Clean Air Plans; Contingency Measures for the Fine Particulate Matter Standards; San Joaquin Valley, California, 80749-80766 [2024-22681]
Download as PDF
80749
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
portion of the Washington, DC-MD-VA
Nonattainment Area for the 2008 8-hour
ozone National Ambient Air Quality
Standard’’ to read as follows:
Subpart VV—Virginia
6. In § 52.2420, the table in paragraph
(e)(1) is amended by revising the entry
‘‘Maintenance plan for the Virginia
■
Name of non-regulatory SIP revision
*
*
*
*
*
Arlington, Fairfax, Loudoun, and Prince
William Counties and the Cities of Alexandria, Fairfax, Falls Church, Manassas, and Manassas Park.
*
*
*
*
*
7. In § 52.2428:
a. Remove the heading from paragraph
(h); and
■ b. Add paragraph (n).
The addition reads as follows:
■
■
§ 52.2428 Control Strategy: Carbon
monoxide and ozone.
*
*
*
*
*
*
*
Identification of plan.
*
*
(e) * * *
(1) * * *
State
submittal
date
Applicable geographic area
*
*
Maintenance plan for the Virginia portion
of the Washington, DC-MD-VA Nonattainment Area for the 2008 8-hour
ozone National Ambient Air Quality
Standard.
§ 52.2420
*
10/11/23
*
EPA approval
date
*
10/4/2024, [INSERT FEDERAL REGISTER CITATION].
*
(n) EPA approves updates to the 2008
8-Hour Ozone national ambient air
quality standard (NAAQS) maintenance
plan for the Virginia portion of the
Washington, DC-MD-VA 2008 8-Hour
Ozone NAAQS Maintenance Area. The
updates include revised motor vehicle
emissions budgets (MVEBs) and updates
to the applicable onroad and nonroad
mobile emissions for VOC and NOX for
the years 2025 and 2030. EPA also
*
Additional
explanation
*
Added § 52.2428(n).
*
*
approves the allocation of a portion of
the safety margins for VOC and NOX in
the ozone maintenance plan to the 2025
and 2030 MVEBs. The revised MVEBs
for VOC and NOX applies to all future
transportation conformity
determinations and analyses for the
entire Washington, DC-MD-VA
Maintenance Area for the 2008 8-Hour
Ozone NAAQS.
TABLE 5 TO PARAGRAPH (n)—REVISED ONROAD MOTOR VEHICLE EMISSIONS BUDGETS USING MOVES 3.0.4
VOC onroad
emissions
(tpd)
Year
2014
2025
2025
2025
2030
2030
2030
Attainment Year ..............................................................................................................................................
Predicted Emissions without Safety Margin ...................................................................................................
Safety Margin .................................................................................................................................................
Interim Budget with Safety Margin .................................................................................................................
Predicted Emissions without Safety Margin ...................................................................................................
Safety Margin .................................................................................................................................................
Final Budget with Safety Margin ....................................................................................................................
[FR Doc. 2024–22535 Filed 10–3–24; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
40 CFR Part 52
[EPA–R09–OAR–2023–0477; FRL–11532–
03–R9]
khammond on DSKJM1Z7X2PROD with RULES
Clean Air Plans; Contingency
Measures for the Fine Particulate
Matter Standards; San Joaquin Valley,
California
Environmental Protection
Agency (EPA).
ACTION: Final rule.
AGENCY:
The Environmental Protection
Agency (EPA) is taking final action to
approve two state implementation plan
(SIP) submissions under the Clean Air
SUMMARY:
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
Act (CAA) that address the contingency
measure requirements for the 1997
annual, 2006 24-hour, and 2012 annual
fine particulate matter (PM2.5) national
ambient air quality standards (NAAQS
or ‘‘standards’’) for the San Joaquin
Valley PM2.5 nonattainment area in
California. The two SIP submissions
include the area’s contingency measure
plan element and two specific
contingency measures that would apply
to residential wood burning heaters and
fireplaces and to non-agricultural, rural
open areas. A third contingency
measure, applicable to light-duty onroad motor vehicles, has been approved
into the California SIP in a separate
action by the EPA, and the related
emission reductions from the third
measure are accounted for in this final
rule. The EPA is finalizing approval of
the SIP submissions because the Agency
has determined that they are in
PO 00000
Frm 00035
Fmt 4700
Sfmt 4700
61.25
27.92
5.58
33.50
21.75
4.35
26.10
NOX onroad
emissions
(tpd)
136.84
46.52
9.30
55.82
34.26
6.85
41.11
accordance with the applicable
requirements for such SIP submissions
under the CAA and the EPA’s
implementing regulations for the PM2.5
NAAQS.
This rule is effective November
4, 2024.
DATES:
The EPA has established a
docket for this action under Docket ID
No. EPA–R09–OAR–2023–0477. All
documents in the docket are listed on
the https://www.regulations.gov
website. Although listed in the index,
some information is not publicly
available, e.g., Confidential Business
Information (CBI) or other information
whose disclosure is restricted by statute.
Certain other material, such as
copyrighted material, is not placed on
the internet and will be publicly
available only in hard copy form.
Publicly available docket materials are
ADDRESSES:
E:\FR\FM\04OCR1.SGM
04OCR1
80750
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
available through https://
www.regulations.gov, or please contact
the person identified in the FOR FURTHER
INFORMATION CONTACT section for
additional availability information. If
you need assistance in a language other
than English or if you are a person with
a disability who needs a reasonable
accommodation at no cost to you, please
contact the person identified in the FOR
FURTHER INFORMATION CONTACT section.
Rory
Mays, Planning and Analysis Branch
(AIR–2), Air and Radiation Division,
EPA Region IX, 75 Hawthorne St., San
Francisco, CA 94105; phone: (415) 972–
3227; email: mays.rory@epa.gov.
FOR FURTHER INFORMATION CONTACT:
SUPPLEMENTARY INFORMATION:
Throughout this document, ‘‘we,’’ ‘‘us’’
and ‘‘our’’ refer to the EPA.
Table of Contents
I. Background
A. Proposed Action
B. Changes to Proposed Action
II. Public Comments and EPA Responses
III. Environmental Justice Considerations
IV. EPA Action
V. Incorporation by Reference
VI. Statutory and Executive Order Reviews
I. Background
khammond on DSKJM1Z7X2PROD with RULES
A. Proposed Action
On December 20, 2023 (88 Federal
Register (FR) 87988), the EPA proposed
to approve California’s contingency
measure SIP submissions for the 1997
annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS submitted by the
California Air Resources Board (CARB)
for the San Joaquin Valley
nonattainment area in California.
Specifically, the SIP submissions
include the ‘‘PM2.5 Contingency
Measure State Implementation Plan
Revision (May 18, 2023)’’ (herein
referred to as the ‘‘SJV PM2.5
Contingency Measure SIP’’), revisions to
San Joaquin Valley Unified Air
Pollution Control District (SJVUAPCD
or ‘‘District’’) Rule 4901 (amended May
18, 2023) 1 that add PM2.5 NAAQS
contingency provisions that we refer to
herein as the ‘‘Residential Wood
Burning Contingency Measure,’’ and
revisions to Rule 8051 (amended
September 21, 2023) 2 that add PM2.5
NAAQS contingency provisions that we
refer to herein as the ‘‘Rural Open Areas
Contingency Measure.’’ CARB
submitted the SJV PM2.5 Contingency
Measure SIP and the Residential Wood
Burning Contingency Measure on June
1 SJVUAPCD Rule 4901 is titled ‘‘Wood Burning
Fireplaces and Wood Burning Heaters.’’
2 SJVUAPCD Rule 8051 is titled ‘‘Open Areas.’’
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
8, 2023,3 and the Rural Open Areas
Contingency Measure on October 16,
2023,4 as revisions to the California SIP.
In addition, in a separate proposed
rule also published on December 20,
2023, the EPA proposed approval of a
third contingency measure, applicable
to light-duty on-road motor vehicles,
and the related emission reductions
from the third measure are accounted
for in this final rule.5 We refer to the
third contingency measure as the ‘‘Smog
Check Contingency Measure.’’
