Fuel’s existing right-of-way in Potter
County, Pennsylvania;
• Line YM59: Install approximately
19.5 miles of new 20-inch-diameter
coated steel pipeline beginning at the
east end of the 3.8-mile Z20 Pipeline
replacement, traversing Potter and Tioga
Counties, Pennsylvania, and ending at
the NFG Midstream Covington, LLC
(Midstream) Lee Hill Interconnect;
• McCutcheon Hill OPP Station:
Construct a new over-pressure
protection (OPP) station at the
interconnection between the eastern
terminus of the Z20 Pipeline
replacement and the western terminus
of the YM59 Pipeline in Potter County;
• Measurement equipment at
Midstream’s Lee Hill Interconnect: 3 4
The Lee Hill Interconnect is a proposed
producer interconnect with Midstream
at the terminus of the proposed YM59
Pipeline in Tioga County;
• Perform minor modifications at
National Fuel’s existing Ellisburg
Compressor Station,5 in Potter County,
including replacing/installing
measurement, OPP devices, flow
control, and other associated
appurtenances; and
• Construct one new remote-control
valve setting and install a new cathodic
protection ground bed along the Line
YM59 Pipeline in Tioga County.
Background
On October 4, 2024, the Commission
issued a Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Proposed
Tioga Pathway Project and Notice of
Public Scoping Session (Notice of
Scoping). The Notice of Scoping was
sent to affected landowners; Federal,
State, and local government agencies;
elected officials; environmental and
public interest groups; Native American
Tribes; other interested parties; and
local libraries and newspapers. All
substantive comments will be addressed
in the EA.
ddrumheller on DSK120RN23PROD with NOTICES1
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
3 This interconnect would be designed, installed,
owned, operated, and maintained by Midstream,
except for the interconnect’s gas measurement, gas
quality, over pressure protection devices and a pig
launcher, which would be owned, operated, and
maintained by National Fuel.
4 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline,
conducting internal inspections, or other purposes.
5 National Fuel does not propose any changes to
compressor units or to the certificated capacity at
the Ellisburg Compressor Station.
VerDate Sep<11>2014
17:40 Oct 24, 2024
Jkt 265001
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP24–514–000), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–24809 Filed 10–24–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2509–051]
PE Hydro Generation, LLC; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 2509–051.
c. Date filed: January 3, 2022.
d. Applicant: PE Hydro Generation,
LLC.
PO 00000
Frm 00056
Fmt 4703
Sfmt 4703
85191
e. Name of Project: Shenandoah
Hydroelectric Project (P–2509–051).
f. Location: The project is located on
the South Fork of the Shenandoah River
near the Town of Shenandoah in Page
and Rockingham, Counties, Virginia.
The project does not occupy any federal
land.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Ms. Jody Smet,
Vice President, Regulatory Affairs, PE
Hydro Generation, LLC, 7315 Wisconsin
Ave., Suite 1100W, Bethesda, MD
20814; Phone at (804) 382–1764 or
email at jody.smet@eaglecreekre.com.
i. FERC Contact: Kristine Sillett at
(202) 502–6575; or email at
kristine.sillett@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy via U. S. Postal
Service to: Debbie-Anne A. Reese,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. All
filings must clearly identify the project
name and docket number on the first
page: Shenandoah Project (P–2509–051).
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervener
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
and is ready for environmental analysis
at this time.
E:\FR\FM\25OCN1.SGM
25OCN1
85192
Federal Register / Vol. 89, No. 207 / Friday, October 25, 2024 / Notices
l. The Shenandoah Project consists of:
(1) a 15-foot-high, 495-foot-long
reinforced concrete dam; (2) a 30-acre
impoundment with a storage capacity of
190 acre feet; (3) a 91-foot-long, 38-footwide powerhouse adjacent to the north
end of the dam, with four generating
units having a total installed capacity of
862 kW; (4) 180-foot-long, 2.4-kilovolt
(kV) project generator lines; (5) a
substation containing a 3-phase, 2.4/
34.5-kV transformer where
interconnection with the grid occurs
and; (6) other appurtenances.
The project operates in a run-of-river
mode with a minimum flow of 44 cubic
feet per second. The project had an
average annual generation of 2,037
megawatt-hours between 2011 and
2016.
m. This filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field, to access the document. For
assistance, contact FERC Online
Support.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicants and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicants.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding in
accordance with 18 CFR 4.34(b) and
385.2010.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202)502–6595, or at
OPP@ferc.gov.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. The applicant must file no later
than 60 days from the issuance date of
this notice: (1) copy of the water quality
certification; (2) a copy of the request for
certification, including proof of the date
on which the certifying agency received
the request; or (3) evidence of a waiver
of water quality certification.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestones
Target date
Deadline for filing comments, recommendations, terms and conditions, and prescriptions ..............................................
Deadline for filing reply comments .....................................................................................................................................
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–24806 Filed 10–24–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG25–12–000.
