Erie Boulevard Hydropower, L.P.; Notice of Revised Procedural Schedule for Final Environmental Assessment for the Proposed Project Relicense, 81518 [2024-23184]

Download as PDF 81518 Federal Register / Vol. 89, No. 195 / Tuesday, October 8, 2024 / Notices also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: October 1, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–23188 Filed 10–7–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Dated: October 1, 2024. Debbie-Anne A. Reese, Acting Secretary. [Project No. 7186–000] ddrumheller on DSK120RN23PROD with NOTICES1 Missisquoi, LLC; Notice of Authorization for Continued Project Operation [FR Doc. 2024–23183 Filed 10–7–24; 8:45 am] BILLING CODE 6717–01–P The license for the Sheldon Springs Hydroelectric Project No. 7186 was issued for a period ending September 30, 2024. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. VerDate Sep<11>2014 17:23 Oct 07, 2024 Jkt 265001 If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 7186 is issued to Missisquoi, LLC for a period effective October 1, 2024, through September 30, 2025, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before September 30, 2025, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Missisquoi, LLC is authorized to continue operation of the Sheldon Springs Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2701–061] Erie Boulevard Hydropower, L.P.; Notice of Revised Procedural Schedule for Final Environmental Assessment for the Proposed Project Relicense On February 26, 2021, Erie Boulevard Hydropower, L.P. (Erie) filed an application for a new major license to continue to operate and maintain the 39.75-megawatt (MW) West Canada Creek Hydroelectric Project No. 2701 (West Canada Creek Project). On June 27, 2022, Commission staff issued a notice of intent to prepare a draft and final Environmental Assessment (EA) to evaluate the effects of relicensing the West Canada Creek Project. The notice of intent included a schedule for preparing a draft and final EA. On September 6, 2023, Commission staff issued the draft EA. By notices issued September 21, 2023 and March 25, 2024, staff revised the procedural schedule for completing the final EA. By this notice, Commission staff is updating the procedural schedule for completing the final EA. The revised PO 00000 Frm 00102 Fmt 4703 Sfmt 4703 schedule is shown below. Further revisions to the schedule may be made as appropriate. Milestone Issue Final EA ........... Target date October 2024. Any questions regarding this notice may be directed to Laurie Bauer at (202) 502–6519, or by email at laurie.bauer@ ferc.gov. Dated: October 1, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–23184 Filed 10–7–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ID–9044–001] Rochow, Garrick, J; Notice of Filing Take notice that on September 27, 2024, Garrick J. Rochow submitted for filing, application for authority to hold interlocking positions, pursuant to section 305(b) of the Federal Power Act, 16 U.S.C. 825d (b) and part 45.8 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR part 45.8. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the E:\FR\FM\08OCN1.SGM 08OCN1

Agencies

[Federal Register Volume 89, Number 195 (Tuesday, October 8, 2024)]
[Notices]
[Page 81518]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-23184]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2701-061]


Erie Boulevard Hydropower, L.P.; Notice of Revised Procedural 
Schedule for Final Environmental Assessment for the Proposed Project 
Relicense

    On February 26, 2021, Erie Boulevard Hydropower, L.P. (Erie) filed 
an application for a new major license to continue to operate and 
maintain the 39.75-megawatt (MW) West Canada Creek Hydroelectric 
Project No. 2701 (West Canada Creek Project). On June 27, 2022, 
Commission staff issued a notice of intent to prepare a draft and final 
Environmental Assessment (EA) to evaluate the effects of relicensing 
the West Canada Creek Project. The notice of intent included a schedule 
for preparing a draft and final EA. On September 6, 2023, Commission 
staff issued the draft EA. By notices issued September 21, 2023 and 
March 25, 2024, staff revised the procedural schedule for completing 
the final EA.
    By this notice, Commission staff is updating the procedural 
schedule for completing the final EA. The revised schedule is shown 
below. Further revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Issue Final EA............................  October 2024.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Laurie Bauer 
at (202) 502-6519, or by email at [email protected].

    Dated: October 1, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-23184 Filed 10-7-24; 8:45 am]
BILLING CODE 6717-01-P