.
Consistent with 10 CFR part 72,
subpart K, ‘‘General License for Storage
of Spent Fuel at Power Reactor Sites,’’
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
13503
a general license is issued for the storage
of spent fuel in an independent spent
fuel storage installation (ISFSI) at power
reactor sites to persons authorized to
possess or operate nuclear power
reactors under 10 CFR part 50. CEG is
authorized to operate nuclear power
reactors under 10 CFR part 50 and holds
a 10 CFR part 72 general license for
storage of spent fuel at the PB ISFSI.
Under the terms of the general license,
CEG stores spent fuel at its PB ISFSI
using the HI–STORM Flood/Wind (FW)
Multi-Purpose Canister (MPC) Storage
System in accordance with Certificate of
Compliance (CoC) No. 1032,
Amendment No. 1, Revision No. 1.
II. Request/Action
By a letter dated January 24, 2025
(Agencywide Documents Access and
Management System (ADAMS)
Accession Number No. ML25024A148),
as supplemented on February 4, 2025
(ML25036A335), CEG requested an
exemption from the requirements of 10
CFR 72.212(a)(2), 72.212(b)(3),
72.212(b)(5)(i), 72.212(b)(11), and
72.214 that require PB to comply with
the terms, conditions, and specifications
of CoC No. 1032, Amendment No. 1,
Revision No. 1 (ML15152A358). If
approved, CEG’s exemption request
would accordingly allow PB to load
seven MPC–89 at the PB ISFSI site in a
near-term loading campaign beginning
in June 2025, in the HI–STORM FW
MPC system, including the use of the
HI–TRAC VW transfer cask (HI–TRAC)
during loading and transport operations,
where the terms, conditions, and
specifications in CoC No. 1032,
Amendment No. 1, Revision No. 1 are
not met.
Before using a CoC, general licensees
are required to perform a site-specific
evaluation to establish that, once loaded
with spent fuel, the cask will conform
to the terms, conditions, and
specifications of the CoC, including
following the NRC-approved final safety
analysis report (FSAR) methodology.
CEG currently uses the HI–STORM FW
MPC Storage System under CoC No.
1032, Amendment No. 1, Revision No.
1, for dry storage of spent nuclear fuel
in MPC–89 at the PB ISFSI. The HI–
STORM FW MPC Storage System CoC
provides the requirements, conditions,
and operating limits necessary for use of
the system to store spent fuel. One of
the operating limits established in the
CoC involves potential tornadogenerated missile impacts. The HI–
STORM FW FSAR table 2.2.5 evaluates
a generic set of tornado-generated
missile impacts (ML24327A229). CEG
discovered that PB’s site-specific
analysis performed to demonstrate
E:\FR\FM\24MRN1.SGM
24MRN1
13504
Federal Register / Vol. 90, No. 55 / Monday, March 24, 2025 / Notices
protection of the loaded MPC–89, while
in the HI–TRAC, against tornadogenerated missiles was not performed
consistent with the NRC-approved
method of evaluation in the FSAR.
Contrary to CEG’s site specific analysis,
the NRC-approved evaluation in the
FSAR does not take credit for the
missile resistance offered by the HI–
TRAC water jacket shell, and assumes
that the small and intermediate missiles
will penetrate the water jacket shell
with no energy loss.
Therefore, CEG requests this
exemption to allow it to conduct the
planned loading and transport
operations of the seven MPC–89 in the
HI–STORM FW MPC Storage System at
PB ISFSI beginning in June 2025, even
though, because of the different tornadogenerated missile analysis of the HI–
TRAC in PB’s site specific review, the
terms, conditions, and specifications of
the CoC will not be met.
III. Discussion
Pursuant to 10 CFR 72.7, ‘‘Specific
exemptions,’’ the Commission may,
upon application by any interested
person or upon its own initiative, grant
such exemptions from the requirements
of the regulations of 10 CFR part 72 as
it determines are authorized by law and
will not endanger life or property or the
common defense and security and are
otherwise in the public interest.
lotter on DSK11XQN23PROD with NOTICES1
A. The Exemption Is Authorized by Law
This exemption would allow CEG to
use the HI–STORM FW MPC Storage
System, including the use of the HI–
TRAC during loading and transport
operations, for seven MPC–89 at its PB
ISFSI, beginning in June 2025, where
the terms, conditions, and specifications
in CoC No. 1032, Amendment No. 1,
Revision No. 1, are not met. CEG is
requesting an exemption from the
provisions in 10 CFR part 72 that
require the licensee to comply with the
terms, conditions, and specifications of
the CoC for the approved cask model it
uses. Section 72.7 allows the NRC to
grant exemptions from the requirements
of 10 CFR part 72. This authority to
grant exemptions is consistent with the
Atomic Energy Act of 1954, as amended,
and is not otherwise inconsistent with
the NRC’s regulations or other
applicable laws. Additionally, no other
law prohibits the activities that would
be authorized by the exemption.
Therefore, the NRC concludes that there
is no statutory prohibition on the
issuance of the requested exemption,
and the NRC is authorized to grant the
exemption by law.