We proposed to approve the SJV PM2.5
Contingency Measure SIP, the
Residential Wood Burning Contingency
Measure, and the Rural Open Areas
Contingency Measure because we
determined that they, along with
emission reductions from the Smog
Check Contingency Measure, comply
with the contingency measure SIP
requirements of CAA section 172(c)(9)
and EPA’s implementing regulations at
40 CFR 51.1014. We collectively refer
herein to CARB’s contingency measure
SIP submissions for the 1997 annual,
2006 24-hour, and 2012 annual PM2.5
NAAQS for the San Joaquin Valley as
the State’s ‘‘2023 SIP Submissions.’’
In sections I and II of the proposed
rule, we presented background
information on the 1997 annual and 24hour, the 2006 24-hour and 2012 annual
PM2.5 NAAQS, the nonattainment
designations and classifications of the
San Joaquin Valley for these PM2.5
NAAQS, and the resultant contingency
measure SIP obligations; summarized
our prior PM2.5 contingency measure
findings of failure to submit 6 and
disapprovals for the San Joaquin
Valley; 7 described the SIP submissions
at issue in this action; and provided the
basis for our preliminary conclusion
3 CARB adopted the SJV PM
2.5 Contingency
Measure SIP and Residential Wood Burning
Contingency Measure as SIP revisions on June 7,
2023, through Executive Order S–23–010 and
submitted the SIP revisions to the EPA
electronically on June 8, 2023, as attachments to a
letter dated June 7, 2023, from Steven S. Cliff,
Ph.D., Executive Officer, CARB to Martha Guzman,
Regional Administrator, EPA Region IX.
4 CARB adopted the Rural Open Areas
Contingency Measure as a SIP revision on October
13, 2023, through Executive Order S–23–014 and
submitted the SIP revision to the EPA electronically
on October 16, 2023, as an attachment to a letter
dated October 13, 2023, from Steven S. Cliff, Ph.D.,
Executive Officer, CARB to Martha Guzman,
Regional Administrator, EPA Region IX.
5 88 FR 87981 (December 20, 2023). We note that
the EPA finalized approval of the Smog Check
Contingency Measure. 89 FR 56222 (July 9, 2024).
6 83 FR 62720 (December 6, 2018). In response to
our finding of failure to submit, the EPA proposed
a Federal Implementation Plan (FIP) to address the
contingency measure requirements for the 1997
annual, 2006 24-hour and 2012 annual PM2.5
NAAQS at 88 FR 53431 (August 8, 2023).
7 86 FR 67343 (November 26, 2021) and 86 FR
67329 (November 26, 2021).
PO 00000
Frm 00036
Fmt 4700
Sfmt 4700
that the SIP submissions met applicable
procedural requirements.8 In section III
of the proposed rule, we summarized
the contingency measure SIP
requirements under the CAA and the
EPA’s implementing regulations,
relevant EPA guidance, and legal
precedent, including a brief discussion
of relevant decisions by the Ninth
Circuit Court of Appeals 9 and the D.C.
Circuit Court of Appeals.10 11
In addition, we described the EPA’s
long-standing approach to contingency
measures and the EPA’s revised
approach for addressing the contingency
measure SIP requirements, as presented
in the EPA’s draft guidance, entitled
‘‘Draft: Guidance on the Preparation of
State Implementation Plan Provisions
that Address the Nonattainment Area
Contingency Measure Requirements for
Ozone and Particulate Matter (DRAFT—
3/17/23—Public Review Version),’’
herein referred to as the ‘‘Draft Revised
Contingency Measure Guidance.’’ 12
Two principal differences between the
draft revised guidance and existing
guidance on contingency measures
relate to the EPA’s recommendations
concerning the specific amount of
emission reductions that
implementation of contingency
measures should achieve 13 and the
timing for when the emission reductions
from the contingency measures should
occur. The Draft Revised Contingency
Measure Guidance also provides
recommended procedures for
developing a demonstration, if
applicable, that the area lacks sufficient
feasible measures to achieve one year’s
worth (OYW) of reductions, building on
existing guidance that the state should
provide a reasoned justification for why
the smaller amount of emission
reductions is appropriate.
In section IV of the proposed rule, we
described the two specific District PM2.5
contingency measures proposed for
approval in this action (i.e., the
District’s Residential Wood Burning
8 88
FR 87988, 87989–87993 (December 20, 2023).
v. EPA, 836 F.3d 1218, 1235–1237 (9th Cir.
2016) and Assoc. of Irritated Residents v. EPA, 10
F.4th 937, 946–47 (9th Cir. 2021) (‘‘AIR v. EPA’’ or
‘‘AIR’’).
10 Sierra Club v. EPA, 21 F.4th 815, 827–828 (D.C.
Cir. 2021).
11 88 FR 87988, 87993–87994.
12 88 FR 87988, 87994. See also, 88 FR 17571
(March 23, 2023) (notice of availability of the EPA’s
Draft Revised Contingency Measure Guidance).
13 The EPA’s long-standing recommendation was
that states should adopt contingency measures
sufficient to provide emission reductions equivalent
to one year’s worth (OYW) of reasonable further
progress (RFP). In the Draft Revised Contingency
Measure Guidance, the EPA recommends a different
amount that contingency measures should
achieve—one that is defined in terms of OYW of
‘‘progress’’ rather than OYW of RFP.
9 Bahr
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
Contingency Measure and Rural Open
Areas Contingency Measure) and
provided our evaluation of the measures
relative to the requirements of CAA
section 172(c)(9) and 40 CFR 51.1014. In
short, we preliminarily concluded that
the contingency measures met the
requirements for such measures because
both measures are designed to be both
prospective and conditional, include
appropriate triggering mechanisms for
requirements, and are structured to be
implemented in a timely manner
without significant further action by the
District, CARB, or the EPA and to
achieve the estimated emission
reductions within roughly a year or two
of the triggering event.14 Furthermore,
both requirements that would be
triggered are not required for any other
CAA purpose, and the emission
reductions from the measures are not
included in any reasonable further
progress (RFP) or attainment
demonstration for the PM2.5 NAAQS in
the San Joaquin Valley. For these
reasons, we proposed to approve
District’s Residential Wood Burning
Contingency Measure and Rural Open
Areas Contingency Measure.15
In section V of the proposed rule, we
summarized how the District and CARB
had applied the revised approach to
fulfilling the contingency measure SIP
requirement in the context of the PM2.5
NAAQS in the San Joaquin Valley, and
we presented our evaluation thereof.16
Specifically, we discussed our
evaluation of the District’s and CARB’s
identification and evaluation of
potential control measures, adoption of
certain contingency measures,
comparison of those contingency
measures against OYW of emission
reductions, and reasoned justification
for not adopting further contingency
measures, which we recap in the
following paragraphs.
In the SJV PM2.5 Contingency Measure
SIP, the District described its ongoing
stationary source regulatory efforts,
identified potential control measures as
candidate contingency measures, and
analyzed the technological and/or
economic feasibility of each candidate
measure, including the feasibility of
implementing such measures within 60
14 88
FR 87988, 87995–87998.
khammond on DSKJM1Z7X2PROD with RULES
15 Id.
16 88
FR 87988, 87999–88009.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
days and achieving the resulting
emission reductions within one to two
years of the triggering event.17 The
District also provided more in-depth
analysis of potential control measures
for five source categories, ultimately
adopting measures for two source
categories (wood burning fireplaces/
heaters and rural open areas) and
providing a justification in the form of
an infeasibility demonstration for not
adopting contingency measures for the
other three source categories
(commercial charbroiling, almond
harvesting, and oil and gas production
combustion equipment).
Similarly, CARB identified potential
mobile source control measures,
assessed whether each candidate
measure could be implemented within
60 days of a triggering event and achieve
emission reductions within one to two
years, and then analyzed their
technological and/or economic
feasibility.18 Regarding timing of
emission reductions from mobile
sources, CARB concluded that new
engine standards and fleet regulations
are not appropriate for contingency
measures given the time needed for
manufacturers to design, develop, and
deploy cleaner engines or equipment at
scale, especially for zero-emission
equipment.
The District and CARB ultimately
adopted three contingency measures
identified through their respective
evaluation processes: the Residential
Wood Burning Contingency Measure,
the Rural Open Areas Contingency
Measure, and the Smog Check
Contingency Measure. Each of these
measures can be implemented without
further action by the District, CARB, or
the EPA and achieve emission
reductions within one to two years of
the triggering event, consistent with the
contingency measure requirements
under CAA section 172(c)(9) and the
EPA’s recommendations regarding
timing in the Draft Revised Contingency
Measures Guidance.19 In addition, the
revisions to SJVUAPCD Rule 4901
PM2.5 Contingency Measure SIP, pp. 9–11.
