PE Hydro Generation, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 85191-85192 [2024-24806]

Download as PDF Federal Register / Vol. 89, No. 207 / Friday, October 25, 2024 / Notices Fuel’s existing right-of-way in Potter County, Pennsylvania; • Line YM59: Install approximately 19.5 miles of new 20-inch-diameter coated steel pipeline beginning at the east end of the 3.8-mile Z20 Pipeline replacement, traversing Potter and Tioga Counties, Pennsylvania, and ending at the NFG Midstream Covington, LLC (Midstream) Lee Hill Interconnect; • McCutcheon Hill OPP Station: Construct a new over-pressure protection (OPP) station at the interconnection between the eastern terminus of the Z20 Pipeline replacement and the western terminus of the YM59 Pipeline in Potter County; • Measurement equipment at Midstream’s Lee Hill Interconnect: 3 4 The Lee Hill Interconnect is a proposed producer interconnect with Midstream at the terminus of the proposed YM59 Pipeline in Tioga County; • Perform minor modifications at National Fuel’s existing Ellisburg Compressor Station,5 in Potter County, including replacing/installing measurement, OPP devices, flow control, and other associated appurtenances; and • Construct one new remote-control valve setting and install a new cathodic protection ground bed along the Line YM59 Pipeline in Tioga County. Background On October 4, 2024, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Tioga Pathway Project and Notice of Public Scoping Session (Notice of Scoping). The Notice of Scoping was sent to affected landowners; Federal, State, and local government agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. All substantive comments will be addressed in the EA. ddrumheller on DSK120RN23PROD with NOTICES1 Additional Information In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This 3 This interconnect would be designed, installed, owned, operated, and maintained by Midstream, except for the interconnect’s gas measurement, gas quality, over pressure protection devices and a pig launcher, which would be owned, operated, and maintained by National Fuel. 4 A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline, conducting internal inspections, or other purposes. 5 National Fuel does not propose any changes to compressor units or to the certificated capacity at the Ellisburg Compressor Station. VerDate Sep<11>2014 17:40 Oct 24, 2024 Jkt 265001 service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP24–514–000), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: October 18, 2024. Debbie-Anne A. Reese, Secretary. [FR Doc. 2024–24809 Filed 10–24–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2509–051] PE Hydro Generation, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 2509–051. c. Date filed: January 3, 2022. d. Applicant: PE Hydro Generation, LLC. PO 00000 Frm 00056 Fmt 4703 Sfmt 4703 85191 e. Name of Project: Shenandoah Hydroelectric Project (P–2509–051). f. Location: The project is located on the South Fork of the Shenandoah River near the Town of Shenandoah in Page and Rockingham, Counties, Virginia. The project does not occupy any federal land. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Ms. Jody Smet, Vice President, Regulatory Affairs, PE Hydro Generation, LLC, 7315 Wisconsin Ave., Suite 1100W, Bethesda, MD 20814; Phone at (804) 382–1764 or email at jody.smet@eaglecreekre.com. i. FERC Contact: Kristine Sillett at (202) 502–6575; or email at kristine.sillett@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy via U. S. Postal Service to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Shenandoah Project (P–2509–051). The Commission’s Rules of Practice and Procedure require all interveners filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is ready for environmental analysis at this time. E:\FR\FM\25OCN1.SGM 25OCN1 85192 Federal Register / Vol. 89, No. 207 / Friday, October 25, 2024 / Notices l. The Shenandoah Project consists of: (1) a 15-foot-high, 495-foot-long reinforced concrete dam; (2) a 30-acre impoundment with a storage capacity of 190 acre feet; (3) a 91-foot-long, 38-footwide powerhouse adjacent to the north end of the dam, with four generating units having a total installed capacity of 862 kW; (4) 180-foot-long, 2.4-kilovolt (kV) project generator lines; (5) a substation containing a 3-phase, 2.4/ 34.5-kV transformer where interconnection with the grid occurs and; (6) other appurtenances. The project operates in a run-of-river mode with a minimum flow of 44 cubic feet per second. The project had an average annual generation of 2,037 megawatt-hours between 2011 and 2016. m. This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field, to access the document. For assistance, contact FERC Online Support. All filings must (1) bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicants and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicants. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding in accordance with 18 CFR 4.34(b) and 385.2010. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595, or at OPP@ferc.gov. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. The applicant must file no later than 60 days from the issuance date of this notice: (1) copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of a waiver of water quality certification. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestones Target date Deadline for filing comments, recommendations, terms and conditions, and prescriptions .............................................. Deadline for filing reply comments ..................................................................................................................................... p. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of this notice. Dated: October 18, 2024. Debbie-Anne A. Reese, Secretary. [FR Doc. 2024–24806 Filed 10–24–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission ddrumheller on DSK120RN23PROD with NOTICES1 Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG25–12–000. Applicants: Azalea Springs Solar Park LLC. Description: Azalea Springs Solar Park LLC submits Notice of SelfCertification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. Accession Number: 20241018–5138. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: EG25–13–000. VerDate Sep<11>2014 17:40 Oct 24, 2024 Jkt 265001 Applicants: Duff Solar Park LLC. Description: Duff Solar Park LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. Accession Number: 20241018–5140. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: EG25–14–000. Applicants: Pleasantville Solar Park LLC. Description: Pleasantville Solar Park LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. Accession Number: 20241018–5142. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: EG25–15–000. Applicants: Riverstart Solar Park IV LLC. Description: Riverstart Solar Park IV LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. Accession Number: 20241018–5143. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: EG25–16–000. Applicants: Sandrini BESS Storage LLC. Description: Sandrini BESS Storage LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. PO 00000 Frm 00057 Fmt 4703 Sfmt 4703 December 17, 2024. January 31, 2025. Accession Number: 20241018–5144. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: EG25–17–000. Applicants: Peregrine Energy Storage, LLC. Description: Peregrine Energy Storage, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 10/18/24. Accession Number: 20241018–5147. Comment Date: 5 p.m. ET 11/8/24. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER24–417–001. Applicants: Flat Ridge Interconnection LLC. Description: Compliance filing: Compliance Filing Reflecting Rate Schedule Effective Date to be effective N/A. Filed Date: 10/18/24. Accession Number: 20241018–5026. Comment Date: 5 p.m. ET 11/8/24. Docket Numbers: ER24–422–001. Applicants: Flat Ridge 2 Wind Energy LLC. Description: Compliance filing: Compliance Filing Reflecting Certiciate of Concurrence Effective Date to be effective N/A. E:\FR\FM\25OCN1.SGM 25OCN1