VerDate Sep<11>2014
17:28 Mar 21, 2025
Jkt 265001
B. The Exemption Will Not Endanger
Life or Property or the Common Defense
and Security
CEG is requesting an exemption to use
the HI–STORM FW MPC Storage
System, including the use of the HI–
TRAC during loading and transport
operations for seven MPC–89 at the PB
ISFSI, beginning in June 2025, where
the terms, conditions, and specifications
in CoC No. 1032, Amendment No. 1,
Revision No. 1, are not met. In support
of its exemption request, CEG asserts
that issuance of the exemption would
not endanger life or property because
the evaluation of PB’s postulated
tornado-generated missiles
demonstrates that all FSAR acceptance
criteria are met. According to CEG, the
site-specific analysis follows the same
mathematical approach as the generic
approach in the FSAR but takes credit
for the additional resistance provided by
the HI–TRAC water jacket shell.
Additionally, CEG notes that the water
jacket shell is an Important-to-Safety
(ITS) component and meets all the
criteria as analyzed. Therefore, CEG
contends the site-specific analysis,
although different from the FSAR
methodology, demonstrates that the
loading and transport operations of the
system using the HI–TRAC provides
adequate protection against PB’s design
basis tornado-generated missiles. As
such, according to CEG, the proposed
exemption does not endanger life or
property or the common defense and
security.
The NRC staff reviewed the requested
exemption and determined that the
request does not change the
fundamental design, components, or
safety features of the storage system.
The NRC staff evaluated the applicable
potential safety impacts of granting the
exemption to assess the potential for
any danger to life or property or the
common defense and security.
Specifically, the NRC staff reviewed the
applicant’s structural, confinement,
thermal, criticality, shielding, and
radiation protection evaluations for the
proposed exemption.
Structural and Confinement Review
for the Requested Exemption: The staff
noted that this exemption does not
involve any change to the physical
design or construction of the HI–
STORM FW overpack, HI–TRAC, or
MPC–89, nor to any operating
procedures. Instead, the exemption is to
allow the use of the CoC system despite
the different methodology used by PB
regarding the tornado-generated missile
impact analysis than that approved by
the NRC and reflected in the CoC FSAR.
Therefore, the staff’s structural review
PO 00000
Frm 00056
Fmt 4703
Sfmt 4703
focused on the analysis and
methodology followed to demonstrate
that the design of the MPC–89 and the
HI–TRAC can withstand the governing
PB site-specific tornado-generated
missile impact without impairing their
capability to perform their intended
functions. The MPC and the HI–TRAC
are deemed to perform their intended
design functions if the following
performance objectives, as described in
HI–STORM FW FSAR section 3.1.2
(ML24327A229), can be satisfied:
(i) The postulated tornado generated
missiles do not compromise the
integrity of the MPC confinement
boundary while the MPC is contained
within the HI–TRAC.
(ii) No geometry changes occur under
the postulated tornado-generated
missiles impact during handling
conditions that may preclude ready
retrievability of the contained MPC.
(iii) The radiation shielding remains
properly positioned under all applicable
handling service conditions for the HI–
TRAC.
In general, the above performance
objectives are deemed to be satisfied for
the MPC and the HI–TRAC if (1) the
missile does not penetrate the inner
shell of the HI–TRAC, MPC or MPC lid,
and does not breach the confinement
boundary, (2) the stresses (stress
intensities or strains, as applicable)
calculated by the appropriate structural
analyses are less than the allowable
defined in FSAR subsection 3.1.2.3, and
(3) the geometry change in the HI–
TRAC, if any, after any event of
structural consequence to the transfer
cask, does not preclude ready
retrievability of the contained MPC.
The HI–TRAC body consists of two
main layers: a water jacket layer and a
lead shield layer. Each layer is
contained within different steel shells:
the water jacket shell (outermost shell of
HI–TRAC), the outer shell of the lead
shield layer (between the water jacket
layer and a lead shield layer), and the
inner shell (innermost shell of the lead
shield layer and the HI–TRAC). The
proprietary Holtec Report HI–2135869,
‘‘Site-Specific Tornado Missile Analysis
for HI–STORM FW System,’’ Revision
No. 9, generically addresses the HI–
TRAC structural responses due to
bounding site-specific small and
intermediate tornado-generated missile
strikes, except for the governing
tornado-generated missile for PB, which
is a 4-inch × 12-inch × 12-foot-long
wooden plank with an impact velocity
of 300 miles per hour (mph). In support
of this exemption request, Holtec’s ‘‘HI–
STORM FW Calculation Package to
Support Exemptions’’ (PB site-specific
analysis, ML25021A244) further
E:\FR\FM\24MRN1.SGM
24MRN1
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 90, No. 55 / Monday, March 24, 2025 / Notices
analyzed the governing site-specific
wooden plank missile using the same
energy balance approach and
assumptions relating to the missile
behavior and kinetic energy as other
evaluated tornado-generated missiles,
with the exception of the credit given in
the analysis for the resistance provided
by the HI–TRAC water jacket shell.
Based on this analysis, CEG concluded
that the HI–TRAC inner shell is not
penetrated and is sufficient to absorb
the remaining kinetic energy of the
wooden plank. Therefore, CEG
concludes that the site-specific
governing tornado-generated missile
does not penetrate the MPC–89
confinement boundary, and no
significant deformation of the HI–TRAC
is expected that would prevent the
MPC–89 from being retrieved or
maintaining shielding effectiveness.
The staff reviewed the sizes, mass,
and velocities of the site-specific
tornado-generated missiles analyzed in
the PB site-specific analysis and verified
that the analyzed tornado-generated
missiles bound the design basis tornadogenerated missile spectrum specified in
section C.2.4 of the PB updated final
safety analysis report, Appendix C
(ML23173A057). The staff’s
independent analysis of the missile
penetration by the wooden plank
concluded that a greater margin of safety
is available for the inner shell
penetration than the one calculated in
the PB site-specific analysis.