PM2.5 Contingency Measure SIP, section
5.3 (‘‘Measure Analysis’’); and Smog Check
Contingency Measure, Appendix A (‘‘Infeasibility
Analysis’’).
19 Draft Revised Contingency Measures Guidance,
pp. 40–42.
80751
establishing the Residential Wood
Burning Contingency Measure resolved
deficiencies identified in the EPA’s
disapproval of prior contingency
provisions in Rule 4901, thereby
ensuring that the direct PM2.5 and NOX
emission reductions will be achieved,
irrespective of which county may
exceed the applicable PM2.5 NAAQS at
the time of any finding of failure to
attain or other applicable
determination.20
The District then assessed how the
emission reductions from the
Residential Wood Burning Contingency
Measure would compare against OYW
of progress as defined in the Draft
Revised Contingency Measure
Guidance. As part of our evaluation and
for the proposed rule, we prepared an
independent assessment of the emission
reductions to include the two additional
contingency measures that were
adopted and submitted after the
submission of the SJV PM2.5
Contingency Measure SIP and to
provide a comparison of the emission
reductions relative to OYW of progress
to the long-standing recommendation of
OYW of RFP. In our proposed rule, we
found that the combined 0.5873 tons per
day (tpd) of direct PM2.5 emission
reductions from the District contingency
measures (for residential wood burning
and for rural open areas) would exceed
both OYW of RFP (0.44–0.58 tpd,
depending on the applicable PM2.5
NAAQS) and OYW of progress (0.41–
0.52 tpd, depending on the applicable
PM2.5 NAAQS).21
With respect to NOX emissions, the
combined 0.1647–0.1977 tpd emission
reductions from all three contingency
measures would provide a portion of the
reductions toward OYW of emission
reductions and, after consideration of
interpollutant trading of excess direct
PM2.5 emission reductions from the two
District contingency measures for
equivalent NOX emission reductions,
would amount to 1.3 percent (%) to
6.3% of OYW of RFP or 8.8% to 15.7%
of OYW of progress for NOX.22
17 SJV
18 SJV
PO 00000
Frm 00037
Fmt 4700
Sfmt 4700
20 88
FR 87988, 87996.
FR 87988, 88004–88005, Table 2 and Table
3. Note that CARB did not estimate any direct PM2.5
emission reductions from implementation of the
Smog Check Contingency Measure.
22 88 FR 87988, 88005.
21 88
E:\FR\FM\04OCR1.SGM
04OCR1
80752
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
As the NOX emission reductions fall
short of OYW of progress, CARB and the
District documented their control
measure analyses across the wide range
of source categories under each agency’s
respective jurisdiction (e.g., on-road
sources, off-road sources, stationary
point sources, and area sources) for NOX
emissions. We described the District’s
and CARB’s infeasibility
demonstrations, and our evaluation
thereof, in detail and proposed that they
adequately justify the contingency
measures selected by CARB and the
District for the 1997 annual, 2006 24hour, and 2012 annual PM2.5 NAAQS in
the San Joaquin Valley. In light of the
three adopted contingency measures
and reasoned justifications for not
adopting additional contingency
measures, we proposed to approve the
SJV PM2.5 Contingency Measure SIP, the
Residential Wood Burning Contingency
Measure, and the Rural Open Areas
Contingency Measure, taking into
account the emission reductions from
the Smog Check Contingency Measure
(as applied to the San Joaquin Valley),
as meeting the contingency measure
requirements of CAA section 172(c)(9)
and 40 CFR 51.1014 for these PM2.5
NAAQS in the San Joaquin Valley.
See our December 20, 2023 proposed
rule (88 FR 87988) for more information
on the SIP submissions and our
evaluation thereof.
Smog Check Contingency Measure by an
amount calculated by CARB to reflect
the effect of a decrease in Moyer
B. Changes to Proposed Action
Program funding in the San Joaquin
In our proposed rule, we evaluated
Valley if the Smog Check Contingency
the SIP submissions for compliance
Measure were triggered.24 However, in
with contingency measure SIP
our final rule approving the Smog Check
requirements, in part, by comparing the Contingency Measure SIP, we indicated
emission reductions from the
that we agreed with comments
contingency measures with OYW of
challenging the discount that we had
progress and OYW of RFP. In so doing,
applied and concluded that the discount
we relied on emissions estimates for the
was inappropriate due to timing
three individual contingency
considerations.25 By no longer
measures—two (the Residential Wood
discounting the emission reductions
Burning Contingency Measure and the
attributed to the Smog Check
Rural Open Areas Contingency
Contingency Measure, the estimates for
Measure) that we proposed to approve
total emission reductions for
in the proposed rule (and that we are
implementation of all three contingency
finalizing in this action) and one (the
Smog Check Contingency Measure) that measures are slightly greater than had
been presented in the proposed rule.
we proposed to approve in a separate
action.23 In Table 2 of the proposed rule, The change in emissions estimates and
percentages is minor and does not
we summarized the estimated emission
change any of the preliminary
reductions from the contingency
conclusions that we made in connection
measures, and in Table 3 of the
with our proposed action on the SJV
proposed rule, we presented the
PM2.5 Contingency Measure SIP.
estimated emission reductions as
Nonetheless, in the interest of
percentages of OYW of RFP and OYW
presenting the most accurate
of progress both with and without
information available, we are
trading emission reductions between
republishing Tables 2 and 3 to reflect
direct PM2.5 and NOX.
In both of these tables in the proposed the updated estimates of emission
reductions from the Smog Check
rule, we discounted the emission
Contingency Measure.
reductions from implementation of the
TABLE 2—REVISED ANNUAL AVERAGE EMISSION REDUCTIONS FROM DISTRICT AND CARB CONTINGENCY MEASURES
[tpd]
1997 Annual PM2.5
NAAQS
2006 24-Hour PM2.5
NAAQS
2012 Annual PM2.5
NAAQS
Contingency measure
Direct
PM2.5
NOX
Direct
PM2.5
NOX
Direct
PM2.5
NOX
District: Residential Wood Burning (first triggering event)
District: Non-agricultural Rural Open Areas ....................
CARB: Smog Check (first triggering event) .....................
0.5793
0.008
....................
0.0817
....................
0.117
0.5793
0.008
....................
0.0817
....................
0.120
0.5793
0.008
....................
0.0817
....................
0.086
Total ..........................................................................
0.5873
0.1987
0.5873
0.2017
0.5873
0.1677
TABLE 3—REVISED EPA EVALUATION OF DISTRICT AND CARB CONTINGENCY MEASURES AS PERCENTAGE OF ONE
YEAR’S WORTH OF RFP AND ONE YEAR’S WORTH OF PROGRESS
One year’s worth of RFP
PM2.5 NAAQS
Pollutant
1997 Annual ..............
Direct PM2.5 .............
NOX ..........................
Direct PM2.5 .............
NOX ..........................
Direct PM2.5 .............
NOX ..........................
khammond on DSKJM1Z7X2PROD with RULES
2006 24-hour .............
2012 Annual ..............
a The
Reductions
target
% OYW
(no trading)
0.44
16.7
0.58
18.4
0.46
15.3
One year’s worth of progress
% OYW
(with trading) a
132
1.2
101
1.1
129
1.1
Reductions
target
100
6.3
100
1.3
100
6.3
0.41
7.9
0.52
6.7
0.43
8.7
% OYW
(no trading)
% OYW
(with trading) a
142
2.5
112
3.0
138
1.9
100
b 15.8
100
b 8.9
100
13.1
EPA has calculated % OYW (With Trading) for NOX based on the 6:1 ratio presented in the SJV PM2.5 Contingency Measure SIP.
23 We proposed to approve the Smog Check
Contingency Measure SIP at 88 FR 87981.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
24 The Carl Moyer Program distributes incentive
grants to fund the incremental cost of cleaner-thanrequired engines, equipment, and other technology
and is funded, in part, by abatement fees that are
PO 00000
Frm 00038
Fmt 4700
Sfmt 4700
assessed on vehicles exempted from Smog Check
testing.
25 89 FR 56222, 56225.
