Combined Notice of Filings, 96241-96242 [2024-28411]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 89, No. 233 / Wednesday, December 4, 2024 / Notices
wide powerhouse with two Kaplan
turbine-generator units; (5) two 0.48
kilovolt (kV) generator leads; (6) three
0.48/34.5-kV transformers; and (7) a
34.5-kV, 300-foot-long transmission
line. The Weston Dam Project has a total
installed capacity of 540 kilowatts (kW).
There are no project recreation facilities.
Pursuant to Article 20 of the current
license Powerhouse Systems operates in
an instantaneous run-of-river mode such
that discharge from the project
approximates the instantaneous sum of
inflow to the project impoundment. The
project has an average annual generation
of 2,357 megawatt-hours.
Powerhouse Systems is not proposing
any changes to project facilities or
operation.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the project’s
docket number excluding the last three
digits in the docket number field to
access the document. For assistance,
contact FERC Online Support.
You may also register at https://
ferconline.ferc.gov/FERCOnline.aspx to
be notified via email of new filings and
issuances related to this or other
pending projects. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
n. Scoping Process
Pursuant to the National
Environmental Policy Act (NEPA),
Commission staff intends to prepare
either an environmental assessment
(EA) or an environmental impact
statement (EIS) (collectively referred to
as the ‘‘NEPA document’’) that describes
and evaluates the probable effects,
including an assessment of the sitespecific, if any, of the proposed action
and alternatives. The Commission’s
scoping process will help determine the
required level of analysis and satisfy the
NEPA scoping requirements,
irrespective of whether the Commission
issues an EA or an EIS.
At this time, we do not anticipate
holding on-site scoping meetings.
Instead, we are soliciting written
VerDate Sep<11>2014
17:36 Dec 03, 2024
Jkt 265001
comments and suggestions on the
preliminary list of issues and
alternatives to be addressed in the
NEPA document, as described in
scoping document 1 (SD1), issued
November 27, 2024.
Copies of the SD1 outlining the
proposed project and subject areas to be
addressed in the NEPA document were
distributed to the parties on the
Commission’s mailing list and the
applicant’s distribution list. Copies of
SD1 may be viewed on the web at
https://www.ferc.gov using the
‘‘eLibrary’’ link (see item m above).
Dated: November 27, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–28405 Filed 12–3–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP25–220–000.
Applicants: UGI Mt. Bethel Pipeline
Company, LLC.
Description: Annual Report of
Operational Purchases and Sales of UGI
Mt. Bethel Pipeline, LLC.
Filed Date: 11/26/24.
Accession Number: 20241126–5223.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–221–000.
Applicants: UGI Sunbury, LLC.
Description: Annual Report of
Operational Purchases and Sales of UGI
Sunbury, LLC.
Filed Date: 11/26/24.
Accession Number: 20241126–5224.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–222–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreements Update
(Sempra Dec 2024) to be effective
12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126–5246.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–223–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreement Update
(Conoco Dec 2024) to be effective
12/1/2024.
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
96241
Filed Date: 11/26/24.
Accession Number: 20241126–5250.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–224–000.
Applicants: Total Peaking Services,
L.L.C.
Description: Tariff Amendment:
Notice of Cancellation to be effective
12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126–5278.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–225–000.
Applicants: Colorado Interstate Gas
Company, L.L.C.
Description: § 4(d) Rate Filing: CIG
Qrtly LUF True-up Nov 2024 to be
effective 1/1/2025.
Filed Date: 11/26/24.
Accession Number: 20241126–5326.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–226–000.
Applicants: Gulf Shore Energy
Partners, LP.
Description: § 4(d) Rate Filing: Gulf
Shore Energy Partners LP Limited
Section 4 Filing to be effective
12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126–5327.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–227–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing:
11.27.24 Negotiated Rates—Emera
Energy Services, Inc. R–2715–103 to be
effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5032.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–228–000.
Applicants: Gas Transmission
Northwest LLC.
Description: Compliance filing:
Annual Fuel Charge Adjustment 2024
Report to be effective N/A.
Filed Date: 11/27/24.
Accession Number: 20241127–5052.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–229–000.
Applicants: Northern Natural Gas
Company.
Description: § 4(d) Rate Filing:
20241127 Negotiated Rates Filing to be
effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5068.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–230–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing: Annual
Fuel and L&U Filing 2025 to be effective
1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127–5072.
E:\FR\FM\04DEN1.SGM
04DEN1
ddrumheller on DSK120RN23PROD with NOTICES1
96242
Federal Register / Vol. 89, No. 233 / Wednesday, December 4, 2024 / Notices
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–231–000.