Furthermore, based on the review of the
PB site-specific analysis, the staff finds
that the missile penetration depth by the
wooden plank in the MPC lid remains
less than the minimum thickness of the
MPC closure lid. Additionally, the
calculated global stress intensities for
the HI–TRAC shell due to the missile
strike satisfy American Society of
Mechanical Engineers, Boiler and
Pressure Vessel Code, Section III,
Division 1, Subsection NF, Level D
limits, as specified in the HI–STORM
FW FSAR section 3.1.2.3. Therefore, in
the event of a tornado-generated missile
impact from the wooden plank
analyzed, damage to the cask or canister
that compromise confinement
boundary, global plastic deformation in
the cask shell, or ovaling of the cask
inner cavity, is not anticipated, and will
not affect the overall shielding
effectiveness of the cask and the
retrievability of the MPC. The staff also
noted that the analysis results are
conservative since they assume that the
wooden plank is rigid, and no kinetic
energy dissipation is being credited due
to deformation of the wooden plank
VerDate Sep<11>2014
17:28 Mar 21, 2025
Jkt 265001
when it strikes the HI–TRAC at high
velocity.
Based on the staff’s review of the
analysis provided for the exemption
request, the staff finds the proposed
methodology used for the PB sitespecific missile penetration analysis
acceptable and concludes that the sitespecific analysis demonstrates that the
MPC and HI–TRAC can withstand the
governing site-specific tornadogenerated missile impact without
compromising their ability to perform
their intended safety functions at PB.
Thermal Review for the Requested
Exemption: The thermal consequences
of a complete loss of water due to
rupture of the HI–TRAC water jacket
from a tornado-generated missile has
been analyzed in FSAR sections 4.6 and
12.2.6.2 (ML24327A229). It
demonstrates that the consequences are
within the short-term fuel cladding and
material temperature limits. The revised
analysis with credit for the HI–TRAC
water jacket shell demonstrates that the
FSAR acceptance criteria continue to be
met, and a complete loss of water
continues to be bounding for thermal
evaluation. Therefore, no further
thermal evaluation is required to
support this exemption request.
Criticality and Shielding Review for
the Requested Exemption: A complete
loss of water due to rupture of the HI–
TRAC water jacket from a tornadogenerated missile has been analyzed for
shielding and no effect on criticality
control features as stated in FSAR
section 12.2.6.2 (ML24327A229). The
revised analysis with credit for the HI–
TRAC water jacket shell demonstrates
that the FSAR acceptance criteria
continue to be met, and a complete loss
of water continues to be bounding for
the shielding evaluation. Therefore, no
further criticality and shielding review
is required to support this exemption
request.
Radiation Protection Review for the
Requested Exemption: There is no
degradation in confinement capabilities
of the MPC when inside of the HI–
TRAC. The local dose rates of a
complete loss of water due to rupture of
the HI–TRAC water jacket from a
tornado-generated missile has been
analyzed in FSAR chapter 5
(ML24327A229). The revised analysis
with credit for the HI–TRAC water
jacket shell demonstrates that the FSAR
acceptance criteria continue to be met,
and a complete loss of water continues
to be bounding for radiation protection.
The necessary compensatory measures
continue to be valid. Therefore, no
further radiation protection review is
required to support this exemption
request.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
13505
Conclusion: Based on staff’s analysis
of the structural and confinement
review, and the otherwise bounding
nature of the FSAR’s analysis in other
areas, the NRC staff has concluded that
under the requested exemption, the
storage system will continue to meet the
safety requirements of 10 CFR part 72
and the offsite dose limits of 10 CFR
part 20 and, therefore, will not endanger
life or property or the common defense
and security.
C. The Exemption Is Otherwise in the
Public Interest
The proposed exemption would allow
CEG to use the HI–STORM FW MPC
Storage System, including the use of the
HI–TRAC solely during loading and
transport operations for seven MPC–89
at PB ISFSI, beginning in June 2025,
even though PB’s tornado-generated
missile analysis of HI–TRAC, which
takes credit for the water jacket shell, is
not part of the NRC-approved CoC No.
1032, Amendment No. 1, Revision No.
1. According to CEG, the exemption is
in the public interest because being
unable to load fuel into dry storage in
the future loading campaign would
impact CEG’s ability to offload fuel from
the PB reactor, consequently impacting
continued safe reactor operation.
CEG states that not being able to use
the HI–STORM FW MPC Storage
System, including the use of the HI–
TRAC during loading and transport
operations for seven MPC–89 at the PB
ISFSI in the June 2025 loading
campaign, would impact its ability to
effectively manage the margin to full
core discharge capacity (FCDC) in the
PB Units 2 and 3 spent fuel pools (SFP).
The low FCDC margin makes it difficult
to stage a complete reload batch of fuel
in the SFPs in preparation for outages
and presents a potential reactivity
management risk to fuel handling
operations during pre- and post-outage
activities. In addition, according to CEG,
a crowded spent fuel pool would
challenge the decay heat removal
demand of the pool and increase the
likelihood of a loss of fuel pool cooling
event and a fuel handling accident.
Furthermore, CEG contends that PB
planned the cask loading campaign
years in advance based on availability of
the specialized work force and
equipment that is shared throughout the
CEG fleet. These specialty resources
support competing activities and
priorities, including fuel pool cleanouts
and refueling outages. Therefore, CEG
asserts that the available windows to
complete the cask loading campaigns
are limited, and any delays would have
a cascading impact on other scheduled
specialized activities.