Agencies

[Federal Register Volume 89, Number 207 (Friday, October 25, 2024)]
[Notices]
[Pages 85191-85192]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-24806]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2509-051]


PE Hydro Generation, LLC; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 2509-051.
    c. Date filed: January 3, 2022.
    d. Applicant: PE Hydro Generation, LLC.
    e. Name of Project: Shenandoah Hydroelectric Project (P-2509-051).
    f. Location: The project is located on the South Fork of the 
Shenandoah River near the Town of Shenandoah in Page and Rockingham, 
Counties, Virginia. The project does not occupy any federal land.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Ms. Jody Smet, Vice President, Regulatory 
Affairs, PE Hydro Generation, LLC, 7315 Wisconsin Ave., Suite 1100W, 
Bethesda, MD 20814; Phone at (804) 382-1764 or email at 
[email protected].
    i. FERC Contact: Kristine Sillett at (202) 502-6575; or email at 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://ferconline.ferc.gov/QuickComment.aspx. For assistance, please 
contact FERC Online Support at [email protected], (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, please send a paper copy via U. S. Postal Service to: Debbie-
Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Debbie-Anne A. Reese, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. All filings must clearly identify the 
project name and docket number on the first page: Shenandoah Project 
(P-2509-051).
    The Commission's Rules of Practice and Procedure require all 
interveners filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted and is ready for 
environmental analysis at this time.

[[Page 85192]]

    l. The Shenandoah Project consists of: (1) a 15-foot-high, 495-
foot-long reinforced concrete dam; (2) a 30-acre impoundment with a 
storage capacity of 190 acre feet; (3) a 91-foot-long, 38-foot-wide 
powerhouse adjacent to the north end of the dam, with four generating 
units having a total installed capacity of 862 kW; (4) 180-foot-long, 
2.4-kilovolt (kV) project generator lines; (5) a substation containing 
a 3-phase, 2.4/34.5-kV transformer where interconnection with the grid 
occurs and; (6) other appurtenances.
    The project operates in a run-of-river mode with a minimum flow of 
44 cubic feet per second. The project had an average annual generation 
of 2,037 megawatt-hours between 2011 and 2016.
    m. This filing may be viewed on the Commission's website at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field, to access 
the document. For assistance, contact FERC Online Support.
    All filings must (1) bear in all capital letters the title 
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicants and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicants. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding in accordance with 
18 CFR 4.34(b) and 385.2010.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202)502-6595, or at [email protected].
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. The applicant must file no later than 60 days from the issuance 
date of this notice: (1) copy of the water quality certification; (2) a 
copy of the request for certification, including proof of the date on 
which the certifying agency received the request; or (3) evidence of a 
waiver of water quality certification.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
            Milestones                           Target date
------------------------------------------------------------------------
Deadline for filing comments,       December 17, 2024.
 recommendations, terms and
 conditions, and prescriptions.
Deadline for filing reply comments  January 31, 2025.
------------------------------------------------------------------------

    p. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.

    Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-24806 Filed 10-24-24; 8:45 am]
BILLING CODE 6717-01-P