Application for Renewal of Authorization To Export Electric Energy; Altop Energy Investments LP, 90277-90278 [2024-26649]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 89, No. 221 / Friday, November 15, 2024 / Notices The existing international transmission facilities to be utilized by the Applicant have been previously authorized by Presidential permits issued pursuant to Executive Order 10485, as amended, and are appropriate for open access transmission by third parties. See App. at Exhibit C. Procedural Matters: Any person desiring to be heard in this proceeding should file a comment or protest to the Application at Electricity.Exports@ hq.doe.gov. Protests should be filed in accordance with Rule 211 of Federal Energy Regulatory Commission’s (FERC’s) Rules of Practice and Procedure (18 CFR 385.211). Any person desiring to become a party to this proceeding should file a motion to intervene at Electricity.Exports@ hq.doe.gov in accordance with FERC Rule 214 (18 CFR 385.214). Comments and other filings concerning Altop Energy Investments LP Application should be clearly marked with GDO Docket No. EA–518. Additional copies are to be provided directly to Gebre-Egziabher Gebre, Altop Energy Investments LP, 440 Louisiana Street, Suite 575, Houston, TX 77002, gebre.gebre@altopenergy.com. A final decision will be made on the requested authorization after the environmental impacts have been evaluated pursuant to DOE’s National Environmental Policy Act Implementing Procedures (10 CFR part 1021) and after DOE evaluates whether the proposed action will have an adverse impact on the sufficiency of supply or reliability of the United States electric power supply system. Copies of this Application will be made available, upon request, by accessing the program website at https://www.energy.gov/gdo/pendingapplications-0 or by emailing Electricity.Exports@hq.doe.gov. Signing Authority: This document of the Department of Energy was signed on November 8, 2024, by Maria Robinson, Director, Grid Deployment Office, pursuant to delegated authority from the Secretary of Energy. That document with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. VerDate Sep<11>2014 16:11 Nov 14, 2024 Jkt 265001 Signed in Washington, DC, on November 12, 2024. Treena V. Garrett, Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–26647 Filed 11–14–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY [GDO Docket No. EA–517] Application for Renewal of Authorization To Export Electric Energy; Altop Energy Investments LP Grid Deployment Office, Department of Energy. ACTION: Notice of application. AGENCY: Altop Energy Investments LP (the Applicant) has applied for authorization to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act. DATES: Comments, protests, or motions to intervene must be submitted on or before December 16, 2024. ADDRESSES: Comments, protests, motions to intervene, or requests for more information should be addressed by electronic mail to Electricity.Exports@hq.doe.gov. FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474–8226, Electricity.Exports@hq.doe.gov. SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) regulates electricity exports from the United States to foreign countries in accordance with section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, previously exercised by the nowdefunct Federal Power Commission, to DOE. Section 202(e) of the FPA provides that an entity which seeks to export electricity must obtain an order from DOE authorizing that export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue such orders was delegated to the DOE’s Grid Deployment Office (GDO) under Redelegation Order No. S3–DEL–GD1–2023. On October 15, 2024, Altop Energy Investments LP filed an application (Application or App.) with DOE to transmit electric energy from the United States to Mexico for a five-year term. App. at 1. According to the Application, Altop Energy Investments LP is a Delaware limited partnership with its principal SUMMARY: PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 90277 place of business in Houston, TX. Id. The Applicant states that it is ‘‘engaged in the trading and marketing of both financial and physical electricity in the wholesale power markets in North America.’’ Id. Further, the Applicant states that it is authorized via its subsidiaries to sell wholesale electric energy, capacity and ancillary services at market-based rates in all regions of the United States. Id. Altop Energy Investment LP states that it ‘‘has no obligation to serve native load, does not own or operate any electric distribution or transmission facilities, does not own or operate any natural gas distribution or transmission facilities, and does not own or operate any generation assets.’’ Id. The Applicant represents that the energy to be exported will be surplus to the requirements of selling entities and the overall electrical system and that its exports ‘‘will not impair the reliability of the grid.’’ Id. at 2. The existing international transmission facilities to be utilized by the Applicant have been previously authorized by Presidential permits issued pursuant to Executive Order 10485, as amended, and are appropriate for open access transmission by third parties. See App. at Exhibit C. Procedural Matters: Any person desiring to be heard in this proceeding should file a comment or protest to the Application at the email address provided previously. Protests should be filed in accordance with Rule 211 of FERC’s Rules of Practice and Procedure (18 CFR 385.211). Any person desiring to become a party to this proceeding should file a motion to intervene at the previously provided email address in accordance with FERC Rule 214 (18 CFR 385.214). Comments and other filings concerning Altop Energy Investments LP’s Application should be clearly marked with GDO Docket No. EA–517. Additional copies are to be provided directly to Gebre-Egziabher Gebre, Altop Energy Investments LP, 440 Louisiana Street, Suite 575, Houston, TX 77002, gebre.gebre@altopenergy.com. A final