E:\FR\FM\24MRN1.SGM
24MRN1
lotter on DSK11XQN23PROD with NOTICES1
13506
Federal Register / Vol. 90, No. 55 / Monday, March 24, 2025 / Notices
For the reasons described by CEG in
the exemption request, the NRC staff
agree that it is in the public interest to
grant the exemption. If the exemption is
not granted, in order to comply with the
CoC, CEG would have to keep spent fuel
in the spent fuel pool if it is not
permitted to use the HI–TRAC during
loading and transport operations for
seven MPC–89 at the PB ISFSI for the
loading campaign beginning in June
2025, thus impacting PB’s ability to
effectively manage the FCDC margin.
Moreover, should spent fuel pool
capacity be reached, the ability to refuel
the operating reactor unit is challenged,
thus potentially impacting continued
reactor operations.
Therefore, the staff concludes that
approving the exemption is in the
public interest.
Acting Chief, Storage and Transportation
Licensing Branch, Division of Fuel
Management, Office of Nuclear Material
Safety, and Safeguards.
Environmental Consideration
The NRC staff also considered
whether there would be any significant
environmental impacts associated with
the exemption. For this proposed action,
the NRC staff performed an
environmental assessment pursuant to
10 CFR 51.30. The environmental
assessment concluded that the proposed
action would not significantly impact
the quality of the human environment.
The NRC staff concluded that the
proposed action would not result in any
changes in the types or amounts of any
radiological or non-radiological
effluents that may be released offsite,
and there would be no significant
increase in occupational or public
radiation exposure because of the
proposed action. The environmental
assessment and the finding of no
significant impact was published on
March 6, 2025 (90 FR 11440).
SUMMARY:
IV. Conclusion
Based on these considerations, the
NRC has determined that, pursuant to
10 CFR 72.7, the exemption is
authorized by law, will not endanger
life or property or the common defense
and security, and is otherwise in the
public interest. Therefore, the NRC
grants CEG an exemption from the
requirements of 10 CFR 72.212(a)(2),
72.212(b)(3), 72.212(b)(5)(i),
72.212(b)(11), and 72.214 solely with
respect to the planned loading and
transport operations for seven MPC–89
at PB ISFSI for the loading campaign
beginning in June 2025.
This exemption is effective upon
issuance.
Table of Contents
Dated: March 6, 2025.
For the Nuclear Regulatory Commission.
/RA/
Thomas Boyce,
VerDate Sep<11>2014
17:28 Mar 21, 2025
Jkt 265001
[FR Doc. 2025–04921 Filed 3–21–25; 8:45 am]
BILLING CODE 7590–01–P
POSTAL REGULATORY COMMISSION
[Docket Nos. MC2025–1234 and K2025–
1233; MC2025–1235 and K2025–1234;
MC2025–1236 and K2025–1235; MC2025–
1237 and K2025–1236; MC2025–1238 and
K2025–1237; MC2025–1239 and K2025–
1238; MC2025–1240 and K2025–1239]
New Postal Products
Postal Regulatory Commission.
Notice.
AGENCY:
ACTION:
The Commission is noticing a
recent Postal Service filing for the
Commission’s consideration concerning
a negotiated service agreement. This
notice informs the public of the filing,
invites public comment, and takes other
administrative steps.
DATES: Comments are due: March 26,
2025.
Submit comments
electronically via the Commission’s
Filing Online system at https://
www.prc.gov. Those who cannot submit
comments electronically should contact
the person identified in the FOR FURTHER
INFORMATION CONTACT section by
telephone for advice on filing
alternatives.
ADDRESSES:
FOR FURTHER INFORMATION CONTACT:
David A. Trissell, General Counsel, at
202–789–6820.
SUPPLEMENTARY INFORMATION:
I. Introduction
II. Public Proceeding(s)
III. Summary Proceeding(s)
I. Introduction
Pursuant to 39 CFR 3041.405, the
Commission gives notice that the Postal
Service filed request(s) for the
Commission to consider matters related
to Competitive negotiated service
agreement(s). The request(s) may
propose the addition of a negotiated
service agreement from the Competitive
product list or the modification of an
existing product currently appearing on
the Competitive product list.
The public portions of the Postal
Service’s request(s) can be accessed via
the Commission’s website (https://
www.prc.gov). Non-public portions of
the Postal Service’s request(s), if any,
can be accessed through compliance
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
with the requirements of 39 CFR
3011.301.1
Section II identifies the docket
number(s) associated with each Postal
Service request, if any, that will be
reviewed in a public proceeding as
defined by 39 CFR 3010.101(p), the title
of each such request, the request’s
acceptance date, and the authority cited
by the Postal Service for each request.
For each such request, the Commission
appoints an officer of the Commission to
represent the interests of the general
public in the proceeding, pursuant to 39
U.S.C. 505 and 39 CFR 3000.114 (Public
Representative). Section II also
establishes comment deadline(s)
pertaining to each such request.
The Commission invites comments on
whether the Postal Service’s request(s)
identified in Section II, if any, are
consistent with the policies of title 39.
Applicable statutory and regulatory
requirements include 39 U.S.C. 3632, 39
U.S.C. 3633, 39 U.S.C. 3642, 39 CFR
part 3035, and 39 CFR part 3041.
Comment deadline(s) for each such
request, if any, appear in Section II.
