Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments: Great Lakes Hydro America, LLC, 84346 [2024-24378]
Download as PDF
84346
Federal Register / Vol. 89, No. 204 / Tuesday, October 22, 2024 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2572–141]
ddrumheller on DSK120RN23PROD with NOTICES1
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments:
Great Lakes Hydro America, LLC
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2572–141.
c. Date Filed: September 30, 2024.
d. Applicant: Great Lakes Hydro
American, LLC (GLHA).
e. Name of Project: Ripogenus
Hydroelectric Project (project).
f. Location: On the West Branch of the
Penobscot River (West Branch) in
Piscataquis and Penobscot Counties,
Maine.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Michael
Scarzello, Licensing Manager,
Brookfield Renewable U.S., 399 Big Bay
Road, Queensbury, NY 12804; (315)
566–0197; Michael.scarzello@
brookfieldrenewable.com.
i. FERC Contact: Allan Creamer,
Project Coordinator; telephone at (202)
502–8365; email at allan.creamer@
ferc.gov.
j. The application is not ready for
environmental analysis at this time.
k. Project Description: The Ripogenus
Project is located about 21 river miles
upstream of the Penobscot Mills Project,
and consists of: (1) the Ripogenus
impoundment, which (a) is about 20.8
miles long, (b) has a surface area of
about 29,270 acres at a normal full pond
elevation of 941.59 feet National
Geodetic Vertical Datum of 1929 (NGVD
29), and (c) has a usable storage of about
688,705 acre-feet, with a maximum
drawdown of 44 feet (to elevation
897.59 feet NGVD 29); and (2)
Umbazooksus Lake, which has a surface
area of 1,600 acres. Ripogenus Dam is
795 feet long and is located at the outlet
of Ripogenus Lake. The dam includes
two concrete spillway sections, an
intake section, a gated sluice section,
and an earthen section.
Water flows from the Ripogenus
impoundment through an intake
structure, which directs water through a
tunnel and penstocks to the powerhouse
(McKay Station). The powerhouse
contains three turbine-generating units,
VerDate Sep<11>2014
17:10 Oct 21, 2024
Jkt 265001
with a total rated capacity of 37.5
megawatts. Power generated at the
project is transmitted to the electric grid
via three transformers and a 29.4-milelong transmission line. An additional
0.75-mile-long transmission line
extends from the McKay Substation to
Ripogenus Dam. The Ripogenus Project
also contains one battery energy storage
site that is used to enhance system
reliability. The Ripogenus Project is
operated as a store-and-release
development, with an annual seasonal
drawdown that allows for management
of water levels and flows downstream
from the project. GLHA releases
minimum flows into the dewatered
section of the West Branch downstream
from Ripogenus Dam, as well as flows
through the McKay Station generating
units to protect aquatic habitat and to
provide whitewater boating
opportunities. GLHA also releases flows
to the West Branch during outages of the
generating units, and diverts flow to the
Holbrook Side Channel to enhance
aquatic habitat. The project provides
some capacity to store water to reduce
downstream flooding, as well as storage
releases during droughts. Additional
details regarding the Ripogenus Project
facilities and operations can be found in
Exhibit A (Ripogenus Project) and
Exhibit B of the license application, and
can be accessed by following the
instructions in paragraph l.
GLHA proposes to continue to operate
the Ripogenus Project as a store-andrelease facility. GLHA would continue
to release flows ranging between 12
cubic feet per second (cfs) and 100 cfs
from Ripogenus Dam to the bypassed
reach, provide a station outage flow of
400 cfs downstream from McKay
Station, continue to operate and
maintain the Holbrook Side Channel as
habitat for salmon and brook trout,
maintain the 200-foot conservation
buffer and 100-foot vegetation buffer
around the Ripogenus impoundment,
and maintain Umbazooksus Lake as
wetland and wildlife habitat. In
addition, GLHA proposes to provide a
year-round minimum flow of 1,700 cfs
downstream from McKay Station for
aquatic habitat; provide seasonallyadjusted flows for whitewater boating;
fund the installation, operation, and
maintenance of a USGS flow gauge
downstream from McKay Station (near
Big Eddy); post impoundment level and
flow information on Brookfield’s
existing SafeWaters website; and
develop a recreation plan, shoreline
management plan, loon management
plan, and historic properties
management plan.
l. In addition to publishing this notice
in the Federal Register, the Commission
PO 00000
Frm 00019
Fmt 4703
Sfmt 9990
provides all interested persons an
opportunity to view and/or print the
contents of this notice, as well as other
documents in the proceeding (e.g.,
license application) via the internet
through the Commission’s Home Page
(https://www.ferc.gov), using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field to access the
document (P–2572). For assistance,
contact FERC at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). You may also
register online at https://ferc
online.ferc.gov/FERCOnline.aspx to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
m. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595, or OPP@
ferc.gov.
