Large Loads Co-Located at Generating Facilities; Fourth Supplemental Notice of Commissioner-Led Technical Conference, 87359-87360 [2024-25436]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 89, No. 212 / Friday, November 1, 2024 / Notices Filed Date: 10/25/24. Accession Number: 20241025–5110. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–225–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.15: Seminole Solar (Seminole IV Solar) LGIA Termination Filing to be effective 10/25/2024. Filed Date: 10/25/24. Accession Number: 20241025–5113. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–226–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.15: Seminole Solar Projects (Seminole VI Solar + BESS) LGIA Termination Filing to be effective 10/25/ 2024. Filed Date: 10/25/24. Accession Number: 20241025–5114. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–227–000. Applicants: Mid-Atlantic Interstate Transmission, LLC, PJM Interconnection, L.L.C. Description: 205(d) Rate Filing: MidAtlantic Interstate Transmission, LLC submits tariff filing per 35.13(a)(2)(iii: MAIT submits Construction Agmnt, SA No. 7220 to be effective 12/26/2024. Filed Date: 10/25/24. Accession Number: 20241025–5115. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–228–000. Applicants: Citizens SycamorePenasquitos Transmission LLC. Description: 205(d) Rate Filing: Annual Operating Cost True-Up Adjustment Informational Filing to be effective 1/1/2025. Filed Date: 10/25/24. Accession Number: 20241025–5117. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–229–000. Applicants: Kuna BESS LLC. Description: Baseline eTariff Filing: Kuna BESS LLC, MBR Tariff to be effective 12/24/2024. Filed Date: 10/25/24. Accession Number: 20241025–5123. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–230–000. Applicants: Midcontinent Independent System Operator, Inc., Northern States Power Company, a Minnesota corporation. Description: 205(d) Rate Filing: Midcontinent Independent System Operator, Inc. submits tariff filing per 35.13(a)(2)(iii: 2024–10–25_SA 2420 NSPM-CapX Brookings Owners 1st Rev T–T to be effective 9/27/2024. Filed Date: 10/25/24. Accession Number: 20241025–5124. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–231–000. Applicants: Citizens Sunrise Transmission LLC. Description: 205(d) Rate Filing: Annual Operating Cost True-Up Adjustment Informational Filing to be effective 1/1/2025. Filed Date: 10/25/24. Accession Number: 20241025–5131. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–232–000. Applicants: Otter Tail Power Company. Description: 205(d) Rate Filing: Revisions to Operating Services Agreement with CPEC, Service Agreement No. 54 to be effective 1/1/ 2025. Filed Date: 10/25/24. Accession Number: 20241025–5146. Comment Date: 5 p.m. ET 11/15/24. Docket Numbers: ER25–233–000. Applicants: Duke Energy Carolinas, LLC. Description: 205(d) Rate Filing: DEC– NCMPA1 DTAs RS Nos. 643, 644 and 645 to be effective 1/1/2025. Filed Date: 10/25/24. Accession Number: 20241025–5159. Comment Date: 5 p.m. ET 11/15/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful PJM Interconnection, L.L.C ...................................................................... Atlantic City Electric Company ................................................................. Baltimore Gas and Electric Company ...................................................... VerDate Sep<11>2014 16:47 Oct 31, 2024 Jkt 265001 PO 00000 Frm 00036 Fmt 4703 public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: October 25, 2024. Debbie-Anne A. Reese, Secretary. [FR Doc. 2024–25435 Filed 10–31–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD24–11–000] Large Loads Co-Located at Generating Facilities; Fourth Supplemental Notice of Commissioner-Led Technical Conference As announced in the August 2, 2024 Notice in this proceeding, and August 16, 2024, September 10, 2024, and October 10, 2024 supplemental notices in this proceeding, the Federal Energy Regulatory Commission (Commission) will convene a Commissioner-led technical conference in the abovereferenced proceeding. The technical conference will take place on Friday, November 1, 2024, from 10:00 a.m. to 3:00 p.m. Eastern Time. The technical conference will be held in-person at the Commission’s headquarters at 888 First Street NE, Washington, DC 20426 in the Commission Meeting Room. The meeting will be available to view online. The updated agenda for the technical conference is attached to this Supplemental Notice, which includes the program and expected panelists. The purpose of this technical conference is to discuss generic issues related to the co-location of large loads at generating facilities. The Commission does not intend to discuss at this technical conference any specific proceeding before the Commission, including proceedings that involve similar issues. These proceedings include, but are not limited to: Docket Nos. ER24–2172–000, ER24–2172–001. Docket No. ER24–2888–000. Docket No. ER24–2889–000. Sfmt 4703 87359 E:\FR\FM\01NON1.SGM 01NON1 87360 Federal Register / Vol. 89, No. 212 / Friday, November 1, 2024 / Notices Commonwealth Edison Company ............................................................ Delmarva Power & Light Company .......................................................... PECO Energy Company .......................................................................... Potomac Electric Power Company ........................................................... PJM Interconnection, L.L.C ...................................................................... Baltimore Gas & Electric Company, PECO Energy Company ................ The technical conference will be open to the public. Advance registration is not required, and there is no fee for attendance. Information will also be posted on the Calendar of Events on the Commission’s website, www.ferc.gov, prior to the event. The technical conference will be transcribed and webcast. Transcripts will be available for a fee from Ace Reporting (202–347–3700). A link to the webcast of this event will be available in the Commission Calendar of Events at www.ferc.gov. The Commission provides technical support for the free webcasts. Please call 202–502–8680 or email customer@ferc.gov if you have any questions. Commission technical conferences are accessible under section 508 of the Rehabilitation Act of 1973. For accessibility accommodations, please send an email to accessibility@ferc.gov or call toll free 1–866–208–3372 (voice) or 202–208–8659 (TTY) or send a fax to 202–208–2106 with the required accommodations. For more information about this technical conference, please contact Keatley Adams at Keatley.Adams@ ferc.gov or 202–502–8678. For legal information, please contact Christopher Chaulk at Christopher.Chaulk@ferc.gov or 202–502–6720. For information related to logistics, please contact Sarah McKinley at sarah.mckinley@ferc.gov or 202–502–8368. For assistance with esubscribing to this docket, accessing docket materials in e-Library, or other participation needs such as entering a comment into the docket, please contact the Commission’s Office of Public Participation at OPP@ferc.gov or 202– 502–6595. Dated: October 25, 2024. Debbie-Anne A. Reese, Secretary. khammond on DSKJM1Z7X2PROD with NOTICES [FR Doc. 2024–25436 Filed 10–31–24; 8:45 am] BILLING CODE 6717–01–P Docket Docket Docket Docket Docket Docket No. ER24–2890–000. No. ER24–2891–000. No. ER24–2893–000. No. ER24–2894–000. Nos. ER24–2447–000, ER24–2447–001. No. EL24–149–000. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–496–000; Docket No. CP23–518–000] NFEnergı́a LLC; Notice of Intent To Prepare an Environmental Impact Statement for the San Juan Micro-Fuel Handling Facility Project, Request for Comments on Environmental Issues, Notice of Public Scoping Session, and Schedule for Environmental Review The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental impact statement (EIS) that will discuss the environmental impacts of the San Juan Micro-Fuel Handling Facility Project (Project) involving operation of facilities by NFEnergı́a LLC (NFEnergı́a) in San Juan, Puerto Rico.1 The Commission will use this EIS in its decision-making process to determine whether the Project is in the public interest. The schedule for preparation of the EIS is discussed in the Schedule for Environmental Review section of this notice. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies regarding the Project. As part of the National Environmental Policy Act (NEPA) review process, the Commission takes into account concerns the public may have about proposals and the environmental impacts that could result from its action whenever it considers the issuance of an authorization. This gathering of public input is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the environmental document on the important environmental issues. Additional information about the Commission’s NEPA process is described below in the NEPA Process and the EIS section of this notice. By this notice, the Commission requests public comments on the scope of issues to address in the environmental document, including 1 In accordance with the Council on Environmental Quality’s regulations, the unique identification number for documents relating to this environmental review is EISX–019–20–000– 1728388200. 40 CFR 1502.4(e)(10) (2024). VerDate Sep<11>2014 16:47 Oct 31, 2024 Jkt 265001 PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 comments on potential alternatives and impacts, and any relevant information, studies, or analyses of any kind concerning impacts affecting the quality of the human environment. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC, on or before 5:00 p.m. Eastern Time on November 25, 2024. Comments may be submitted in written or oral form. Further details on how to submit comments are provided in the Public Participation section of this notice. Public Participation There are four methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to FERC Online. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is also located on the Commission’s website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; a comment on a particular project is considered a ‘‘Comment on a Filing’’; (3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the Project docket numbers (CP21–496–000 and/or CP23–518–000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: DebbieAnne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: E:\FR\FM\01NON1.SGM 01NON1

