BOST1 Hydroelectric, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 81514-81515 [2024-23182]

Download as PDF ddrumheller on DSK120RN23PROD with NOTICES1 81514 Federal Register / Vol. 89, No. 195 / Tuesday, October 8, 2024 / Notices Accession Number: 20241001–5079. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–9–000. Applicants: Iroquois Gas Transmission System, L.P. Description: § 4(d) Rate Filing: 10.1.24 Negotiated Rates—Citadel Energy Marketing LLC R–7705–28 to be effective 11/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5083. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–10–000. Applicants: NEXUS Gas Transmission, LLC. Description: § 4(d) Rate Filing: Negotiated Rates—Various Releases eff 10–1–2024 to be effective 10/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5086. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–11–000. Applicants: Maritimes & Northeast Pipeline, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rates—Northern to Emera Energy 3145 eff 10–1–24 to be effective 10/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5087. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–12–000. Applicants: Northern Natural Gas Company. Description: § 4(d) Rate Filing: 20241001 Non-Conforming Contract Iogen RC to be effective 11/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5107. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–13–000. Applicants: Rover Pipeline LLC. Description: § 4(d) Rate Filing: Summary of Negotiated Rate Capacity Release Agreements 10–1–2024 to be effective 10/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5126. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–14–000. Applicants: Texas Gas Transmission, LLC. Description: § 4(d) Rate Filing: 2024 Fuel Tracker Filing to be effective 11/1/ 2024. Filed Date: 10/1/24. Accession Number: 20241001–5142. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–15–000. Applicants: Spire STL Pipeline LLC. Description: § 4(d) Rate Filing: Spire STL Pipeline Annual LAUF Filing to be effective 11/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5167. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–16–000. VerDate Sep<11>2014 17:23 Oct 07, 2024 Jkt 265001 Applicants: Saltville Gas Storage Company L.L.C. Description: § 4(d) Rate Filing: SGSC 2024 Fuel Filing to be effective 11/1/ 2024. Filed Date: 10/1/24. Accession Number: 20241001–5172. Comment Date: 5 p.m. ET 10/15/24. Docket Numbers: RP25–17–000. Applicants: Equitrans, L.P. Description: § 4(d) Rate Filing: Negotiated Rate Capacity Release Agreement—10/01/2024 to be effective 10/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5201. Comment Date: 5 p.m. ET 10/15/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Filings in Existing Proceedings Docket Numbers: RP24–1106–001. Applicants: Adelphia Gateway, LLC. Description: Tariff Amendment: Adelphia Gateways Amended Rate Case Filing to be effective 11/1/2024. Filed Date: 9/30/24. Accession Number: 20240930–5211. Comment Date: 5 p.m. ET 10/15/24. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as PO 00000 Frm 00098 Fmt 4703 Sfmt 4703 interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: October 1, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–23186 Filed 10–7–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 15350–000] BOST1 Hydroelectric, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On April 22, 2024, BOST1 Hydroelectric, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the proposed Lock and Dam No. 14 Hydroelectric Project, a hydropower project proposed to be located at the U.S. Army Corps of Engineers’ (Corps) Mississippi Lock and Dam 14 located on the Mississippi River, near Hampton, Illinois. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Lock and Dam 14 Hydroelectric Project would consist of the following: (1) a 700-foot-long and 300-foot-wide intake area with trashracks; (2) a 150-foot-long and 78foot-wide reinforced concrete powerhouse adjacent to the existing Corps dam; (3) three turbine-generator units each with a rated capacity of 8.0 megawatts (MW), for a total installed powerhouse capacity of 24.0 MW; (4) a 150-foot-long tailrace; (5) a 2.5-milelong underground transmission line extending from the switchyard adjacent to the powerhouse to the point of interconnect with the existing MidAtlantic Power 161 kilovolt transmission line; and (6) a rockfill dike extending 500 feet upstream and a deflection dike extending 900 feet downstream. The proposed project would have an estimated annual generation of 153.3 gigawatt-hours. E:\FR\FM\08OCN1.SGM 08OCN1 ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 89, No. 195 / Tuesday, October 8, 2024 / Notices Applicant Contact: Douglas A. Spaulding, Nelson Energy, 1030 Tyrol Trail, Minnesota, MN 55416; phone: (612) 599–8493. FERC Contact: Shivani Khetani; phone: (212) 273–5917, or by email at shivani.khetani@ferc.gov. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–15350–000. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s website at https://elibrary.ferc.gov/eLibrary/search. Enter the docket number (P–15350) in the docket number field to access the VerDate Sep<11>2014 17:23 Oct 07, 2024 Jkt 265001 document. For assistance, contact FERC Online Support. Dated: October 1, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–23182 Filed 10–7–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC24–125–000. Applicants: Darby Power, LLC, Gavin Power, LLC, Lawrenceburg Power, LLC, Waterford Power, LLC, Lightstone Marketing LLC, ECP ControlCo, LLC. Description: Joint Application for Authorization Under Section 203 of the Federal Power Act of Darby Power, LLC, et al. Filed Date: 9/27/24. Accession Number: 20240927–5296. Comment Date: 5 p.m. ET 11/26/24. Docket Numbers: EC24–126–000. Applicants: Griffith Energy LLC, Onward Griffith Holdings, LLC. Description: Joint Application for Authorization Under Section 203 of the Federal Power Act of Griffith Energy LLC, et al. Filed Date: 9/27/24. Accession Number: 20240927–5297. Comment Date: 5 p.m. ET 10/18/24. Take notice that the Commission received the following Complaints and Compliance filings in EL Dockets: Docket Numbers: EL24–113–000. Applicants: Independent Market Monitor for PJM v. Indicated Energy Efficiency Sellers. Description: Offer of Settlement of the Independent Market Monitor for PJM. Filed Date: 9/30/24. Accession Number: 20240930–5359. Comment Date: 5 p.m. ET 10/22/24. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2302–011; ER19–2674–004. Applicants: New Mexico PPA Corporation, Public Service Company of New Mexico. Description: Notice of Non-Material Change in Status of Public Service Company of New Mexico, et al. Filed Date: 9/27/24. Accession Number: 20240927–5295. Comment Date: 5 p.m. ET 10/18/24. Docket Numbers: ER17–261–005. PO 00000 Frm 00099 Fmt 4703 Sfmt 4703 81515 Applicants: Lawrenceburg Power, LLC. Description: Compliance filing: Lawrenceburg Informational Filing to be effective 12/1/2018. Filed Date: 9/30/24. Accession Number: 20240930–5288. Comment Date: 5 p.m. ET 10/21/24. Docket Numbers: ER17–262–005. Applicants: Waterford Power, LLC. Description: Compliance filing: Waterford Informational Filing to be effective 8/1/2018. Filed Date: 9/30/24. Accession Number: 20240930–5299. Comment Date: 5 p.m. ET 10/21/24. Docket Numbers: ER24–2448–002. Applicants: Wisconsin Electric Power Company. Description: Tariff Amendment: Notice Regarding August 28, 2024 Deficiency Letter to be effective 9/1/ 2024. Filed Date: 10/1/24. Accession Number: 20241001–5260. Comment Date: 5 p.m. ET 10/22/24. Docket Numbers: ER24–3059–000. Applicants: Dan’s Mountain Wind Force, LLC. Description: Supplement to 09/17/ 2024 Dan’s Mountain Wind Force, LLC tariff filing. Filed Date: 9/26/24. Accession Number: 20240926–5194. Comment Date: 5 p.m. ET 10/8/24. Docket Numbers: ER24–3158–000. Applicants: Public Service Company of New Mexico. Description: § 205(d) Rate Filing: Economic Benefit Contracts to be effective 10/1/2024. Filed Date: 9/30/24. Accession Number: 20240930–5280. Comment Date: 5 p.m. ET 10/21/24. Docket Numbers: ER24–3159–000. Applicants: Public Service Company of Colorado. Description: § 205(d) Rate Filing: 2024–09–30–PSC–SSL–AP–2023–3– APSISA–755–0.0.0 to be effective 10/1/ 2024. Filed Date: 9/30/24. Accession Number: 20240930–5326. Comment Date: 5 p.m. ET 10/21/24. Docket Numbers: ER25–1–000. Applicants: Consolidated Edison Company of New York, Inc. Description: § 205(d) Rate Filing: Amendment of CESD Surcharge 9–2024 to be effective 10/1/2024. Filed Date: 10/1/24. Accession Number: 20241001–5004. Comment Date: 5 p.m. ET 10/22/24. Docket Numbers: ER25–2–000. Applicants: Midcontinent Independent System Operator, Inc., Missouri Joint Municipal Electric Utility Commission. E:\FR\FM\08OCN1.SGM 08OCN1

