Application for Renewal of Authorization To Export Electric Energy; Calpine Energy Solutions, LLC, 103806-103807 [2024-30221]

Download as PDF 103806 Federal Register / Vol. 89, No. 244 / Thursday, December 19, 2024 / Notices Public Participation: The in-person/ online virtual hybrid meeting is open to the public in person or virtually, via WebEx. Written statements may be filed with the Board no later than 5 p.m. MST on Friday, January 24, 2025, or within seven days after the meeting by sending them to the NNMCAB Executive Director at the aforementioned email address. Written public comments received prior to the meeting will be read into the record. The Deputy Designated Federal Officer is empowered to conduct the meeting in a fashion that will facilitate the orderly conduct of business. Individuals wishing to submit public comments should follow as directed above. Minutes: Minutes will be available by emailing or calling Bridget Maestas, NNMCAB Executive Director, at bridget.maestas@em.doe.gov or at (505) 709–7466. Signing Authority: This document of the Department of Energy was signed on December 13, 2024, by Alyssa Petit, Deputy Committee Management Officer, pursuant to delegated authority from the Secretary of Energy. That document with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. Signed in Washington, DC on December 13, 2024. Jennifer Hartzell, Alternate Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–30062 Filed 12–18–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY [GDO Docket No. EA–284–G] Application for Renewal of Authorization To Export Electric Energy; Calpine Energy Solutions, LLC Grid Deployment Office, Department of Energy. ACTION: Notice of application. lotter on DSK11XQN23PROD with NOTICES1 AGENCY: Calpine Energy Solutions, LLC (the Applicant or Calpine Solutions) has applied for the renewal of authorization to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act. SUMMARY: VerDate Sep<11>2014 18:08 Dec 18, 2024 Jkt 265001 Comments, protests, or motions to intervene must be submitted on or before January 21, 2025. ADDRESSES: Comments, protests, motions to intervene, or requests for more information should be addressed by electronic mail to Electricity.Exports@hq.doe.gov. FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474–8226, Electricity.Exports@hq.doe.gov. SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) regulates electricity exports from the United States to foreign countries in accordance with section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, previously exercised by the nowdefunct Federal Power Commission, to DOE. Section 202(e) of the FPA provides that an entity which seeks to export electricity must obtain an order from DOE authorizing that export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue such orders was delegated to the DOE’s Grid Deployment Office (GDO) under Redelegation Order No. S3–DEL–GD1–2023. On November 22, 2024, Calpine Solutions filed an application for the renewal of authorization to transmit electric energy from the United States to Mexico for a term of five years. App. at 1. According to the Application, Calpine Solutions is ‘‘a California limited liability company with its principal place of business at 401 West A Street, Suite 400, San Diego, California, and is an indirect, wholly owned subsidiary of Calpine Corporation.’’ Id. The Applicant represents that its wholesale sales ‘‘are made pursuant to authority granted by the Federal Energy Regulatory Commission (‘‘FERC’’) to sell wholesale power at market-based rates under a wholesale power sales tariff currently on file with FERC.’’ Id. at 1–2. The Applicant states it ‘‘does not own or control electric generation, transmission, cogeneration facilities, or distribution facilities, nor does [it] have a franchised service area.’’ App. at 5. Calpine Solutions states that any electric energy it exports ‘‘on either a firm or interruptible basis, will be surplus to the system of the generator thereof.’’ Id. Thus, the Applicant states that ‘‘its exports cannot have any adverse impact on the reliability, stability, or sufficiency of supply on a franchise electric supply system or the DATES: PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 electric power supply within the U.S.’’ Id. at 5–6. Further, regarding the second criterion used to analyze applications to export electricity, Calpine Solutions states it ‘‘will comply with existing industry procedures for obtaining transmission capacity’’ and ‘‘will comply with any other export limits that DOE may deem appropriate, consistent with DOE’s orders authorizing exports of electric energy by power marketers.’’ App. at 6–7. The existing international transmission facilities to be utilized by the Applicant have been previously authorized by Presidential permits issued pursuant to Executive Order 10485, as amended, and are appropriate for open access transmission by third parties. See App. at Exhibit C. Procedural Matters: Any person desiring to be heard in this proceeding should file a comment or protest to the Application at Electricity.Exports@ hq.doe.gov. Protests should be filed in accordance with Rule 211 of FERC’s Rules of Practice and Procedure (18 CFR 385.211). Any person desiring to become a party to this proceeding should file a motion to intervene at Electricity.Exports@hq.doe.gov in accordance with FERC Rule 214 (18 CFR 385.214). Comments and other filings concerning Calpine Solutions’ Application should be clearly marked with GDO Docket No. EA–284–G. Additional copies are to be provided directly to Rachael Marsh, Calpine Corporation, 875 15th Street NW, Suite 700, Washington, DC 20005, rachel.marsh@calpine.com, and Greg Bass, Calpine Energy Solutions, LLC, 401 West A Street, Suite 500, San Diego, CA 92101, greg.bass@calpine.com. A final decision will be made on the requested authorization after the environmental impacts have been evaluated pursuant to DOE’s National Environmental Policy Act Implementing Procedures (10 CFR part 1021) and after DOE evaluates whether the proposed action will have an adverse impact on the sufficiency of supply or reliability of the United States electric power supply system. Copies of this Application will be made available, upon request, by accessing the program website at https://www.energy.gov/gdo/pendingapplications-0 or by emailing Electricity.Exports@hq.doe.gov. Signing Authority: This document of the Department of Energy was signed on December 13, 2024, by Maria Robinson, Director, Grid Deployment Office, pursuant to delegated authority from the Secretary of Energy. That document E:\FR\FM\19DEN1.SGM 19DEN1 Federal Register / Vol. 89, No. 244 / Thursday, December 19, 2024 / Notices with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. Signed in Washington, DC, on December 16, 2024. Treena V. Garrett, Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–30221 Filed 12–18–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission lotter on DSK11XQN23PROD with NOTICES1 Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER22–1697–003. Applicants: Southwest Power Pool, Inc. Description: Compliance filing: Order No. 2222 Compliance Filing in Response to March 2024 Order to be effective 12/31/9998. Filed Date: 12/13/24. Accession Number: 20241213–5144. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER24–2037–001. Applicants: Tucson Electric Power Company. Description: Compliance filing: Order Nos. 2023 and 2023–A Second Compliance Filing to be effective 8/15/ 2024. Filed Date: 12/13/24. Accession Number: 20241213–5068. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–699–000. Applicants: Arizona Public Service Company. Description: § 205(d) Rate Filing: Service Agreement No. 429—E&P Agreement w/RWE to be effective 11/ 12/2024. Filed Date: 12/12/24. Accession Number: 20241212–5228. Comment Date: 5 p.m. ET 1/2/25. Docket Numbers: ER25–700–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4268R1 Blue Valley Grid GIA to be effective 12/3/2024. VerDate Sep<11>2014 18:08 Dec 18, 2024 Jkt 265001 Filed Date: 12/13/24. Accession Number: 20241213–5023. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–701–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original NSA, Service Agreement No. 7432; AF1–140 to be effective 2/12/ 2025. Filed Date: 12/13/24. Accession Number: 20241213–5034. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–702–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to WMPA, Service Agreement No. 6082; Queue No. AF1– 039 to be effective 2/12/2025. Filed Date: 12/13/24. Accession Number: 20241213–5043. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–703–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 1628R27 Western Farmers Electric Cooperative NITSA NOAs to be effective 12/1/2024. Filed Date: 12/13/24. Accession Number: 20241213–5050. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–704–000. Applicants: Amite Solar, LLC. Description: § 205(d) Rate Filing: Application for MBR Authorization to be effective 2/12/2025. Filed Date: 12/13/24. Accession Number: 20241213–5102. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–705–000. Applicants: Green River Solar, LLC. Description: § 205(d) Rate Filing: Application for MBR Authorization to be effective 2/12/2025. Filed Date: 12/13/24. Accession Number: 20241213–5104. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–706–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original GIA Service Agreement No. 7433; Project Identifier No. AF2–306 to be effective 11/15/2024. Filed Date: 12/13/24. Accession Number: 20241213–5108. Comment Date: 5 p.m. ET 1/3/25. Docket Numbers: ER25–707–000. Applicants: Taunton Municipal Lighting Plant Hudson Light & Power Department North Attleborough Electric Department. Description: Petition for Declaratory Order of Taunton Municipal Lighting Plant Hudson Light & Power PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 103807 Department North Attleborough Electric Department. Filed Date: 12/2/24. Accession Number: 20241202–5311. Comment Date: 5 p.m. ET 12/23/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: December 13, 2024. Debbie-Anne A. Reese, Secretary. [FR Doc. 2024–30279 Filed 12–18–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3451–047] Beaver Falls Municipal Authority; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. E:\FR\FM\19DEN1.SGM 19DEN1