Applicants: Azalea Springs Solar Park
LLC.
Description: Azalea Springs Solar
Park LLC submits Notice of SelfCertification of Exempt Wholesale
Generator Status.
Filed Date: 10/18/24.
Accession Number: 20241018–5138.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: EG25–13–000.
VerDate Sep<11>2014
17:40 Oct 24, 2024
Jkt 265001
Applicants: Duff Solar Park LLC.
Description: Duff Solar Park LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 10/18/24.
Accession Number: 20241018–5140.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: EG25–14–000.
Applicants: Pleasantville Solar Park
LLC.
Description: Pleasantville Solar Park
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 10/18/24.
Accession Number: 20241018–5142.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: EG25–15–000.
Applicants: Riverstart Solar Park IV
LLC.
Description: Riverstart Solar Park IV
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 10/18/24.
Accession Number: 20241018–5143.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: EG25–16–000.
Applicants: Sandrini BESS Storage
LLC.
Description: Sandrini BESS Storage
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 10/18/24.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
December 17, 2024.
January 31, 2025.
Accession Number: 20241018–5144.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: EG25–17–000.
Applicants: Peregrine Energy Storage,
LLC.
Description: Peregrine Energy Storage,
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 10/18/24.
Accession Number: 20241018–5147.
Comment Date: 5 p.m. ET 11/8/24.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER24–417–001.
Applicants: Flat Ridge
Interconnection LLC.
Description: Compliance filing:
Compliance Filing Reflecting Rate
Schedule Effective Date to be effective
N/A.
Filed Date: 10/18/24.
Accession Number: 20241018–5026.
Comment Date: 5 p.m. ET 11/8/24.
Docket Numbers: ER24–422–001.
Applicants: Flat Ridge 2 Wind Energy
LLC.
Description: Compliance filing:
Compliance Filing Reflecting Certiciate
of Concurrence Effective Date to be
effective N/A.
E:\FR\FM\25OCN1.SGM
25OCN1
Agencies
[Federal Register Volume 89, Number 207 (Friday, October 25, 2024)]
[Notices]
[Pages 85191-85192]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-24806]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2509-051]
PE Hydro Generation, LLC; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 2509-051.
c. Date filed: January 3, 2022.
d. Applicant: PE Hydro Generation, LLC.
e. Name of Project: Shenandoah Hydroelectric Project (P-2509-051).
f. Location: The project is located on the South Fork of the
Shenandoah River near the Town of Shenandoah in Page and Rockingham,
Counties, Virginia. The project does not occupy any federal land.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Ms. Jody Smet, Vice President, Regulatory
Affairs, PE Hydro Generation, LLC, 7315 Wisconsin Ave., Suite 1100W,
Bethesda, MD 20814; Phone at (804) 382-1764 or email at
[email protected].
i. FERC Contact: Kristine Sillett at (202) 502-6575; or email at
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://ferconline.ferc.gov/QuickComment.aspx. For assistance, please
contact FERC Online Support at [email protected], (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic
filing, please send a paper copy via U. S. Postal Service to: Debbie-
Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Debbie-Anne A. Reese,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings must clearly identify the
project name and docket number on the first page: Shenandoah Project
(P-2509-051).
The Commission's Rules of Practice and Procedure require all
interveners filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted and is ready for
environmental analysis at this time.
[[Page 85192]]
l. The Shenandoah Project consists of: (1) a 15-foot-high, 495-
foot-long reinforced concrete dam; (2) a 30-acre impoundment with a
storage capacity of 190 acre feet; (3) a 91-foot-long, 38-foot-wide
powerhouse adjacent to the north end of the dam, with four generating
units having a total installed capacity of 862 kW; (4) 180-foot-long,
2.4-kilovolt (kV) project generator lines; (5) a substation containing
a 3-phase, 2.4/34.5-kV transformer where interconnection with the grid
occurs and; (6) other appurtenances.
The project operates in a run-of-river mode with a minimum flow of
44 cubic feet per second. The project had an average annual generation
of 2,037 megawatt-hours between 2011 and 2016.
m. This filing may be viewed on the Commission's website at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field, to access
the document. For assistance, contact FERC Online Support.
All filings must (1) bear in all capital letters the title
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicants and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicants. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding in accordance with
18 CFR 4.34(b) and 385.2010.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202)502-6595, or at [email protected].
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. The applicant must file no later than 60 days from the issuance
date of this notice: (1) copy of the water quality certification; (2) a
copy of the request for certification, including proof of the date on
which the certifying agency received the request; or (3) evidence of a
waiver of water quality certification.
o. Procedural schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
------------------------------------------------------------------------
Milestones Target date
------------------------------------------------------------------------
Deadline for filing comments, December 17, 2024.
recommendations, terms and
conditions, and prescriptions.
Deadline for filing reply comments January 31, 2025.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-24806 Filed 10-24-24; 8:45 am]