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
80753
b The percentage of OYW of Progress (With Trading) is 0.1% higher in this table for NO for the 1997 annual and 2006 24-hour PM
X
2.5 NAAQS
relative to Table 3 of our proposed rule.
khammond on DSKJM1Z7X2PROD with RULES
II. Public Comments and EPA
Responses
The EPA’s proposed action provided
a 30-day public comment period. During
this period, we received comment
letters from three organizations or
groups. CARB submitted a letter
supporting the EPA’s proposed
approval.26 A group of four
environmental, public health, and
community organizations (collectively
referred to herein as ‘‘Valley EJ
Organizations’’) submitted adverse
comments,27 and a separate group of
five environmental, public health, and
community organizations (collectively
referred to herein as ‘‘CVAQ’’)
submitted adverse comments.28 To the
extent that certain comments by the
Valley EJ Organizations solely pertain to
the Smog Check Contingency Measure
and the State’s commitments to submit
attainment contingency measures for the
1997 ozone NAAQS, we have addressed
those comments in a separate final rule
on the Smog Check Contingency
Measure.29
Comment 1: The Valley EJ
Organizations assert that the EPA’s
proposed approval of the PM2.5
contingency measures departs from the
EPA’s long-standing interpretation
requiring OYW of RFP. They further
state that the proposed approvals based
on the Draft Revised Contingency
Measure Guidance violate CAA section
172(c)(9) by severing the amount of
required emission reductions from the
parallel and related RFP requirement
when the EPA shifts from its OYW of
RFP to its new OYW of progress
interpretation. The Valley EJ
Organizations further assert that the
plain meaning does not allow, and the
EPA cannot provide a reasoned
justification for, an interpretation that
requires less than that which the Act
requires for RFP and that, here, the
26 Letter dated January 17, 2024, from Steven S.
Cliff, Executive Officer, CARB, to Martha Guzman,
Regional Administrator, EPA Region IX.
27 Letter dated January 19, 2024, from Brent
Newell, Attorney for Central California
Environmental Justice Network, Committee for a
Better Arvin, Medical Advocates for Healthy Air,
and Healthy Environment for All Lives, to Jeffrey
Buss and Rory Mays, Air and Radiation Division,
EPA Region IX, including 16 exhibits (‘‘Valley EJ
Organizations Comment Letter’’).
28 Letter dated January 19, 2024, from Central
Valley Air Quality Coalition, National Parks
Conservation Association, Little Manila Rising,
Valley Improvement Projects, and Leadership
Counsel for Justice and Accountability, to Rory
Mays, Air and Radiation Division, EPA Region IX
(‘‘CVAQ Comment Letter’’).
29 89 FR 56222, 56224–56229.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
PM2.5 contingency measures plainly
provide reductions far less than OYW of
RFP. The CVAQ Comment Letter echoes
these points, stating that the emission
reductions from the Residential Wood
Burning Contingency Measure and the
Rural Open Areas Contingency Measure
would ‘‘fall well short of the emission
reductions needed to comply with the
weakened average annual reduction
requirement in EPA’s draft guidance
even when allowing for the
interpollutant substitution of excess
direct PM2.5 emissions for NOX
emissions.’’ 30
Response to Comment 1: Regarding
emission reduction metrics (i.e., the
recommended amount of emission
reductions that contingency measures
should achieve), we disagree with
commenters as to what is required
under the CAA and with the
commenters’ broader framing of
contingency measures within the overall
planning requirements for
nonattainment areas. While there is a
statutory link between RFP and the
contingency measure requirements of
CAA section 172(c)(9), it does not
function as the commenter suggests (i.e.,
to establish an amount of emission
reductions that contingency measures
should achieve). The statutory text of
this provision is as follows:
CAA section 172(c)(9) (‘‘Contingency
measures’’)—‘‘Such plan shall provide for the
implementation of specific measures to be
undertaken if the area fails to make
reasonable further progress, or to attain the
national primary ambient air quality standard
by the attainment date applicable under this
part. Such measures shall be included in the
plan revision as contingency measures to
take effect in any such case without further
action by the State or the Administrator.’’
Thus, while section 172(c)(9) requires
contingency measures where an area
fails to make RFP, the language does not
specify what amount of emission
reductions such measures should
achieve (i.e., does not explicitly tie the
amount of reductions to RFP).
Moreover, the statutory text also has a
link to attainment, but it too does not
specify what amount of emission
reductions contingency measures
should achieve.
While Congress did not specify an
amount that contingency measures must
achieve to comply with CAA section
172(c)(9), Congress must have intended
the amount to be material because,
without a specified amount, a state
would not know how to comply with
30 CVAQ
PO 00000
Comment Letter, p. 2.
Frm 00039
Fmt 4700
Sfmt 4700
the requirement. Thus Congress must
have at least implicitly delegated to the
EPA the authority to determine an
amount of emissions reductions that
contingency measures should achieve
and thereby give meaning to the
requirement and provide states with a
basis to comply with CAA section
172(c)(9) for a given nonattainment area.
The EPA has taken a policy approach to
this question, and in the past, the EPA
has indicated that the recommended
amount is OYW of RFP but allowed
states to provide a reasoned justification
for adopting contingency measures that
would provide less than the
recommended amount. Under the Draft
Revised Contingency Measure
Guidance, the EPA is continuing to take
a policy approach but is recommending
OYW of progress and describing a
specific analytical framework that states
may use to develop a reasoned
justification if the state is unable to
identify and adopt contingency
measures that can achieve the
recommended amount of emissions
reductions.31
In support of our revised approach,
we first note that, for both RFP and
attainment purposes, contingency
measures are intended to provide for
continued progress in the event that an
area fails to meet an RFP milestone or
fails to attain the NAAQS by the
applicable attainment date. They are not
themselves expected to provide for
either RFP or attainment. With respect
to RFP, the CAA provides certain
remedies if the contingency measures
do not make up the shortfall for a given
RFP milestone.32 With respect to a
failure to attain by the applicable
attainment date, the CAA too provides
a remedy by requiring a new attainment
plan.33
31 OYW of RFP is calculated differently for ozone
and particular matter (PM). For ozone, annual RFP
is essentially defined as three percent of the base
year emissions inventory (EI). For PM, annual RFP
is the average annual reductions between the base
year EI and the projected attainment year EI (i.e.,
the projected attainment inventory for the
nonattainment area). In contrast, OYW of progress
is calculated the same way for ozone and PM: by
determining the average annual reductions between
the base year EI and the projected attainment year
EI, determining what percentage of the base year EI
this amount represents, then applying that
percentage to the projected attainment year EI to
determine the amount of reductions needed to
ensure ongoing progress if contingency measures
are triggered. See also 88 FR 87988, 87994 and the
EPA’s Draft Revised Contingency Measure
Guidance, pp. 21–23.
32 See CAA sections 182(g)(3) and 189(c)(3).
33 See CAA section 179(d).
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
80754
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
In reviewing our long-standing
approach to contingency measures, the
EPA observed that basing the amount of
emission reductions on the annual
amount of reductions needed to meet
the separate RFP requirement—OYW of
RFP—may in some cases lead to an
amount that is greater than what
typically would be needed to make up
for a shortfall in RFP or for attainment
purposes.34 The OYW of RFP approach
was unnecessarily conservative for
estimating the amount of emission
reductions needed for contingency
measure purposes because a given
percentage of the base year inventory
tends to represent a much more
significant portion of the attainment
projected inventory.
In shifting to the OYW of progress
approach, the EPA recognizes
attainment of the NAAQS as the
primary objective of the nonattainment
plan requirements, and thus the
appropriate metric should be
attainment-focused. In the absence of a
CAA-specified amount of emission
reductions required for contingency
measures, the EPA’s new approach is a
better reading of the contingency
measure SIP requirement given our
understanding of the statutory purpose
of contingency measures following a
failure to attain or to meet an RFP
milestone, which is to ensure
uninterrupted progress toward
attainment while the next steps unfold
in response to the failure. In addition,
unlike the previous approach, the EPA’s
new approach takes into account the
declining emissions inventories
between the base year and attainment
year for a given nonattainment area and
aligns the metric for determining the
amount of emission reductions that
contingency measures should achieve
for ozone and particulate matter (PM).
The alignment between ozone and PM
is a better reading of the statute
considering that the relevant statutory
provision, CAA section 172(c)(9),
applies to all the NAAQS.