Agencies

[Federal Register Volume 89, Number 244 (Thursday, December 19, 2024)]
[Notices]
[Pages 103806-103807]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-30221]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

[GDO Docket No. EA-284-G]


Application for Renewal of Authorization To Export Electric 
Energy; Calpine Energy Solutions, LLC

AGENCY: Grid Deployment Office, Department of Energy.

ACTION: Notice of application.

-----------------------------------------------------------------------

SUMMARY: Calpine Energy Solutions, LLC (the Applicant or Calpine 
Solutions) has applied for the renewal of authorization to transmit 
electric energy from the United States to Mexico pursuant to the 
Federal Power Act.

DATES: Comments, protests, or motions to intervene must be submitted on 
or before January 21, 2025.

ADDRESSES: Comments, protests, motions to intervene, or requests for 
more information should be addressed by electronic mail to 
[email protected].

FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474-8226, 
[email protected].

SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) 
regulates electricity exports from the United States to foreign 
countries in accordance with section 202(e) of the Federal Power Act 
(FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et 
seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 
U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, 
previously exercised by the now-defunct Federal Power Commission, to 
DOE.
    Section 202(e) of the FPA provides that an entity which seeks to 
export electricity must obtain an order from DOE authorizing that 
export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue 
such orders was delegated to the DOE's Grid Deployment Office (GDO) 
under Redelegation Order No. S3-DEL-GD1-2023.
    On November 22, 2024, Calpine Solutions filed an application for 
the renewal of authorization to transmit electric energy from the 
United States to Mexico for a term of five years. App. at 1.
    According to the Application, Calpine Solutions is ``a California 
limited liability company with its principal place of business at 401 
West A Street, Suite 400, San Diego, California, and is an indirect, 
wholly owned subsidiary of Calpine Corporation.'' Id. The Applicant 
represents that its wholesale sales ``are made pursuant to authority 
granted by the Federal Energy Regulatory Commission (``FERC'') to sell 
wholesale power at market-based rates under a wholesale power sales 
tariff currently on file with FERC.'' Id. at 1-2.
    The Applicant states it ``does not own or control electric 
generation, transmission, cogeneration facilities, or distribution 
facilities, nor does [it] have a franchised service area.'' App. at 5. 
Calpine Solutions states that any electric energy it exports ``on 
either a firm or interruptible basis, will be surplus to the system of 
the generator thereof.'' Id. Thus, the Applicant states that ``its 
exports cannot have any adverse impact on the reliability, stability, 
or sufficiency of supply on a franchise electric supply system or the 
electric power supply within the U.S.'' Id. at 5-6.
    Further, regarding the second criterion used to analyze 
applications to export electricity, Calpine Solutions states it ``will 
comply with existing industry procedures for obtaining transmission 
capacity'' and ``will comply with any other export limits that DOE may 
deem appropriate, consistent with DOE's orders authorizing exports of 
electric energy by power marketers.'' App. at 6-7.
    The existing international transmission facilities to be utilized 
by the Applicant have been previously authorized by Presidential 
permits issued pursuant to Executive Order 10485, as amended, and are 
appropriate for open access transmission by third parties. See App. at 
Exhibit C.
    Procedural Matters: Any person desiring to be heard in this 
proceeding should file a comment or protest to the Application at 
[email protected]. Protests should be filed in accordance 
with Rule 211 of FERC's Rules of Practice and Procedure (18 CFR 
385.211). Any person desiring to become a party to this proceeding 
should file a motion to intervene at [email protected] in 
accordance with FERC Rule 214 (18 CFR 385.214).
    Comments and other filings concerning Calpine Solutions' 
Application should be clearly marked with GDO Docket No. EA-284-G. 
Additional copies are to be provided directly to Rachael Marsh, Calpine 
Corporation, 875 15th Street NW, Suite 700, Washington, DC 20005, 
[email protected], and Greg Bass, Calpine Energy Solutions, LLC, 
401 West A Street, Suite 500, San Diego, CA 92101, 
[email protected].
    A final decision will be made on the requested authorization after 
the environmental impacts have been evaluated pursuant to DOE's 
National Environmental Policy Act Implementing Procedures (10 CFR part 
1021) and after DOE evaluates whether the proposed action will have an 
adverse impact on the sufficiency of supply or reliability of the 
United States electric power supply system.
    Copies of this Application will be made available, upon request, by 
accessing the program website at https://www.energy.gov/gdo/pending-applications-0 or by emailing [email protected].
    Signing Authority: This document of the Department of Energy was 
signed on December 13, 2024, by Maria Robinson, Director, Grid 
Deployment Office, pursuant to delegated authority from the Secretary 
of Energy. That document

[[Page 103807]]

with the original signature and date is maintained by DOE. For 
administrative purposes only, and in compliance with requirements of 
the Office of the Federal Register, the undersigned DOE Federal 
Register Liaison Officer has been authorized to sign and submit the 
document in electronic format for publication, as an official document 
of the Department of Energy. This administrative process in no way 
alters the legal effect of this document upon publication in the 
Federal Register.

    Signed in Washington, DC, on December 16, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2024-30221 Filed 12-18-24; 8:45 am]