Section III identifies the docket
number(s) associated with each Postal
Service request, if any, to add a
standardized distinct product to the
Competitive product list or to amend a
standardized distinct product, the title
of each such request, the request’s
acceptance date, and the authority cited
by the Postal Service for each request.
Standardized distinct products are
negotiated service agreements that are
variations of one or more Competitive
products, and for which financial
models, minimum rates, and
classification criteria have undergone
advance Commission review. See 39
CFR 3041.110(n); 39 CFR 3041.205(a).
Such requests are reviewed in summary
proceedings pursuant to 39 CFR
3041.325(c)(2) and 39 CFR
3041.505(f)(1). Pursuant to 39 CFR
3041.405(c)–(d), the Commission does
not appoint a Public Representative or
request public comment in proceedings
to review such requests.
II. Public Proceeding(s)
1. Docket No(s).: Docket No(s).:
MC2025–1234 and K2025–1233; Filing
Title: USPS Request to Add Priority
Mail & USPS Ground Advantage
Contract 650 to the Competitive Product
List and Notice of Filing Materials
Under Seal; Filing Acceptance Date:
March 18, 2025; Filing Authority: 39
U.S.C. 3642, 39 CFR 3035.105, and 39
1 See Docket No. RM2018–3, Order Adopting
Final Rules Relating to Non-Public Information,
June 27, 2018, Attachment A at 19–22 (Order No.
4679).
E:\FR\FM\24MRN1.SGM
24MRN1
Agencies
[Federal Register Volume 90, Number 55 (Monday, March 24, 2025)]
[Notices]
[Pages 13503-13506]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-04921]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 72-29, 50-277, and 50-278; NRC-2025-0033]
Constellation Energy Generation, LLC; Peach Bottom Atomic Power
Station Units 2 and 3; Independent Spent Fuel Storage Installation;
Exemption
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) issued an
exemption to Constellation Energy Generation, LLC, permitting Peach
Bottom Atomic Power Station (PB) Units 2 and 3 to use the Holtec HI-
STORM Flood/Wind (FW) Multi-Purpose Canister (MPC) Storage System,
including the use of the HI-TRAC VW transfer cask during loading and
transport operations, at the PB independent spent fuel storage
installation, for seven 89 multi-purpose canisters, in a near-term
loading campaign beginning in June 2025, where the terms, conditions,
and specifications in Certificate of Compliance No. 1032, Amendment No.
1, Revision No. 1, are not met.
DATES: The exemption was issued on March 6, 2025.
ADDRESSES: Please refer to Docket ID NRC-2025-0033 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-0033. Address
questions about Docket IDs in Regulations.gov to Bridget Curran;
telephone: 301-415-1003; email: [email protected]. For technical
questions, contact the individual listed in the For Further Information
Contact section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737,
or by email to [email protected]. The ADAMS accession number for
each document referenced (if it is available in ADAMS) is provided the
first time that it is mentioned in this document.
NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
Federal holidays.
FOR FURTHER INFORMATION CONTACT: Yen-Ju Chen, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555; telephone: 301-415-1018; email: [email protected].
SUPPLEMENTARY INFORMATION: The text of the exemption is attached.
Dated: March 19, 2025.
For the Nuclear Regulatory Commission.
Yoira Diaz-Sanabria,
Chief, Storage and Transportation Licensing Branch, Division of Fuel
Management, Office of Nuclear Material Safety, and Safeguards.
Attachment--Exemption
Nuclear Regulatory Commission
Docket Nos. 72-29, 50-277, and 50-278
Constellation Energy Generation, LLC; Peach Bottom Atomic Power Station
Units 2 and 3; Independent Spent Fuel Storage Installation
I. Background
Constellation Energy Generation, LLC (CEG) is the holder of renewed
facility operating license Nos. DPR-44 and DPR-56, which authorize
operation of the Peach Bottom Atomic Power Station (PB) Units 2 and 3
in Delta, Pennsylvania, under Title 10 of the Code of Federal
Regulations (10 CFR) Part 50, ``Domestic Licensing of Production and
Utilization Facilities.'' The licenses provide, among other things,
that the facility is subject to all rules, regulations, and orders of
the U.S. Nuclear Regulatory Commission (NRC) now or hereafter in
effect.
Consistent with 10 CFR part 72, subpart K, ``General License for
Storage of Spent Fuel at Power Reactor Sites,'' a general license is
issued for the storage of spent fuel in an independent spent fuel
storage installation (ISFSI) at power reactor sites to persons
authorized to possess or operate nuclear power reactors under 10 CFR
part 50. CEG is authorized to operate nuclear power reactors under 10
CFR part 50 and holds a 10 CFR part 72 general license for storage of
spent fuel at the PB ISFSI. Under the terms of the general license, CEG
stores spent fuel at its PB ISFSI using the HI-STORM Flood/Wind (FW)
Multi-Purpose Canister (MPC) Storage System in accordance with
Certificate of Compliance (CoC) No. 1032, Amendment No. 1, Revision No.
1.