As to the specific SIP submission
addressed in this document, we
acknowledge that CARB and the District
used the newly-recommended metric in
preparing the SJV PM2.5 Contingency
Measure SIP for which the EPA is now
finalizing approval but, in this instance,
the SIP submission and the EPA’s
evaluation thereof would have been the
same in substance if the previous metric
(i.e., OYW of RFP) had been used
instead. This is because, using either
metric, the SIP submissions include
contingency measures that collectively
34 EPA’s Draft Revised Contingency Measures
Guidance, pp. 21–23.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
provide for OYW of progress or RFP for
direct PM2.5 and a portion of OYW of
progress or RFP for NOX.35 The only
difference is the extent to which the
emission reductions from the
contingency measures fall short of each
metric for NOX reductions. Using the
OYW of progress metric (with trading),
the contingency measures are estimated
to achieve between 8.9% and 15.8% of
OYW of progress for NOX as compared
to between 1.3% and 6.3% of OYW of
RFP for NOX using the previouslyrecommended metric (with trading).36
Using either metric, the EPA would
have expected the State to provide a
reasoned justification for not adopting
contingency measures sufficient to
achieve greater NOX emission
reductions; consistent with the EPA’s
recommendations in the Draft Revised
Contingency Measure Guidance, CARB
and the District provided such reasoned
justification in their infeasibility
demonstrations.
Comment 2: The Valley EJ
Organizations assert that the EPA’s
proposed approval of the State’s 2023
SIP Submissions circumvents three
recent court decisions 37 and unlawfully
and arbitrarily (a) lowers the amount of
emission reductions required for
contingency measures (‘‘by severing the
statutory link to [RFP],’’ i.e., by shifting
from OYW of RFP under the EPA’s prior
interpretation to OYW of progress under
the EPA’s revised interpretation), (b)
extends implementation of contingency
measures from one year to two years,
and (c) invents a new feasibility
exemption that does not appear in CAA
section 172(c)(9). The commenters state
that the EPA’s proposed approval relies
on the Draft Revised Contingency
Measures Guidance ‘‘to replicate the
arbitrary and capricious interpretation
the [AIR] court invalidated.’’
Response to Comment 2: In relevant
part, the Bahr and Sierra Club decisions
stand for the proposition that
contingency measures under CAA
section 172(c)(9) must be conditional
and prospective, and thus, alreadyimplemented control measures cannot
serve as contingency measures. The AIR
decision stands for the proposition that
surplus emission reductions from
already-implemented measures cannot
be relied upon as a justification for
adoption of contingency measures that
provide for less than the recommended
amount of emission reductions for such
measures. However, none of the cited
35 See
Table 3 of this final rule.
Table 3 of this final rule.
37 The commenter cites Bahr v. EPA, 836 F.3d
1218 (9th Cir. 2016) (‘‘Bahr’’); Sierra Club v. EPA,
21 F.4th 815 (D.C. Cir. 2021) (‘‘Sierra Club’’); AIR
v. EPA, 10 F.4th 937 (9th Cir. 2021) (‘‘AIR’’).
36 See
PO 00000
Frm 00040
Fmt 4700
Sfmt 4700
court decisions bear on the questions of
the amount of emission reductions that
contingency measures should achieve,
the timeline for achieving the emission
reductions from contingency measures,
or the consideration of feasibility of
additional measures as justification for
not adopting contingency measures
sufficient to achieve the recommended
amount of such measures.
Moreover, our proposed approval of
the SJV PM2.5 Contingency Measure SIP
is consistent with the three cited
decisions in that the SIP relies on
contingency measures (Residential
Wood Burning Contingency Measure,
the Rural Open Areas Contingency
Measures, and the Smog Check
Contingency Measure) that are designed
to be conditional and prospective. In
addition, as discussed further in the
following paragraph, the State has not
relied on emission reductions from
already-implemented measures.
The rationale for our approval of the
SJV PM2.5 Contingency Measure SIP is
not the same as the rationale for our
approval, later withdrawn in response
to the AIR decision, of the contingency
measure element for San Joaquin Valley
for the 2008 ozone NAAQS that was at
issue in the AIR case. In the case of the
contingency measure element for the
2008 ozone NAAQS, the EPA took into
account the surplus emission reductions
from already-implemented measures in
the milestone years and the years
following the attainment date, not as
constituting contingency measures per
se, but rather, as justification for
approving a contingency measure
element that included a single
contingency measure that would
provide for far less than the
recommended amount.
The Court found that, by doing so, the
EPA had ‘‘severed the relationship
between the requirement of contingency
measures and the benchmark of
reasonable further progress, without an
adequate explanation of why the new—
and far more modest—contingency
measure is reasonable.’’ 38 The Court did
not indicate that the Agency could not
depart from previous guidance but
cautioned that the EPA ‘‘must give a
reasoned explanation for departing from
agency practice or policy.’’ 39 The Court
concluded that ‘‘[I]f alreadyimplemented measures cannot
themselves be contingency measures—
and Bahr makes clear that they cannot—
then neither can they be a basis for
declining to establish contingency
measures that would otherwise be
38 AIR
v. EPA, 10 F.4th 937, 946 (9th Cir. 2021).
39 Id.
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
appropriate.’’ 40 The Court rejected the
EPA’s rationale for allowing
consideration of surplus emission
reductions from already-implemented
measures, reasoning that the EPA could
not approve a contingency measure
element ‘‘lacking robust contingency
measures by assuming that they will not
be needed. Because the agency did not
provide a reasoned explanation for
approving the state plan, the rule is
arbitrary and capricious.’’ 41
In the wake of the AIR decision, and
other case law interpreting the
contingency measure SIP requirement,
the EPA undertook an internal process
to reconsider previous guidance
provided by the Agency to states for
preparation of SIP submissions to meet
the contingency measure
requirements—a process that led to the
publication of the Draft Revised
Contingency Measure Guidance. Among
other things, in the Draft Revised
Contingency Measure Guidance, the
EPA explains why the Agency believes
that it is appropriate to update its prior
guidance with respect to the
recommended amount of emission
reductions that contingency measures
should achieve and the considerations
that states could use to justify adoption
of contingency measures that do not
provide for the recommended amount of
emission reductions.42 We found that an
update to our contingency measures
guidance was justified in light of
changed factual circumstances 43 and a
current understanding of what
remaining controls may be available for
states to adopt as contingency measures.
For a more detailed explanation of our
rationale for updating the metric, see
Response to Comment 1, and for a more
detailed explanation for allowing for
consideration of feasibility, see
Response to Comment 4.
With respect to this action, CARB and
the District have adopted a contingency
measure element that includes three
40 Id.
41 Id.
at 947.
Draft Revised Contingency Measure
Guidance, pp. 21–28 (revised metric) and pp. 29–
40 (reasoned justification for adoption of
contingency measures that provide for less than the
recommended amount of emission reductions).
43 By ‘‘changed circumstances,’’ we are referring
to recent court decisions that have invalidated key
aspects of EPA’s historical approach to
implementing the contingency measure
requirement and the evolution toward more
stringent control programs in the 30 years since the
EPA first articulated its contingency measure
guidance where, as described in Response to
Comments 3, the progressively stringent control
measures adopted to meet prior attainment and RFP
planning requirements are already implemented
measures and therefore ineligible to serve as
contingency measures and result in a narrowing
pool of candidate contingency measures.
khammond on DSKJM1Z7X2PROD with RULES
42 EPA’s
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
contingency measures that would
collectively achieve the recommended
amount of emission reductions for one
of the two pollutants or precursors at
issue, and they have provided a
reasoned justification in the form of
infeasibility demonstrations for
adopting contingency measures that
provide for less than the recommended
amount for the other relevant pollutant
or precursor. The EPA’s approval of a
contingency measure element that
relies, in part, on CARB and the
District’s infeasibility demonstrations,
rather than relying on surplus emission
reductions from already-implemented
measures, stands in contrast to the EPA
action on the SIP submission at issue in
AIR. The EPA does not assume that
contingency measures would not be
needed for San Joaquin Valley but rather
that CARB and the District have
adequately demonstrated that there are
no feasible contingency measures for
that particular pollutant or precursor
that are left to adopt or that could be
implemented within one to two years of
the triggering event.
Comment 3: For areas with more
severe air pollution, such as Serious
PM2.5 nonattainment areas, the
commenters state that the EPA has not
articulated a reasoned justification for
why OYW of progress is consistent with
the CAA remedial scheme that imposes
more stringent requirements on such
areas. They suggest that a voluntary
reclassification of an area (e.g., from
‘‘Moderate’’ to ‘‘Serious’’ for PM2.5)
would lower the average annual
reductions needed for contingency
measures (e.g., if the same attainment
year inventory applied for a Moderate or
Serious areas, then the annual average
reduction would be lower due to
averaging over more years).
