Briar Hydro Associates; Notice of Authorization for Continued Project Operation, 106464 [2024-31071]

Download as PDF 106464 Federal Register / Vol. 89, No. 249 / Monday, December 30, 2024 / Notices ddrumheller on DSK120RN23PROD with NOTICES1 Description: 284.123(g) Rate Filing: BHKG Revised SOC and Statement of Rates to be effective 11/1/2024. Filed Date: 12/18/24. Accession Number: 20241218–5267. Comment Date: 5 p.m. ET 1/8/25. 284.123(g) Protest: 5 p.m. ET 2/17/25. Docket Numbers: RP25–291–000. Applicants: Iroquois Gas Transmission System, L.P. Description: 4(d) Rate Filing: 12.18.24 Negotiated Rates—Mercury Energy America, LLC H–7540–89 to be effective 12/18/2024. Filed Date: 12/18/24. Accession Number: 20241218–5232. Comment Date: 5 p.m. ET 12/30/24. Docket Numbers: RP25–292–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: 4(d) Rate Filing: Negotiated Rate Agreement Update (NRG Feb 2025) to be effective 2/1/2025. Filed Date: 12/18/24. Accession Number: 20241218–5240. Comment Date: 5 p.m. ET 12/30/24. Docket Numbers: RP25–293–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: 4(d) Rate Filing: Negotiated Rate Agreement Update (Shell Feb 2025) to be effective 2/1/ 2025. Filed Date: 12/19/24. Accession Number: 20241219–5131. Comment Date: 5 p.m. ET 12/31/24. Docket Numbers: RP25–294–000. Applicants: Midcontinent Express Pipeline LLC. Description: 4(d) Rate Filing: MEP December 2024 NRA Filing to be effective 1/1/2025. Filed Date: 12/19/24. Accession Number: 20241219–5180. Comment Date: 5 p.m. ET 12/31/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Filings in Existing Proceedings Docket Numbers: PR25–16–001. Applicants: Black Hills Energy Arkansas, Inc. Description: 284.123(g) Rate Filing: BHEA Amended SOC Filing to be effective 10/14/2024. Filed Date: 12/19/24. Accession Number: 20241219–5151. Comment Date: 5 p.m. ET 1/9/25. Any person desiring to protest in any the above proceedings must file in VerDate Sep<11>2014 23:58 Dec 27, 2024 Jkt 265001 accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: December 19, 2024. Carlos D. Clay, Acting Deputy Secretary. [FR Doc. 2024–31070 Filed 12–27–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3240–000] Briar Hydro Associates; Notice of Authorization for Continued Project Operation The license for the Rolfe Canal Hydroelectric Project No. 3240 was issued for a period ending November 30, 2024. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the PO 00000 Frm 00059 Fmt 4703 Sfmt 4703 licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 3240 is issued to Briar Hydro Associates for a period effective December 1, 2024, through November 30, 2025, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before November 30, 2025, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Briar Hydro Associates is authorized to continue operation of the Rolfe Canal Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. Dated: December 19, 2024. Carlos D. Clay, Acting Deputy Secretary. [FR Doc. 2024–31071 Filed 12–27–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AC25–38–000] Western Power Pool; Notice of Filing Take notice that on December 13, 2024, Northwest Power Pool d/b/a Western Power Pool (WPP) submitted a request for waiver of the Federal Energy Regulatory Commission’s (Commission) requirement to file a certified public accountant (CPA) certification on a calendar-year basis and for extensions of time to file certain CPA certifications. Any person desiring to intervene or to protest this filing must file in E:\FR\FM\30DEN1.SGM 30DEN1

Agencies

[Federal Register Volume 89, Number 249 (Monday, December 30, 2024)]
[Notices]
[Page 106464]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-31071]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3240-000]


Briar Hydro Associates; Notice of Authorization for Continued 
Project Operation

    The license for the Rolfe Canal Hydroelectric Project No. 3240 was 
issued for a period ending November 30, 2024.
    Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the 
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and 
conditions of the prior license until a new license is issued, or the 
project is otherwise disposed of as provided in section 15 or any other 
applicable section of the FPA. If the project's prior license waived 
the applicability of section 15 of the FPA, then, based on section 9(b) 
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth 
at 18 CFR 16.21(a), if the licensee of such project has filed an 
application for a subsequent license, the licensee may continue to 
operate the project in accordance with the terms and conditions of the 
license after the minor or minor part license expires, until the 
Commission acts on its application. If the licensee of such a project 
has not filed an application for a subsequent license, then it may be 
required, pursuant to 18 CFR 16.21(b), to continue project operations 
until the Commission issues someone else a license for the project or 
otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 3240 is issued to 
Briar Hydro Associates for a period effective December 1, 2024, through 
November 30, 2025, or until the issuance of a new license for the 
project or other disposition under the FPA, whichever comes first.
    If issuance of a new license (or other disposition) does not take 
place on or before November 30, 2025, notice is hereby given that, 
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) 
of the FPA is renewed automatically without further order or notice by 
the Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Briar Hydro Associates is authorized to continue 
operation of the Rolfe Canal Hydroelectric Project under the terms and 
conditions of the prior license until the issuance of a subsequent 
license for the project or other disposition under the FPA, whichever 
comes first.

    Dated: December 19, 2024.
Carlos D. Clay,
Acting Deputy Secretary.
[FR Doc. 2024-31071 Filed 12-27-24; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.