II. Request/Action
By a letter dated January 24, 2025 (Agencywide Documents Access and
Management System (ADAMS) Accession Number No. ML25024A148), as
supplemented on February 4, 2025 (ML25036A335), CEG requested an
exemption from the requirements of 10 CFR 72.212(a)(2), 72.212(b)(3),
72.212(b)(5)(i), 72.212(b)(11), and 72.214 that require PB to comply
with the terms, conditions, and specifications of CoC No. 1032,
Amendment No. 1, Revision No. 1 (ML15152A358). If approved, CEG's
exemption request would accordingly allow PB to load seven MPC-89 at
the PB ISFSI site in a near-term loading campaign beginning in June
2025, in the HI-STORM FW MPC system, including the use of the HI-TRAC
VW transfer cask (HI-TRAC) during loading and transport operations,
where the terms, conditions, and specifications in CoC No. 1032,
Amendment No. 1, Revision No. 1 are not met.
Before using a CoC, general licensees are required to perform a
site-specific evaluation to establish that, once loaded with spent
fuel, the cask will conform to the terms, conditions, and
specifications of the CoC, including following the NRC-approved final
safety analysis report (FSAR) methodology. CEG currently uses the HI-
STORM FW MPC Storage System under CoC No. 1032, Amendment No. 1,
Revision No. 1, for dry storage of spent nuclear fuel in MPC-89 at the
PB ISFSI. The HI-STORM FW MPC Storage System CoC provides the
requirements, conditions, and operating limits necessary for use of the
system to store spent fuel. One of the operating limits established in
the CoC involves potential tornado-generated missile impacts. The HI-
STORM FW FSAR table 2.2.5 evaluates a generic set of tornado-generated
missile impacts (ML24327A229). CEG discovered that PB's site-specific
analysis performed to demonstrate
[[Page 13504]]
protection of the loaded MPC-89, while in the HI-TRAC, against tornado-
generated missiles was not performed consistent with the NRC-approved
method of evaluation in the FSAR. Contrary to CEG's site specific
analysis, the NRC-approved evaluation in the FSAR does not take credit
for the missile resistance offered by the HI-TRAC water jacket shell,
and assumes that the small and intermediate missiles will penetrate the
water jacket shell with no energy loss.
Therefore, CEG requests this exemption to allow it to conduct the
planned loading and transport operations of the seven MPC-89 in the HI-
STORM FW MPC Storage System at PB ISFSI beginning in June 2025, even
though, because of the different tornado-generated missile analysis of
the HI-TRAC in PB's site specific review, the terms, conditions, and
specifications of the CoC will not be met.
III. Discussion
Pursuant to 10 CFR 72.7, ``Specific exemptions,'' the Commission
may, upon application by any interested person or upon its own
initiative, grant such exemptions from the requirements of the
regulations of 10 CFR part 72 as it determines are authorized by law
and will not endanger life or property or the common defense and
security and are otherwise in the public interest.
A. The Exemption Is Authorized by Law
This exemption would allow CEG to use the HI-STORM FW MPC Storage
System, including the use of the HI-TRAC during loading and transport
operations, for seven MPC-89 at its PB ISFSI, beginning in June 2025,
where the terms, conditions, and specifications in CoC No. 1032,
Amendment No. 1, Revision No. 1, are not met. CEG is requesting an
exemption from the provisions in 10 CFR part 72 that require the
licensee to comply with the terms, conditions, and specifications of
the CoC for the approved cask model it uses. Section 72.7 allows the
NRC to grant exemptions from the requirements of 10 CFR part 72. This
authority to grant exemptions is consistent with the Atomic Energy Act
of 1954, as amended, and is not otherwise inconsistent with the NRC's
regulations or other applicable laws. Additionally, no other law
prohibits the activities that would be authorized by the exemption.
Therefore, the NRC concludes that there is no statutory prohibition on
the issuance of the requested exemption, and the NRC is authorized to
grant the exemption by law.
B. The Exemption Will Not Endanger Life or Property or the Common
Defense and Security
CEG is requesting an exemption to use the HI-STORM FW MPC Storage
System, including the use of the HI-TRAC during loading and transport
operations for seven MPC-89 at the PB ISFSI, beginning in June 2025,
where the terms, conditions, and specifications in CoC No. 1032,
Amendment No. 1, Revision No. 1, are not met. In support of its
exemption request, CEG asserts that issuance of the exemption would not
endanger life or property because the evaluation of PB's postulated
tornado-generated missiles demonstrates that all FSAR acceptance
criteria are met. According to CEG, the site-specific analysis follows
the same mathematical approach as the generic approach in the FSAR but
takes credit for the additional resistance provided by the HI-TRAC
water jacket shell. Additionally, CEG notes that the water jacket shell
is an Important-to-Safety (ITS) component and meets all the criteria as
analyzed. Therefore, CEG contends the site-specific analysis, although
different from the FSAR methodology, demonstrates that the loading and
transport operations of the system using the HI-TRAC provides adequate
protection against PB's design basis tornado-generated missiles. As
such, according to CEG, the proposed exemption does not endanger life
or property or the common defense and security.
The NRC staff reviewed the requested exemption and determined that
the request does not change the fundamental design, components, or
safety features of the storage system. The NRC staff evaluated the
applicable potential safety impacts of granting the exemption to assess
the potential for any danger to life or property or the common defense
and security. Specifically, the NRC staff reviewed the applicant's
structural, confinement, thermal, criticality, shielding, and radiation
protection evaluations for the proposed exemption.