Applicants: Carlsbad Gateway, LLC.
Description: § 4(d) Rate Filing:
Carlsbad Gateway Non-Conforming
NRA and Tariff Housekeeping to be
effective 1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127–5078.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–232–000.
Applicants: Chandeleur Pipe Line,
LLC.
Description: Compliance filing:
Chandeleur Annual FLLA Filing to be
effective 1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127–5084.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–233–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing:
11.27.24 Negotiated Rates—Mercuria
Energy America, LLC R–7540–02 to be
effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5103.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–234–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing:
11.27.24 Negotiated Rates—Vitol Inc. R–
7495–22 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5108.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–235–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing:
11.27.24 Negotiated Rates—Vitol Inc. R–
7495–23 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5123.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25–236–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing:
11.27.24 Negotiated Rates—Twin Eagle
Resource Management, LLC R–7300–31
to be effective 11/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127–5135.
Comment Date: 5 p.m. ET 12/9/24.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
VerDate Sep<11>2014
17:36 Dec 03, 2024
Jkt 265001
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: November 27, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–28411 Filed 12–3–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP19–502–000 and CP19–502–
001]
Commonwealth LNG, LLC; Notice of
Schedule for the Preparation of a
Supplemental Environmental Impact
Statement for the Commonwealth LNG
Project
On November 17, 2022, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Order
Granting Authorization Under Section 3
of the Natural Gas Act (Order) for
Commonwealth LNG, LLC’s
Commonwealth LNG Project (Project).1
On July 16, 2024, the U.S. Court of
Appeals for the District of Columbia
Circuit issued an opinion finding, as
relevant here, that FERC failed to
properly assess the cumulative effects of
the Project’s nitrogen dioxide (NO2)
emissions, and remanded the Order to
FERC for further proceedings.2
1 Commonwealth
LNG, LLC, 181 FERC ¶ 61,143
(2022), order on reh’g, 183 FERC ¶ 61,173 (2023).
2 Healthy Gulf v. FERC, 107 F.4th 1033 (D.C. Cir.
2024).
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
Schedule for Environmental Review
This notice identifies the planned
schedule for completion of a
supplemental environmental impact
statement (SEIS) for the Project to
address the issues related to the
Commission’s analysis of NO2.3
This planned schedule is based on an
issuance of the draft SEIS in February
2025, opening a 45-day comment
period.
Issuance of Notice of Availability of the
final SEIS May 16, 2025
This notice identifies the
Commission’s anticipated schedule for
issuance of the final order for the
Project, which serves as the
Commission’s record of decision. We
currently anticipate issuing a final order
for the Project no later than:
Issuance of Final Order July 24, 2025
If a schedule change becomes
necessary, additional notice will be
provided.
Project Description
The Project consists of two main
components: (1) construction and
operation of the LNG export terminal,
which includes six liquefied natural gas
(LNG) plant facilities to liquefy natural
gas, six tanks to store the LNG, an LNG
carrier loading/berthing facility (marine
facility), and other appurtenant
facilities; and (2) construction and
operation of approximately 3.0 miles of
42-inch-diameter pipeline and one new
meter station to deliver natural gas to
the terminal. The Project would produce
8.4 million metric tonnes per annum of
LNG for export on an average of 156
LNG carriers per year.
Background
On August 20, 2019, as amended July
8, 2021, Commonwealth LNG, LLC filed
an application in Docket No. CP19–502–
000 requesting authorization pursuant
to section 3 of the Natural Gas Act
(NGA) and Part 153 of the Commission’s
regulations to construct and operate a
natural gas liquefaction and export
facility, including an NGA section 3
natural gas pipeline, in Cameron Parish,
Louisiana.
The Commission issued a Notice of
Availability of the Draft Environmental
Impact Statement on March 31, 2022.
On September 9, 2022, the final EIS was
issued. As noted above, on November
17, 2022, the Commission issued an
order granting authorization for the
3 In accordance with the Council on
Environmental Quality’s regulations, the unique
identification number for documents relating to this
environmental review is SEIS–019–20–000–
1732105648. 40 CFR 1501.5(c)(4) (2024).
E:\FR\FM\04DEN1.SGM
04DEN1
Agencies
[Federal Register Volume 89, Number 233 (Wednesday, December 4, 2024)]
[Notices]
[Pages 96241-96242]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-28411]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP25-220-000.