Agencies

[Federal Register Volume 89, Number 212 (Friday, November 1, 2024)]
[Notices]
[Pages 87359-87360]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-25436]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. AD24-11-000]


Large Loads Co-Located at Generating Facilities; Fourth 
Supplemental Notice of Commissioner-Led Technical Conference

    As announced in the August 2, 2024 Notice in this proceeding, and 
August 16, 2024, September 10, 2024, and October 10, 2024 supplemental 
notices in this proceeding, the Federal Energy Regulatory Commission 
(Commission) will convene a Commissioner-led technical conference in 
the above-referenced proceeding. The technical conference will take 
place on Friday, November 1, 2024, from 10:00 a.m. to 3:00 p.m. Eastern 
Time. The technical conference will be held in-person at the 
Commission's headquarters at 888 First Street NE, Washington, DC 20426 
in the Commission Meeting Room. The meeting will be available to view 
online.
    The updated agenda for the technical conference is attached to this 
Supplemental Notice, which includes the program and expected panelists.
    The purpose of this technical conference is to discuss generic 
issues related to the co-location of large loads at generating 
facilities. The Commission does not intend to discuss at this technical 
conference any specific proceeding before the Commission, including 
proceedings that involve similar issues. These proceedings include, but 
are not limited to:

------------------------------------------------------------------------
 
------------------------------------------------------------------------
PJM Interconnection, L.L.C.............  Docket Nos. ER24-2172-000, ER24-
                                          2172-001.
Atlantic City Electric Company.........  Docket No. ER24-2888-000.
Baltimore Gas and Electric Company.....  Docket No. ER24-2889-000.

[[Page 87360]]

 
Commonwealth Edison Company............  Docket No. ER24-2890-000.
Delmarva Power & Light Company.........  Docket No. ER24-2891-000.
PECO Energy Company....................  Docket No. ER24-2893-000.
Potomac Electric Power Company.........  Docket No. ER24-2894-000.
PJM Interconnection, L.L.C.............  Docket Nos. ER24-2447-000, ER24-
                                          2447-001.
Baltimore Gas & Electric Company, PECO   Docket No. EL24-149-000.
 Energy Company.
------------------------------------------------------------------------

    The technical conference will be open to the public. Advance 
registration is not required, and there is no fee for attendance. 
Information will also be posted on the Calendar of Events on the 
Commission's website, www.ferc.gov, prior to the event.
    The technical conference will be transcribed and webcast. 
Transcripts will be available for a fee from Ace Reporting (202-347-
3700). A link to the webcast of this event will be available in the 
Commission Calendar of Events at www.ferc.gov. The Commission provides 
technical support for the free webcasts. Please call 202-502-8680 or 
email [email protected] if you have any questions.
    Commission technical conferences are accessible under section 508 
of the Rehabilitation Act of 1973. For accessibility accommodations, 
please send an email to [email protected] or call toll free 1-866-
208-3372 (voice) or 202-208-8659 (TTY) or send a fax to 202-208-2106 
with the required accommodations.
    For more information about this technical conference, please 
contact Keatley Adams at [email protected] or 202-502-8678. For 
legal information, please contact Christopher Chaulk at 
[email protected] or 202-502-6720. For information related to 
logistics, please contact Sarah McKinley at [email protected] or 
202-502-8368. For assistance with e-subscribing to this docket, 
accessing docket materials in e-Library, or other participation needs 
such as entering a comment into the docket, please contact the 
Commission's Office of Public Participation at [email protected] or 202-502-
6595.

    Dated: October 25, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-25436 Filed 10-31-24; 8:45 am]
BILLING CODE 6717-01-P