decision will be made on the requested authorization after the environmental impacts have been evaluated pursuant to DOE’s National Environmental Policy Act Implementing Procedures (10 CFR part 1021) and after DOE evaluates whether the proposed action will have an adverse impact on the sufficiency of supply or reliability of the United States electric power supply system. Copies of this Application will be made available, upon request, by accessing the program website at https://www.energy.gov/gdo/pending- E:\FR\FM\15NON1.SGM 15NON1 90278 Federal Register / Vol. 89, No. 221 / Friday, November 15, 2024 / Notices applications-0 or by emailing Electricity.Exports@hq.doe.gov. Signing Authority: This document of the Department of Energy was signed on November 8, 2024, by Maria Robinson, Director, Grid Deployment Office, pursuant to delegated authority from the Secretary of Energy. That document with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. Signed in Washington, DC, on November 12, 2024. Treena V. Garrett, Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–26649 Filed 11–14–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission khammond on DSKJM1Z7X2PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG25–28–000. Applicants: Morgnec Road Solar, LLC. Description: Morgnec Road Solar, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 11/8/24. Accession Number: 20241108–5035. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: EG25–29–000. Applicants: Spring Grove Solar II, LLC. Description: Spring Grove Solar II, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 11/8/24. Accession Number: 20241108–5037. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: EG25–30–000. Applicants: Cascade Energy Storage II LLC. Description: Cascade Energy Storage II LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 11/8/24. Accession Number: 20241108–5149. Comment Date: 5 p.m. ET 11/29/24. Take notice that the Commission received the following electric rate filings: VerDate Sep<11>2014 16:11 Nov 14, 2024 Jkt 265001 Docket Numbers: ER22–2293–001. Applicants: Dominion Energy South Carolina, Inc. Description: Compliance filing: Order No 881 Compliance filing to be effective 10/29/2019. Filed Date: 11/8/24. Accession Number: 20241108–5106. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER22–2317–001. Applicants: Portland General Electric Company. Description: Compliance filing: PGE OATT Att Q Order No. 881 Second Compliance Filing to be effective 7/12/ 2025. Filed Date: 11/8/24. Accession Number: 20241108–5001. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER22–2353–001. Applicants: Florida Power & Light Company. Description: Compliance filing: Order No. 881 Compliance Filing Regarding Timeline for AAR Calculation to be effective N/A. Filed Date: 11/8/24. Accession Number: 20241108–5133. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER24–3005–001. Applicants: Eldorado Solar Project, LLC. Description: Tariff Amendment: Supplement to Application for MBR Authority to be effective 10/28/2024. Filed Date: 11/8/24. Accession Number: 20241108–5150. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–392–000. Applicants: Dominion Energy South Carolina, Inc. Description: Compliance filing: Order No 881 Compliance filing to be effective 7/12/2025. Filed Date: 11/8/24. Accession Number: 20241108–5045. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–393–000. Applicants: Midcontinent Independent System Operator, Inc. Description: 205(d) Rate Filing: 2024– 11–08_System Support Resource (SSR) Tariff Provision Clean-Up to be effective 2/1/2025. Filed Date: 11/8/24. Accession Number: 20241108–5051. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–394–000. Applicants: New York Independent System Operator, Inc., NextEra Energy Transmission New York, Inc., Niagara Mohawk Power Corporation. Description: 205(d) Rate Filing: New York Independent System Operator, Inc. submits tariff filing per 35.13(a)(2)(iii: Joint 205: Amnd EPCA among NYISO, NEETNY, Nat Grid, and Alle Catt Wind (SA2812) to be effective 10/25/2024. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 Filed Date: 11/8/24. Accession Number: 20241108–5065. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–395–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: 205(d) Rate Filing: Amendment to Service Agreement FERC No. 804 to be effective 10/10/2024. Filed Date: 11/8/24. Accession Number: 20241108–5101. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–396–000. Applicants: Bluebird Solar LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 1/8/2025. Filed Date: 11/8/24. Accession Number: 20241108–5138. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–397–000. Applicants: New York State Electric & Gas Corporation, York Independent System Operator, Inc. Description: 205(d) Rate Filing: New York State Electric & Gas Corporation submits tariff filing per 35.13(a)(2)(iii: NYISO–NYSEG Joint 205: Amnd EPCA NYISO, NYSEG, Cassadaga, Arkwright, Ball Hill to be effective 10/25/2024. Filed Date: 11/8/24. Accession Number: 20241108–5145. Comment Date: 5 p.m. ET 11/29/24. Docket Numbers: ER25–398–000. Applicants: Niagara Mohawk Power Corporation, New York Independent System Operator, Inc. Description: 205(d) Rate Filing: Niagara Mohawk Power Corporation submits tariff filing per 35.13(a)(2)(iii: NMPC 205: proposed revisions to OATT Att. H regarding post-employment benefits to be effective 1/1/2025. Filed Date: 11/8/24. Accession Number: 20241108–5173. Comment Date: 5 p.m. ET 11/29/24. Take notice that the Commission received the following electric reliability filings: Docket Numbers: RR24–4–001. Applicants: North American Electric Reliability Corporation. Description: North American Electric Reliability Corporation submits supplemental filing to the Five-Year Electric Reliability Organization Performance Assessment Assessment Report. Filed Date: 11/8/24. Accession Number: 20241108–5040. Comment Date: 5 p.m. ET 11/22/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any E:\FR\FM\15NON1.SGM 15NON1