Applicants: UGI Mt. Bethel Pipeline Company, LLC.
Description: Annual Report of Operational Purchases and Sales of
UGI Mt. Bethel Pipeline, LLC.
Filed Date: 11/26/24.
Accession Number: 20241126-5223.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-221-000.
Applicants: UGI Sunbury, LLC.
Description: Annual Report of Operational Purchases and Sales of
UGI Sunbury, LLC.
Filed Date: 11/26/24.
Accession Number: 20241126-5224.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-222-000.
Applicants: El Paso Natural Gas Company, L.L.C.
Description: Sec. 4(d) Rate Filing: Negotiated Rate Agreements
Update (Sempra Dec 2024) to be effective 12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126-5246.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-223-000.
Applicants: El Paso Natural Gas Company, L.L.C.
Description: Sec. 4(d) Rate Filing: Negotiated Rate Agreement
Update (Conoco Dec 2024) to be effective 12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126-5250.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-224-000.
Applicants: Total Peaking Services, L.L.C.
Description: Tariff Amendment: Notice of Cancellation to be
effective 12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126-5278.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-225-000.
Applicants: Colorado Interstate Gas Company, L.L.C.
Description: Sec. 4(d) Rate Filing: CIG Qrtly LUF True-up Nov 2024
to be effective 1/1/2025.
Filed Date: 11/26/24.
Accession Number: 20241126-5326.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-226-000.
Applicants: Gulf Shore Energy Partners, LP.
Description: Sec. 4(d) Rate Filing: Gulf Shore Energy Partners LP
Limited Section 4 Filing to be effective 12/1/2024.
Filed Date: 11/26/24.
Accession Number: 20241126-5327.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-227-000.
Applicants: Iroquois Gas Transmission System, L.P.
Description: Sec. 4(d) Rate Filing: 11.27.24 Negotiated Rates--
Emera Energy Services, Inc. R-2715-103 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5032.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-228-000.
Applicants: Gas Transmission Northwest LLC.
Description: Compliance filing: Annual Fuel Charge Adjustment 2024
Report to be effective N/A.
Filed Date: 11/27/24.
Accession Number: 20241127-5052.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-229-000.
Applicants: Northern Natural Gas Company.
Description: Sec. 4(d) Rate Filing: 20241127 Negotiated Rates
Filing to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5068.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-230-000.
Applicants: El Paso Natural Gas Company, L.L.C.
Description: Sec. 4(d) Rate Filing: Annual Fuel and L&U Filing
2025 to be effective 1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127-5072.
[[Page 96242]]
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-231-000.
Applicants: Carlsbad Gateway, LLC.
Description: Sec. 4(d) Rate Filing: Carlsbad Gateway Non-
Conforming NRA and Tariff Housekeeping to be effective 1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127-5078.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-232-000.
Applicants: Chandeleur Pipe Line, LLC.
Description: Compliance filing: Chandeleur Annual FLLA Filing to be
effective 1/1/2025.
Filed Date: 11/27/24.
Accession Number: 20241127-5084.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-233-000.
Applicants: Iroquois Gas Transmission System, L.P.
Description: Sec. 4(d) Rate Filing: 11.27.24 Negotiated Rates--
Mercuria Energy America, LLC R-7540-02 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5103.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-234-000.
Applicants: Iroquois Gas Transmission System, L.P.
Description: Sec. 4(d) Rate Filing: 11.27.24 Negotiated Rates--
Vitol Inc. R-7495-22 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5108.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-235-000.
Applicants: Iroquois Gas Transmission System, L.P.
Description: Sec. 4(d) Rate Filing: 11.27.24 Negotiated Rates--
Vitol Inc. R-7495-23 to be effective 12/1/2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5123.
Comment Date: 5 p.m. ET 12/9/24.
Docket Numbers: RP25-236-000.
Applicants: Iroquois Gas Transmission System, L.P.
Description: Sec. 4(d) Rate Filing: 11.27.24 Negotiated Rates--
Twin Eagle Resource Management, LLC R-7300-31 to be effective 11/1/
2024.
Filed Date: 11/27/24.
Accession Number: 20241127-5135.
Comment Date: 5 p.m. ET 12/9/24.
Any person desiring to intervene, to protest, or to answer a
complaint in any of the above proceedings must file in accordance with
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211,
385.214, or 385.206) on or before 5:00 p.m. Eastern time on the
specified comment date. Protests may be considered, but intervention is
necessary to become a party to the proceeding.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Dated: November 27, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-28411 Filed 12-3-24; 8:45 am]