n. Procedural Schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Deficiency Letter—October 2024
Additional Information Request—
November 2024
Notice of Acceptance—March 2025
Issue Notice of Ready for Environmental
Analysis—March 2025
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: October 15, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024–24378 Filed 10–21–24; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\22OCN1.SGM
22OCN1
Agencies
[Federal Register Volume 89, Number 204 (Tuesday, October 22, 2024)]
[Notices]
[Page 84346]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-24378]
[[Page 84346]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2572-141]
Notice of Application Tendered for Filing With the Commission and
Establishing Procedural Schedule for Licensing and Deadline for
Submission of Final Amendments: Great Lakes Hydro America, LLC
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2572-141.
c. Date Filed: September 30, 2024.
d. Applicant: Great Lakes Hydro American, LLC (GLHA).
e. Name of Project: Ripogenus Hydroelectric Project (project).
f. Location: On the West Branch of the Penobscot River (West
Branch) in Piscataquis and Penobscot Counties, Maine.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Michael Scarzello, Licensing Manager,
Brookfield Renewable U.S., 399 Big Bay Road, Queensbury, NY 12804;
(315) 566-0197; [email protected].
i. FERC Contact: Allan Creamer, Project Coordinator; telephone at
(202) 502-8365; email at [email protected].
j. The application is not ready for environmental analysis at this
time.
k. Project Description: The Ripogenus Project is located about 21
river miles upstream of the Penobscot Mills Project, and consists of:
(1) the Ripogenus impoundment, which (a) is about 20.8 miles long, (b)
has a surface area of about 29,270 acres at a normal full pond
elevation of 941.59 feet National Geodetic Vertical Datum of 1929 (NGVD
29), and (c) has a usable storage of about 688,705 acre-feet, with a
maximum drawdown of 44 feet (to elevation 897.59 feet NGVD 29); and (2)
Umbazooksus Lake, which has a surface area of 1,600 acres. Ripogenus
Dam is 795 feet long and is located at the outlet of Ripogenus Lake.
The dam includes two concrete spillway sections, an intake section, a
gated sluice section, and an earthen section.
Water flows from the Ripogenus impoundment through an intake
structure, which directs water through a tunnel and penstocks to the
powerhouse (McKay Station). The powerhouse contains three turbine-
generating units, with a total rated capacity of 37.5 megawatts. Power
generated at the project is transmitted to the electric grid via three
transformers and a 29.4-mile-long transmission line. An additional
0.75-mile-long transmission line extends from the McKay Substation to
Ripogenus Dam. The Ripogenus Project also contains one battery energy
storage site that is used to enhance system reliability. The Ripogenus
Project is operated as a store-and-release development, with an annual
seasonal drawdown that allows for management of water levels and flows
downstream from the project. GLHA releases minimum flows into the
dewatered section of the West Branch downstream from Ripogenus Dam, as
well as flows through the McKay Station generating units to protect
aquatic habitat and to provide whitewater boating opportunities. GLHA
also releases flows to the West Branch during outages of the generating
units, and diverts flow to the Holbrook Side Channel to enhance aquatic
habitat. The project provides some capacity to store water to reduce
downstream flooding, as well as storage releases during droughts.
Additional details regarding the Ripogenus Project facilities and
operations can be found in Exhibit A (Ripogenus Project) and Exhibit B
of the license application, and can be accessed by following the
instructions in paragraph l.
GLHA proposes to continue to operate the Ripogenus Project as a
store-and-release facility. GLHA would continue to release flows
ranging between 12 cubic feet per second (cfs) and 100 cfs from
Ripogenus Dam to the bypassed reach, provide a station outage flow of
400 cfs downstream from McKay Station, continue to operate and maintain
the Holbrook Side Channel as habitat for salmon and brook trout,
maintain the 200-foot conservation buffer and 100-foot vegetation
buffer around the Ripogenus impoundment, and maintain Umbazooksus Lake
as wetland and wildlife habitat. In addition, GLHA proposes to provide
a year-round minimum flow of 1,700 cfs downstream from McKay Station
for aquatic habitat; provide seasonally-adjusted flows for whitewater
boating; fund the installation, operation, and maintenance of a USGS
flow gauge downstream from McKay Station (near Big Eddy); post
impoundment level and flow information on Brookfield's existing
SafeWaters website; and develop a recreation plan, shoreline management
plan, loon management plan, and historic properties management plan.
l. In addition to publishing this notice in the Federal Register,
the Commission provides all interested persons an opportunity to view
and/or print the contents of this notice, as well as other documents in
the proceeding (e.g., license application) via the internet through the
Commission's Home Page (https://www.ferc.gov), using the ``eLibrary''
link. Enter the docket number, excluding the last three digits in the
docket number field to access the document (P-2572). For assistance,
contact FERC at [email protected], (866) 208-3676 (toll free),
or (202) 502-8659 (TTY). You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new
filings and issuances related to this or other pending projects. For
assistance, contact FERC Online Support.
m. The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595, or [email protected].
n. Procedural Schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
Deficiency Letter--October 2024
Additional Information Request--November 2024
Notice of Acceptance--March 2025
Issue Notice of Ready for Environmental Analysis--March 2025
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: October 15, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-24378 Filed 10-21-24; 8:45 am]