Agencies

[Federal Register Volume 89, Number 221 (Friday, November 15, 2024)]
[Notices]
[Pages 90277-90278]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-26649]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

[GDO Docket No. EA-517]


Application for Renewal of Authorization To Export Electric 
Energy; Altop Energy Investments LP

AGENCY: Grid Deployment Office, Department of Energy.

ACTION: Notice of application.

-----------------------------------------------------------------------

SUMMARY: Altop Energy Investments LP (the Applicant) has applied for 
authorization to transmit electric energy from the United States to 
Mexico pursuant to the Federal Power Act.

DATES: Comments, protests, or motions to intervene must be submitted on 
or before December 16, 2024.

ADDRESSES: Comments, protests, motions to intervene, or requests for 
more information should be addressed by electronic mail to 
[email protected].

FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474-8226, 
[email protected].

SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) 
regulates electricity exports from the United States to foreign 
countries in accordance with section 202(e) of the Federal Power Act 
(FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et 
seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 
U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, 
previously exercised by the now-defunct Federal Power Commission, to 
DOE.
    Section 202(e) of the FPA provides that an entity which seeks to 
export electricity must obtain an order from DOE authorizing that 
export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue 
such orders was delegated to the DOE's Grid Deployment Office (GDO) 
under Redelegation Order No. S3-DEL-GD1-2023.
    On October 15, 2024, Altop Energy Investments LP filed an 
application (Application or App.) with DOE to transmit electric energy 
from the United States to Mexico for a five-year term. App. at 1.
    According to the Application, Altop Energy Investments LP is a 
Delaware limited partnership with its principal place of business in 
Houston, TX. Id. The Applicant states that it is ``engaged in the 
trading and marketing of both financial and physical electricity in the 
wholesale power markets in North America.'' Id. Further, the Applicant 
states that it is authorized via its subsidiaries to sell wholesale 
electric energy, capacity and ancillary services at market-based rates 
in all regions of the United States. Id. Altop Energy Investment LP 
states that it ``has no obligation to serve native load, does not own 
or operate any electric distribution or transmission facilities, does 
not own or operate any natural gas distribution or transmission 
facilities, and does not own or operate any generation assets.'' Id. 
The Applicant represents that the energy to be exported will be surplus 
to the requirements of selling entities and the overall electrical 
system and that its exports ``will not impair the reliability of the 
grid.'' Id. at 2.
    The existing international transmission facilities to be utilized 
by the Applicant have been previously authorized by Presidential 
permits issued pursuant to Executive Order 10485, as amended, and are 
appropriate for open access transmission by third parties. See App. at 
Exhibit C.
    Procedural Matters: Any person desiring to be heard in this 
proceeding should file a comment or protest to the Application at the 
email address provided previously. Protests should be filed in 
accordance with Rule 211 of FERC's Rules of Practice and Procedure (18 
CFR 385.211). Any person desiring to become a party to this proceeding 
should file a motion to intervene at the previously provided email 
address in accordance with FERC Rule 214 (18 CFR 385.214).
    Comments and other filings concerning Altop Energy Investments LP's 
Application should be clearly marked with GDO Docket No. EA-517. 
Additional copies are to be provided directly to Gebre-Egziabher Gebre, 
Altop Energy Investments LP, 440 Louisiana Street, Suite 575, Houston, 
TX 77002, [email protected].
    A final decision will be made on the requested authorization after 
the environmental impacts have been evaluated pursuant to DOE's 
National Environmental Policy Act Implementing Procedures (10 CFR part 
1021) and after DOE evaluates whether the proposed action will have an 
adverse impact on the sufficiency of supply or reliability of the 
United States electric power supply system.
    Copies of this Application will be made available, upon request, by 
accessing the program website at https://www.energy.gov/gdo/pending-

[[Page 90278]]

applications-0 or by emailing [email protected].
    Signing Authority: This document of the Department of Energy was 
signed on November 8, 2024, by Maria Robinson, Director, Grid 
Deployment Office, pursuant to delegated authority from the Secretary 
of Energy. That document with the original signature and date is 
maintained by DOE. For administrative purposes only, and in compliance 
with requirements of the Office of the Federal Register, the 
undersigned DOE Federal Register Liaison Officer has been authorized to 
sign and submit the document in electronic format for publication, as 
an official document of the Department of Energy. This administrative 
process in no way alters the legal effect of this document upon 
publication in the Federal Register.

    Signed in Washington, DC, on November 12, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2024-26649 Filed 11-14-24; 8:45 am]