Structural and Confinement Review for the Requested Exemption: The
staff noted that this exemption does not involve any change to the
physical design or construction of the HI-STORM FW overpack, HI-TRAC,
or MPC-89, nor to any operating procedures. Instead, the exemption is
to allow the use of the CoC system despite the different methodology
used by PB regarding the tornado-generated missile impact analysis than
that approved by the NRC and reflected in the CoC FSAR. Therefore, the
staff's structural review focused on the analysis and methodology
followed to demonstrate that the design of the MPC-89 and the HI-TRAC
can withstand the governing PB site-specific tornado-generated missile
impact without impairing their capability to perform their intended
functions. The MPC and the HI-TRAC are deemed to perform their intended
design functions if the following performance objectives, as described
in HI-STORM FW FSAR section 3.1.2 (ML24327A229), can be satisfied:
(i) The postulated tornado generated missiles do not compromise the
integrity of the MPC confinement boundary while the MPC is contained
within the HI-TRAC.
(ii) No geometry changes occur under the postulated tornado-
generated missiles impact during handling conditions that may preclude
ready retrievability of the contained MPC.
(iii) The radiation shielding remains properly positioned under all
applicable handling service conditions for the HI-TRAC.
In general, the above performance objectives are deemed to be
satisfied for the MPC and the HI-TRAC if (1) the missile does not
penetrate the inner shell of the HI-TRAC, MPC or MPC lid, and does not
breach the confinement boundary, (2) the stresses (stress intensities
or strains, as applicable) calculated by the appropriate structural
analyses are less than the allowable defined in FSAR subsection
3.1.2.3, and (3) the geometry change in the HI-TRAC, if any, after any
event of structural consequence to the transfer cask, does not preclude
ready retrievability of the contained MPC.
The HI-TRAC body consists of two main layers: a water jacket layer
and a lead shield layer. Each layer is contained within different steel
shells: the water jacket shell (outermost shell of HI-TRAC), the outer
shell of the lead shield layer (between the water jacket layer and a
lead shield layer), and the inner shell (innermost shell of the lead
shield layer and the HI-TRAC). The proprietary Holtec Report HI-
2135869, ``Site-Specific Tornado Missile Analysis for HI-STORM FW
System,'' Revision No. 9, generically addresses the HI-TRAC structural
responses due to bounding site-specific small and intermediate tornado-
generated missile strikes, except for the governing tornado-generated
missile for PB, which is a 4-inch x 12-inch x 12-foot-long wooden plank
with an impact velocity of 300 miles per hour (mph). In support of this
exemption request, Holtec's ``HI-STORM FW Calculation Package to
Support Exemptions'' (PB site-specific analysis, ML25021A244) further
[[Page 13505]]
analyzed the governing site-specific wooden plank missile using the
same energy balance approach and assumptions relating to the missile
behavior and kinetic energy as other evaluated tornado-generated
missiles, with the exception of the credit given in the analysis for
the resistance provided by the HI-TRAC water jacket shell. Based on
this analysis, CEG concluded that the HI-TRAC inner shell is not
penetrated and is sufficient to absorb the remaining kinetic energy of
the wooden plank. Therefore, CEG concludes that the site-specific
governing tornado-generated missile does not penetrate the MPC-89
confinement boundary, and no significant deformation of the HI-TRAC is
expected that would prevent the MPC-89 from being retrieved or
maintaining shielding effectiveness.
The staff reviewed the sizes, mass, and velocities of the site-
specific tornado-generated missiles analyzed in the PB site-specific
analysis and verified that the analyzed tornado-generated missiles
bound the design basis tornado-generated missile spectrum specified in
section C.2.4 of the PB updated final safety analysis report, Appendix
C (ML23173A057). The staff's independent analysis of the missile
penetration by the wooden plank concluded that a greater margin of
safety is available for the inner shell penetration than the one
calculated in the PB site-specific analysis. Furthermore, based on the
review of the PB site-specific analysis, the staff finds that the
missile penetration depth by the wooden plank in the MPC lid remains
less than the minimum thickness of the MPC closure lid. Additionally,
the calculated global stress intensities for the HI-TRAC shell due to
the missile strike satisfy American Society of Mechanical Engineers,
Boiler and Pressure Vessel Code, Section III, Division 1, Subsection
NF, Level D limits, as specified in the HI-STORM FW FSAR section
3.1.2.3. Therefore, in the event of a tornado-generated missile impact
from the wooden plank analyzed, damage to the cask or canister that
compromise confinement boundary, global plastic deformation in the cask
shell, or ovaling of the cask inner cavity, is not anticipated, and
will not affect the overall shielding effectiveness of the cask and the
retrievability of the MPC. The staff also noted that the analysis
results are conservative since they assume that the wooden plank is
rigid, and no kinetic energy dissipation is being credited due to
deformation of the wooden plank when it strikes the HI-TRAC at high
velocity.
Based on the staff's review of the analysis provided for the
exemption request, the staff finds the proposed methodology used for
the PB site-specific missile penetration analysis acceptable and
concludes that the site-specific analysis demonstrates that the MPC and
HI-TRAC can withstand the governing site-specific tornado-generated
missile impact without compromising their ability to perform their
intended safety functions at PB.
Thermal Review for the Requested Exemption: The thermal
consequences of a complete loss of water due to rupture of the HI-TRAC
water jacket from a tornado-generated missile has been analyzed in FSAR
sections 4.6 and 12.2.6.2 (ML24327A229). It demonstrates that the
consequences are within the short-term fuel cladding and material
temperature limits. The revised analysis with credit for the HI-TRAC
water jacket shell demonstrates that the FSAR acceptance criteria
continue to be met, and a complete loss of water continues to be
bounding for thermal evaluation. Therefore, no further thermal
evaluation is required to support this exemption request.