In addition, the commenters illustrate
a purported fatal flaw in the EPA’s
interpretation of OYW of progress using
a table that shows OYW of progress for
NOX in a hypothetical ozone
reclassification from Serious to Extreme
(in tons per day of NOX) and state that
a lesser amount of emission reductions
for contingency measures for such
hypothetical Extreme ozone
nonattainment area runs contrary to the
structure of the Act.
Response to Comment 3: As explained
in more detail in our Response to
Comment 1, with respect to this specific
action, the use of the new OYW of
progress metric here does not materially
impact our approval where the SJV
PM2.5 Contingency Measure SIP falls
short of the emissions reductions
recommended under either metric.
However, we note that, contrary to
commenters’ assertions, the EPA’s
PO 00000
Frm 00041
Fmt 4700
Sfmt 4700
80755
interpretation of the contingency
measure requirement under CAA
section 172(c)(9) is consistent with the
CAA’s general scheme of subjecting
areas with higher classifications to more
stringent requirements. More
specifically, the increased stringency
relates to the types of measures that
qualify as contingency measures rather
than the amount of emission reductions
that such measures must achieve.
Under the EPA’s interpretation of the
contingency measure requirement,
contingency measures must be designed
to provide emission reductions (if
triggered) that are not otherwise
required to meet other attainment plan
requirements and not relied upon to
demonstrate RFP nor attainment. Thus,
for example, contingency measures in
PM2.5 nonattainment areas classified as
Moderate, which are thereby subject to
the reasonably available control
measures (RACM) requirement, must be
measures that go beyond the RACM
requirement, whereas contingency
measures in PM2.5 nonattainment areas
classified as Serious (and thus subject to
the best available control measures
(BACM) requirement) must be measures
that go beyond the BACM requirement.
In other words, reclassification of an
area to a higher classification shrinks
the pool of candidate contingency
measures because some of the candidate
contingency measures will be required
to be adopted and implemented in the
reclassified area to meet the specific
control requirements for that
classification and, thus, will be
unavailable for adoption as contingency
measures. The candidate contingency
measures that remain eligible to meet
the contingency measure SIP
requirement under the higher
classification are different, and
potentially more stringent, than those
that had been available to meet the
requirement under the lower
classification. While more stringent
measures would achieve further
emission reductions, if triggered, they
may achieve a smaller scale of emission
reductions than the prior iterations of
increasingly stringent control measures
on a given emission source; stringency
(a relative measure) is not the same as
tons per day of emission reductions (an
absolute measure).
Regarding the commenters’ assertion
that areas with more severe air pollution
should have contingency measures that
achieve a larger amount of emission
reductions (i.e., OYW of RFP), we look
once more to the broader framing of
contingency measures within the overall
planning requirements for
nonattainment areas. The EPA finds that
the statutory and regulatory
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
80756
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
requirements to demonstrate attainment
as expeditiously as practicable, and the
absence of a specific statutory metric for
how much emission reductions
contingency measures should achieve,
give priority to adopting control
measures to attain in the first place,
even if that leaves fewer options for
contingency measures in the event of a
failure to attain or to make RFP.
In the SJV PM2.5 Contingency Measure
SIP, the State elaborates further on using
an attainment-focused metric by
highlighting the scarcity of potential
control measures that would qualify as
contingency measures given the facts
and circumstances of the San Joaquin
Valley,44 where the progressively
stringent set of control measures
adopted to meet prior attainment and
RFP planning requirements are already
implemented measures and therefore
ineligible to serve as contingency
measures.45 This scarcity concept
echoes the tension between the CAA
requirements for attainment and
contingency measures, and the
prioritization of adopting measures to
attain in the first place.
Notwithstanding, the EPA does not
endorse the scarcity concept as a
starting point, but rather recommends
the detailed analytical approach to
identifying and evaluating potential
control measures that can serve as
contingency measures, as described in
the Draft Revised Contingency Measures
Guidance, and that the State employed
in developing the PM2.5 Contingency
Measure SIP.
Regarding the commenters’ suggestion
that a state could reduce the amount of
emission reductions needed for
contingency measures by requesting a
voluntary reclassification that would
extend the amount of time to attain
while relying on the same level of
emission reductions, we disagree that
such an action runs contrary to the
general remedial scheme of the CAA
that imposes more stringent
requirements on reclassified areas.
Under the statutory and regulatory
requirements for PM2.5, a State may
request reclassification from Moderate
to Serious, but only where it can show
that it is impracticable to attain by the
Moderate area attainment year.46 Thus,
a combination of direct PM2.5 and plan
precursor emission reductions that
would achieve attainment would
constrain the ability of the State to seek
44 SJV PM
2.5 Contingency Measure SIP, section
4.1 (‘‘Stringency of District’s Regulatory Program’’)
and section 5.2 (‘‘CARB’s Opportunities for
Contingency Measures’’).
45 SJV PM
2.5 Contingency Measure SIP, pp. 53–54.
46 CAA section 188(b)(1) and 40 CFR
51.1002(b)(1).
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
such reclassification—it would instead
be practicable to attain by the Moderate
area attainment date. Similarly, if the
Moderate area attainment year were
approaching and air quality for two of
three design value years indicated that
the area would not achieve the standard,
then the air quality basis resulting from
prior attainment planning would be
insufficient to attain. In either case, the
State would need to develop a Serious
area plan that achieves additional
emission reductions and also addresses
the additional control requirements for
Serious areas (e.g., tighter new source
review requirements, BACM and best
available control technology (BACT),
and, if the State were to seek an
attainment date extension under CAA
section 188(e), most stringent measures
(MSM)).
For these reasons, as well as those
described in Response to Comment 1 of
this document, we conclude that the
EPA’s revised metric for contingency
measure emission reductions (OYW of
progress) does not run contrary to the
general remedial scheme of the CAA
that imposes more stringent
requirements on areas reclassified to a
higher classification. Lastly, the EPA
finds that the comment on a
hypothetical scenario for an ozone
nonattainment area is outside the scope
of this rulemaking because we are not
acting on ozone contingency measure
SIP submissions in this action.
Comment 4: Regarding feasibility
assessments, the Valley EJ Organizations
state that the CAA does not subject the
contingency measure requirements to a
feasibility standard and reject the State’s
and the EPA’s proposed reliance on
infeasibility demonstrations. The
commenters argue that Congress made
no exceptions to the contingency
measure requirements nor did it provide
authority to relax those requirements
based on technological or economic
challenges. They state that the CAA
requirements for RACM or reasonably
available control technology (RACT)
include a ‘‘reasonably available’’
qualifier and that those for MSM are
expressly limited to ‘‘feasible’’
measures, while such terms do not
appear in the CAA requirements for
contingency measures. They contend
that the EPA conflates the contingency
measure requirements with the primary
requirements to attain the NAAQS in
the first place. They further state that
Congress expressly provided limited
authority to relax the CAA requirements
for RFP but did not do so for
contingency measures.
The commenters state that the RACM
requirements (under CAA sections
172(c)(1), 181(a)(1), and 188(c)(1))
PO 00000
Frm 00042
Fmt 4700
Sfmt 4700
require that the primary attainment
strategy include ‘‘all’’ RACM and other
available control measures that would
expedite attainment and that the MSM
provision (for Serious PM2.5
nonattainment areas that cannot attain
the standards within 10 years, under
CAA section 188(e)) requires additional
control measure implementation. They
argue that contingency measures should
not comprise the same controls that the
CAA already requires for attainment and
that failed to attain the NAAQS in the
first place and that the EPA unlawfully
and arbitrarily excuses contingency
measures needed when the feasible
measures the State has already adopted
result in a failure to attain the NAAQS
(citing AIR, 10 F.4th at 946).
Given these alleged flaws in the EPA’s
interpretation, the commenters state that
the EPA’s proposed approval violates
the plain meaning of the CAA
contingency measure requirement, fails
to reasonably explain the Agency’s
relaxation of the emission reductions
that contingency measures must
provide, and is therefore arbitrary and
capricious.
Response to Comment 4: As discussed
in Response to Comment 1, Congress
must have at least implicitly delegated
to the EPA the authority to determine an
amount of emissions reductions that
contingency measures should achieve
and thereby give meaning to the
requirement and provide states with a
basis to comply with CAA section
172(c)(9) for a given nonattainment area.
