Commission staff issued a notice that
the project was ready for environmental
analysis (REA Notice). Based on the
information in the record, staff does not
anticipate that licensing the project
would constitute a major Federal action
significantly affecting the quality of the
human environment. Therefore, staff
intends to prepare an Environmental
Assessment (EA) on the application to
license the project.1
The EA will be issued and circulated
for review by all interested parties. All
comments filed on the EA will be
analyzed by staff and considered in the
Commission’s final licensing decision.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members, and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
The application will be processed
according to the following schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Commission issues
EA.
Target date
March 4, 2025.
Any questions regarding this notice
may be directed to Jeanne Edwards at
(202) 502–6181 or jeanne.edwards@
ferc.gov.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–24805 Filed 10–24–24; 8:45 am]
BILLING CODE 6717–01–P
schedule for processing Black Canyon
Hydro, LLC’s license application for the
Seminoe Pumped Storage Project. A
prior notice issued on January 10, 2024,
identified an anticipated schedule for
issuance of draft and final National
Environmental Policy Act (NEPA)
documents and a final order for the
project. On September 4, 2024, Black
Canyon Hydro, LLC requested an
extension of time to file its historic
properties management plan by October
31, 2024. Commission staff issued a
letter approving the extension of time
on September 11, 2024. To account for
the additional time needed for Black
Canyon Hydro, LLC to file the required
information, the application will be
processed according to the following
revised schedule.
Notice of Ready for Environmental
Analysis: January 2025.
Draft NEPA Document: September
2025.
Final NEPA Document: April 13,
2026.
In addition, in accordance with title
41 of the Fixing America’s Surface
Transportation Act, enacted on
December 4, 2015, agencies are to
publish completion dates for all federal
environmental reviews and
authorizations. This notice identifies the
Commission’s anticipated schedule for
issuance of the final order for the
project, which is based on the revised
issuance date for the final NEPA
document. Accordingly, we currently
anticipate issuing a final order for the
project no later than:
Issuance of Final Order: July 16, 2026.
If a schedule change becomes
necessary, an additional notice will be
provided so that interested parties and
government agencies are kept informed
of the project’s progress.
Convenience and Necessity pursuant to
section 7(c) and Authorization pursuant
to section 7(b) of the Natural Gas Act to
construct and operate and abandon
certain natural gas pipeline facilities.
The proposed project is known as the
Tioga Pathway Project (Project), and
would provide 190,000 dekatherms per
day of firm transportation service from
the Tioga County, Pennsylvania natural
gas production area to downstream
delivery points with other interstate
pipelines, which reach various end-use
markets and demand centers in the
United States and Canada, and
modernize a portion of National Fuel’s
existing Line Z20 pipeline system.
On August 30, 2024, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing Federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a Federal authorization
within 90 days of the date of issuance
of the Commission staff’s environmental
document for the Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1 The EA will be issued for a 30day comment period.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
Project Description
[FR Doc. 2024–24802 Filed 10–24–24; 8:45 am]
BILLING CODE 6717–01–P
ddrumheller on DSK120RN23PROD with NOTICES1
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Project No. 14787–004]
Federal Energy Regulatory
Commission
Black Canyon Hydro, LLC; Notice of
Revised Schedule for the Seminoe
Pumped Storage Project
[Docket No. CP24–514–000]
This notice revises the Federal Energy
Regulatory Commission’s (Commission)
1 In accordance with the Council on
Environmental Quality’s regulations, the unique
identification number for documents relating to this
environmental review is 3240. 40 CFR 1501.5(c)(4)
(2024).
VerDate Sep<11>2014
17:40 Oct 24, 2024
Jkt 265001
National Fuel Gas Supply Corporation;
Notice of Schedule for the Preparation
of an Environmental Assessment for
the Tioga Pathway Project
On August, 21, 2024, National Fuel
Gas Supply Corporation filed an
application in Docket No. CP24–514–
000 requesting a Certificate of Public
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
Schedule for Environmental Review
Issuance of EA—February 13, 2025
90-day Federal Authorization Decision
Deadline 2—May 14, 2025
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
The Tioga Pathway would consist of
the following facilities:
• Line Z20: Replace approximately
3.8 miles of 12-inch-diameter 1936vintage bare steel pipeline with new 20inch-diameter coated steel pipeline and
perform modifications to an existing
valve setting on Line Z20 in National
1 In accordance with the Council on
Environmental Quality’s regulations, the unique
identification number for documents relating to this
environmental review is EAXX–019–20–000–
1728990440. 40 CFR 1501.5(c)(4) (2024).
2 The Commission’s deadline applies to the
decisions of other Federal agencies, and state
agencies acting under federally delegated authority,
that are responsible for Federal authorizations,
permits, and other approvals necessary for
proposed projects under the Natural Gas Act. Per
18 CFR 157.22(a), the Commission’s deadline for
other agency’s decisions applies unless a schedule
is otherwise established by Federal law.
E:\FR\FM\25OCN1.SGM
25OCN1
Agencies
[Federal Register Volume 89, Number 207 (Friday, October 25, 2024)]
[Notices]
[Page 85190]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-24802]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14787-004]
Black Canyon Hydro, LLC; Notice of Revised Schedule for the
Seminoe Pumped Storage Project
This notice revises the Federal Energy Regulatory Commission's
(Commission) schedule for processing Black Canyon Hydro, LLC's license
application for the Seminoe Pumped Storage Project. A prior notice
issued on January 10, 2024, identified an anticipated schedule for
issuance of draft and final National Environmental Policy Act (NEPA)
documents and a final order for the project. On September 4, 2024,
Black Canyon Hydro, LLC requested an extension of time to file its
historic properties management plan by October 31, 2024. Commission
staff issued a letter approving the extension of time on September 11,
2024. To account for the additional time needed for Black Canyon Hydro,
LLC to file the required information, the application will be processed
according to the following revised schedule.
Notice of Ready for Environmental Analysis: January 2025.
Draft NEPA Document: September 2025.
Final NEPA Document: April 13, 2026.
In addition, in accordance with title 41 of the Fixing America's
Surface Transportation Act, enacted on December 4, 2015, agencies are
to publish completion dates for all federal environmental reviews and
authorizations. This notice identifies the Commission's anticipated
schedule for issuance of the final order for the project, which is
based on the revised issuance date for the final NEPA document.
Accordingly, we currently anticipate issuing a final order for the
project no later than:
Issuance of Final Order: July 16, 2026.
If a schedule change becomes necessary, an additional notice will
be provided so that interested parties and government agencies are kept
informed of the project's progress.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-24802 Filed 10-24-24; 8:45 am]