Criticality and Shielding Review for the Requested Exemption: A
complete loss of water due to rupture of the HI-TRAC water jacket from
a tornado-generated missile has been analyzed for shielding and no
effect on criticality control features as stated in FSAR section
12.2.6.2 (ML24327A229). The revised analysis with credit for the HI-
TRAC water jacket shell demonstrates that the FSAR acceptance criteria
continue to be met, and a complete loss of water continues to be
bounding for the shielding evaluation. Therefore, no further
criticality and shielding review is required to support this exemption
request.
Radiation Protection Review for the Requested Exemption: There is
no degradation in confinement capabilities of the MPC when inside of
the HI-TRAC. The local dose rates of a complete loss of water due to
rupture of the HI-TRAC water jacket from a tornado-generated missile
has been analyzed in FSAR chapter 5 (ML24327A229). The revised analysis
with credit for the HI-TRAC water jacket shell demonstrates that the
FSAR acceptance criteria continue to be met, and a complete loss of
water continues to be bounding for radiation protection. The necessary
compensatory measures continue to be valid. Therefore, no further
radiation protection review is required to support this exemption
request.
Conclusion: Based on staff's analysis of the structural and
confinement review, and the otherwise bounding nature of the FSAR's
analysis in other areas, the NRC staff has concluded that under the
requested exemption, the storage system will continue to meet the
safety requirements of 10 CFR part 72 and the offsite dose limits of 10
CFR part 20 and, therefore, will not endanger life or property or the
common defense and security.
C. The Exemption Is Otherwise in the Public Interest
The proposed exemption would allow CEG to use the HI-STORM FW MPC
Storage System, including the use of the HI-TRAC solely during loading
and transport operations for seven MPC-89 at PB ISFSI, beginning in
June 2025, even though PB's tornado-generated missile analysis of HI-
TRAC, which takes credit for the water jacket shell, is not part of the
NRC-approved CoC No. 1032, Amendment No. 1, Revision No. 1. According
to CEG, the exemption is in the public interest because being unable to
load fuel into dry storage in the future loading campaign would impact
CEG's ability to offload fuel from the PB reactor, consequently
impacting continued safe reactor operation.
CEG states that not being able to use the HI-STORM FW MPC Storage
System, including the use of the HI-TRAC during loading and transport
operations for seven MPC-89 at the PB ISFSI in the June 2025 loading
campaign, would impact its ability to effectively manage the margin to
full core discharge capacity (FCDC) in the PB Units 2 and 3 spent fuel
pools (SFP). The low FCDC margin makes it difficult to stage a complete
reload batch of fuel in the SFPs in preparation for outages and
presents a potential reactivity management risk to fuel handling
operations during pre- and post-outage activities. In addition,
according to CEG, a crowded spent fuel pool would challenge the decay
heat removal demand of the pool and increase the likelihood of a loss
of fuel pool cooling event and a fuel handling accident. Furthermore,
CEG contends that PB planned the cask loading campaign years in advance
based on availability of the specialized work force and equipment that
is shared throughout the CEG fleet. These specialty resources support
competing activities and priorities, including fuel pool cleanouts and
refueling outages. Therefore, CEG asserts that the available windows to
complete the cask loading campaigns are limited, and any delays would
have a cascading impact on other scheduled specialized activities.
[[Page 13506]]
For the reasons described by CEG in the exemption request, the NRC
staff agree that it is in the public interest to grant the exemption.
If the exemption is not granted, in order to comply with the CoC, CEG
would have to keep spent fuel in the spent fuel pool if it is not
permitted to use the HI-TRAC during loading and transport operations
for seven MPC-89 at the PB ISFSI for the loading campaign beginning in
June 2025, thus impacting PB's ability to effectively manage the FCDC
margin. Moreover, should spent fuel pool capacity be reached, the
ability to refuel the operating reactor unit is challenged, thus
potentially impacting continued reactor operations.
Therefore, the staff concludes that approving the exemption is in
the public interest.
Environmental Consideration
The NRC staff also considered whether there would be any
significant environmental impacts associated with the exemption. For
this proposed action, the NRC staff performed an environmental
assessment pursuant to 10 CFR 51.30. The environmental assessment
concluded that the proposed action would not significantly impact the
quality of the human environment. The NRC staff concluded that the
proposed action would not result in any changes in the types or amounts
of any radiological or non-radiological effluents that may be released
offsite, and there would be no significant increase in occupational or
public radiation exposure because of the proposed action. The
environmental assessment and the finding of no significant impact was
published on March 6, 2025 (90 FR 11440).
IV. Conclusion
Based on these considerations, the NRC has determined that,
pursuant to 10 CFR 72.7, the exemption is authorized by law, will not
endanger life or property or the common defense and security, and is
otherwise in the public interest. Therefore, the NRC grants CEG an
exemption from the requirements of 10 CFR 72.212(a)(2), 72.212(b)(3),
72.212(b)(5)(i), 72.212(b)(11), and 72.214 solely with respect to the
planned loading and transport operations for seven MPC-89 at PB ISFSI
for the loading campaign beginning in June 2025.
This exemption is effective upon issuance.
Dated: March 6, 2025.
For the Nuclear Regulatory Commission.
/RA/
Thomas Boyce,
Acting Chief, Storage and Transportation Licensing Branch, Division
of Fuel Management, Office of Nuclear Material Safety, and
Safeguards.
[FR Doc. 2025-04921 Filed 3-21-25; 8:45 am]
BILLING CODE 7590-01-P