The EPA is continuing to take a policy
approach to this question and is
recommending OYW of progress and
describing a specific analytical
framework that states may use to
develop a reasoned justification if the
state is unable to identify and adopt
contingency measures that can achieve
the recommended amount of emissions
reductions. More specifically, as stated
in our proposed rule and the EPA’s
Draft Revised Contingency Measures
Guidance, where a state is unable to
identify contingency measures that
would provide approximately OYW of
emission reductions, the state should
provide a reasoned justification
(referred to herein as an ‘‘infeasibility
demonstration’’) that explains and
documents how it has evaluated all
existing and potential control measures
relevant to the appropriate source
categories and pollutants in the
nonattainment area and has reached
reasonable conclusions regarding
whether such measures are feasible.47
Thus, while the EPA acknowledges that
47 88 FR 87988, 87994 and EPA’s Draft Revised
Contingency Measure Guidance, p. 29.
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
CAA section 172(c)(9) does not
explicitly provide for consideration of
whether specific measures are feasible,
the EPA does not read the statute to
require air agencies to adopt and impose
infeasible measures.48
As stated in the proposed rule, the
statutory provisions applicable to other
nonattainment area plan control
measure requirements, including
RACM/RACT, BACM/BACT, and MSM,
allow air agencies to exclude certain
control measures that are deemed
unreasonable or infeasible (depending
on the requirement).49 For example, the
MSM provision in CAA section 188(e)
requires plans to include ‘‘the most
stringent measures that are included in
the implementation plan of any state or
are achieved in practice in any state,
and can feasibly be implemented in the
area.’’ While the contingency measures
provisions do not include such caveats,
the EPA does not conclude that the
contingency measures provisions
should be read to require plans to
include infeasible measures. Thus, the
EPA anticipates that a demonstrated
lack of feasible measures would be a
reasoned justification for adopting
contingency measures that achieve less
than the recommended amount of
emission reductions.50
The EPA does not, as the commenters
suggest, simply conflate the contingency
measure requirements with other
control requirements (e.g., RACM/
RACT, BACM/BACT, and MSM) that are
integral to demonstrating attainment of
the ozone and/or PM2.5 NAAQS. Rather,
while the analytical approach to
identifying and evaluating existing and
potential control measures may be
similar to those used for RACM/RACT,
BACM/BACT, and MSM (e.g.,
48 Id.
khammond on DSKJM1Z7X2PROD with RULES
49 Id.
50 Moreover, we note that contingency measures
under CAA section 172(c)(9), once triggered, are
generally permanent and become one of the
baseline control measures for the next milestone
demonstration or the new attainment plan that must
be adopted and submitted by the state for an area
that has failed to attain the NAAQS by the
applicable attainment date. As noted in this
document, technological and economic feasibility is
a hallmark of such control measures. In contrast,
CAA section 110(a)(2)(G) requires states to adopt
and submit contingency plans to address emergency
episodes as part of their SIPs, and the contingency
plans for emergency episodes identify emission
control actions to be taken at different episode
levels, which are much higher than the NAAQS,
without consideration of economic or technological
feasibility. See, generally, 40 CFR 51.150–51.152
and appendix L to 40 CFR part 51. One significant
difference, however, between the emission control
actions for emergency episode plans under CAA
section 110(a)(2)(G) and the control measures relied
upon for RFP and attainment is that the former are
temporary and are implemented only while the
emergency episode persists whereas the latter are,
as noted, permanent controls for the area.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
identifying the universe of control
devices that can reduce NOX emissions
from combustion equipment and
whether they are technologically and
economically feasible as applied to a
specific type of emission source in the
area), the EPA expects that the state
‘‘should not simply repeat the control
strategy’s infeasibility showing.’’ 51 The
contingency measure requirement is in
addition to the other control measure
requirements.
A conclusion that a measure is not
reasonable or feasible, for example, for
RACM does not automatically disqualify
it as a potential contingency measure. If
the state identifies control measures that
it determines are not needed to attain
nor to collectively advance attainment,
those measures would not be required to
satisfy the RACM requirement but
would remain as candidates for
contingency measures. To the extent
that the adopted contingency measures
achieve a small amount of emission
reductions, the state should provide a
more robust infeasibility showing that
there are no additional feasible
contingency measures that could
achieve the recommended amount of
reductions.52 Furthermore, to the extent
that the state’s analyses and
development of contingency measures
occur after the state’s analyses and
development of the SIP submissions to
meet the attainment control strategy
requirements of the CAA (including
associated control requirements and
RFP), the state should update their
analyses to reflect the latest potential
control measures.
In the case of the SJV PM2.5
Contingency Measure SIP, submitted in
2023, CARB and the District
documented their analyses to identify
and evaluate potential control measures
that might serve as contingency
measures. These analyses are updated
relative to their 2021 submission of the
Serious area attainment plan for the
1997 annual PM2.5 NAAQS and to their
2019 submissions of the Serious area
attainment plan for the 1997 24-hour
PM2.5 NAAQS (including BACM
demonstration), Serious area plan for
the 2006 24-hour PM2.5 NAAQS
(including demonstrations for BACM
and MSM), and Moderate area plan for
the 2012 annual PM2.5 NAAQS
(including RACM demonstration). The
EPA has approved these attainment plan
control strategies in successive
actions 53 and they represent an overall
51 EPA’s Draft Revised Contingency Measure
Guidance, p. 31.
52 EPA’s Draft Revised Contingency Measure
Guidance, p. 31.
53 88 FR 86581 (December 14, 2023) (approving
the State’s demonstrations for BACM and five
PO 00000
Frm 00043
Fmt 4700
Sfmt 4700
80757
stringent set of control requirements.
The State did not set aside measures for
lack of their ability to collectively
advance attainment (as might be
possible in theory, e.g., for RACM for an
ozone nonattainment area).
In their updated analyses, CARB and
the District considered the wide range of
emission sources under their primary
jurisdiction, identified potential control
measures, analyzed their technological
and economic feasibility, and assessed
whether they could achieve emission
reductions within one to two years of a
triggering event, consistent with the
EPA’s discussion of the timing objective
inherent to the contingency measure
requirement.54 For the potential control
measures identified through this
process, the District further analyzed
possible contingency measures for wood
burning fireplaces and wood burning
heaters, rural open areas, commercial
charbroiling, almond harvesting, and oil
and gas production combustion
equipment, and ultimately adopted the
Residential Wood Burning Contingency
Measure and the Rural Open Areas
Contingency Measure.
CARB, in turn, made a reasonable
case that new engine standards and new
fleet requirements require more time to
implement than would be appropriate
for contingency measures (i.e., would
exceed one to two years after a
triggering event) and that the State’s
technology-forcing and zero-emissionbased nature of its mobile source
regulations reduce or eliminate
opportunities for yet-further emission
reductions that could qualify as
contingency measures.55 Nevertheless,
through its process CARB ultimately
adopted the Smog Check Contingency
Measure.
The three contingency measures
proposed for approval stand in contrast
to the commenters’ argument that the
feasibility assessment process put
forward in the EPA’s Draft Revised
Contingency Measure Guidance, in the
State’s 2023 SIP Submissions, and the
EPA’s proposed approval thereof would
simply re-employ the control measures
originally employed to attain the PM2.5
NAAQS in the San Joaquin Valley.
Furthermore, in many instances the
percent annual emission reductions under CAA
section 189(d) for the 1997 annual PM2.5 NAAQS);
87 FR 4503 (January 28, 2022) (approving the
State’s BACM demonstration for the 1997 24-hour
PM2.5 NAAQS); and 85 FR 44192 (July 22, 2020)
(approving the State’s demonstrations for BACM
and MSM for the 2006 24-hour PM2.5 NAAQS).
54 88 FR 87988, 88000–88001 (summary of State’s
feasibility analyses), and 88005–88009 (the EPA’s
evaluation of the State’s feasibility analyses). See
also Draft Revised Contingency Measures Guidance,
pp. 40–42.
55 88 FR 87988, 88008–88009.
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
80758
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
reason for which the EPA agreed with
the State for not adopting a potential
control measure as a contingency
measure was not based on any
affirmation that a measure was
economically infeasible, but rather was
based on other reasons. In evaluating
CARB and the District’s infeasibility
demonstrations in the SJV PM2.5
Contingency Measure SIP, we relied
heavily on the ‘‘EPA Source Category
and Control Measure Assessment and
Reasoned Justification Technical
Support Document, Proposed
Contingency Measures Federal
Implementation Plan for the Fine
Particulate Matter Standards for San
Joaquin Valley, California,’’ July 2023
(‘‘EPA’s Reasoned Justification TSD’’)
given its breadth and depth, as well as
the expertise of EPA Region IX staff, to
review the State’s demonstrations,
understand where the State’s analyses
and the EPA’s analyses draw largely
similar conclusions, and identify those
source categories where the control
measure analyses differ.