Agencies

[Federal Register Volume 89, Number 195 (Tuesday, October 8, 2024)]
[Notices]
[Pages 81514-81515]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-23182]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15350-000]


BOST1 Hydroelectric, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On April 22, 2024, BOST1 Hydroelectric, LLC filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the proposed Lock and 
Dam No. 14 Hydroelectric Project, a hydropower project proposed to be 
located at the U.S. Army Corps of Engineers' (Corps) Mississippi Lock 
and Dam 14 located on the Mississippi River, near Hampton, Illinois. 
The sole purpose of a preliminary permit, if issued, is to grant the 
permit holder priority to file a license application during the permit 
term. A preliminary permit does not authorize the permit holder to 
perform any land-disturbing activities or otherwise enter upon lands or 
waters owned by others without the owners' express permission.
    The proposed Lock and Dam 14 Hydroelectric Project would consist of 
the following: (1) a 700-foot-long and 300-foot-wide intake area with 
trashracks; (2) a 150-foot-long and 78-foot-wide reinforced concrete 
powerhouse adjacent to the existing Corps dam; (3) three turbine-
generator units each with a rated capacity of 8.0 megawatts (MW), for a 
total installed powerhouse capacity of 24.0 MW; (4) a 150-foot-long 
tailrace; (5) a 2.5-mile-long underground transmission line extending 
from the switchyard adjacent to the powerhouse to the point of 
interconnect with the existing Mid-Atlantic Power 161 kilovolt 
transmission line; and (6) a rockfill dike extending 500 feet upstream 
and a deflection dike extending 900 feet downstream. The proposed 
project would have an estimated annual generation of 153.3 gigawatt-
hours.

[[Page 81515]]

    Applicant Contact: Douglas A. Spaulding, Nelson Energy, 1030 Tyrol 
Trail, Minnesota, MN 55416; phone: (612) 599-8493.
    FERC Contact: Shivani Khetani; phone: (212) 273-5917, or by email 
at [email protected].
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments 
up to 6,000 characters, without prior registration, using the eComment 
system at https://ferconline.ferc.gov/QuickComment.aspx. You must 
include your name and contact information at the end of your comments. 
For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Debbie-
Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any 
filing should include docket number P-15350-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at https://elibrary.ferc.gov/eLibrary/search. 
Enter the docket number (P-15350) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: October 1, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-23182 Filed 10-7-24; 8:45 am]