For example, for the potential control
measure of requiring electric water
heaters and furnaces at point of sale, the
EPA determined that such a measure
would not be feasible because we expect
that it would result in negligible
emission reductions within two years
after trigger, consistent with the
District’s suggestion that the attritionbased nature of implementation of this
contingency measure option deem the
measure infeasible.56 For the potential
control measure of requiring low-dust
almond harvesters, the EPA determined
that such a measure would be infeasible
based only on the timing of emission
reductions.57
For the potential control measure of
requiring the installation of control
devices on commercial under-fired
charbroilers, the EPA determined that
such measure would be infeasible based
on fire safety certification concerns and
lack of demonstrated implementation of
controls.58 For the potential control
measure of lower NOX emission limits
on oil and gas production equipment
with a total rated heat input of greater
than 5.0 million Btu per hour, the EPA
determined that it would be
technologically infeasible to meet the
lower limits within the two-year
timeframe for contingency measures due
to the likely requirement that affected
units would need to install selective
catalytic reduction (SCR) devices to
56 88 FR 87988, 88007, and EPA’s Reasoned
Justification TSD, pp. 43–51.
57 88 FR 87988, 88007, and EPA’s Reasoned
Justification TSD, pp. 43–51.
58 88 FR 87988, 88008, and EPA’s Reasoned
Justification TSD, chapter V.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
meet the lower limits (i.e., the planning,
engineering, and installation of SCR
would take more than two years).59
Similarly, for the potential control
measure of lower NOX emission limits
for boilers, steam generators, and
process heaters with a total rated heat
input of 5.0 million Btu per hour or less,
the EPA expects that units required to
meet lower limits than those already
adopted in Rules 4307 and 4308 would
require installation of SCR, which
cannot be feasibly achieved within the
two-year timeframe for contingency
measures.60
In sum, the EPA maintains that it does
not read the statute to require air
agencies to adopt and impose infeasible
measures. Furthermore, as applied to
the SIP submissions subject to this
rulemaking, we continue to find that the
State’s three contingency measures for
the San Joaquin Valley for the 1997
annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS, in conjunction with the
State’s infeasibility demonstrations that
adequately justify the contingency
measures selected by the State, meet the
contingency measure requirement under
CAA section 172(c)(9) and 40 CFR
51.1014.
Comment 5: The Valley EJ
Organizations assert that the EPA
unlawfully and arbitrarily proposes
approval of the PM2.5 contingency
measures based on the Agency’s new
interpretation in the Draft Revised
Contingency Measures Guidance by
extending the implementation period
from one year to two years.
Response to Comment 5: With respect
to the issue of extending the period in
which the emission reductions from
contingency measures can be
considered in meeting the contingency
measure SIP requirement, we note that
the commenters raise this particular
objection to the EPA’s proposed
approval in a single sentence and fail to
elaborate on how extending the time
period for achieving the emission
reductions from contingency measures
from one to two years conflicts with the
CAA or the EPA’s implementing
regulations.
In this instance, we proposed, and are
now taking final action, to approve two
specific contingency measures (the
Residential Wood Burning Contingency
Measures and the Rural Open Areas
Contingency Measures), both of which,
if triggered, will achieve emission
reductions within a year of the
triggering event. Our approval of the
59 88 FR 87988, 88008, and EPA’s Reasoned
Justification TSD, pp. 9–22.
60 88 FR 87988, 88008, and EPA’s Reasoned
Justification TSD, pp. 9–22.
PO 00000
Frm 00044
Fmt 4700
Sfmt 4700
2023 SIP Submissions as meeting the
contingency measure SIP requirement
for San Joaquin Valley for the relevant
PM2.5 NAAQS also relies on emission
reductions from a third contingency
measure (the Smog Check Contingency
Measure) that we have approved in a
separate action.
As explained in the EPA’s final rule
on CARB’s Smog Check Contingency
Measure, the emission reductions from
the Smog Check Contingency Measure
may not be fully achieved until the
second year after the triggering event.61
However, as further explained in that
final rule, and consistent with the Draft
Revised Contingency Measure
Guidance, in instances where there are
insufficient contingency measures
available to achieve the recommended
amount of emission reductions within
one year of the triggering event,
contingency measures that provide
reductions within two years of the
triggering event could be appropriate to
consider toward achieving the
recommended amount of emission
reductions.62 Contingency measures
that result in additional emission
reductions during the second year
following the triggering event, as
contemplated by the Draft Revised
Contingency Measure Guidance, can
still serve the important purpose of
contingency measures to continue
progress toward attainment, as the State
develops and submits, and the EPA acts
on, a SIP submission to address the
underlying condition (e.g., failure to
make RFP or to attain by the applicable
attainment date) that triggered the
contingency measures in the first place.
Comment 6: The Valley EJ
Organizations state that, after a first
triggering event, the EPA unlawfully
and arbitrarily allows California
discretion in adopting further
contingency measures, fails to evaluate
whether the emission reductions to
follow a second triggering event would
meet either OYW of RFP or OYW of
progress, and allows California to
‘‘ ‘double dip’ for contingency measure
purposes’’ without enforceable
provisions that would require adoption
and submission of additional
contingency measures.
Response to Comment 6: Our
approval relates to the SIP requirements
for contingency measures under CAA
section 172(c)(9) and 40 CFR 51.1014 for
the 1997 annual, 2006 24-hour and 2012
annual PM2.5 NAAQS. Under the
applicable requirements, states with
PM2.5 nonattainment areas must provide
contingency measures that can be
61 89
FR 56222, 56224–56225.
62 Id.
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
triggered in the event of a failure to meet
any RFP requirement in an attainment
plan, to meet any quantitative milestone
in an attainment plan, to submit a
quantitative milestone report, or to
attain the applicable PM2.5 NAAQS by
the applicable attainment date.
Neither the CAA nor the EPA’s
regulations specify a minimum number
of contingency measures or prescribe
separate contingency measures for
different contingency measure triggers.
The CAA and the EPA’s regulations also
do not preclude the reliance on the
same contingency measures for separate
NAAQS, and the commenter does not
identify any specific statutory or
regulatory requirement that does so.
Moreover, it is not uncommon for a state
or district to rely on a core set of control
measures for multiple NAAQS. For
example, the State and District rely on
a core set of NOX control measures as
part of the control strategies for
demonstrating RFP and attainment for
both ozone and PM2.5 in the San Joaquin
Valley. Regardless, we acknowledge that
neither the State nor District has
submitted an enforceable commitment
to submit additional contingency
measures in response to the triggering of
the contingency measures. The EPA
does not believe that such commitment
is required.
In this instance, the 2023 SIP
Submissions rely on three contingency
measures, all of which provide for an
initial triggering event and two of which
provide for a second triggering event. In
other words, all three contingency
measures provide for implementation of
more stringent requirements upon a first
triggering event, and two of the
contingency measures also provide for
implementation of yet more stringent
requirements upon a second triggering
event (i.e., further tightening of the
requirements beyond that triggered by
the first event).
While the EPA is not requiring CARB
or the District to provide separate
contingency measures for each of the
triggering events or separate
contingency measures for different
PM2.5 NAAQS in San Joaquin Valley, we
find that a SIP deficiency would arise
upon the first triggering event
notwithstanding the existence of the
built-in provisions for further
reductions upon a second triggering
event. This is because the adequacy of
the contingency measure SIP depended
on measures that are now being
implemented as a result of the first
triggering event, meaning they can no
longer be used to satisfy the contingency
measure requirements for subsequent
triggering events. In response, we expect
that CARB and the District would adopt
and submit a SIP revision within one
year of the triggering event to
demonstrate that the SIP continues to
meet contingency measure
requirements. We would also expect the
SIP revision to take into account the
emission reductions from the two
remaining contingency measures and to
include additional contingency
measures as needed to ensure that the
San Joaquin Valley continues to meet
the contingency measure requirements
of CAA section 172(c)(9) and 40 CFR
51.1014.
Comment 7: CVAQ asserts that the
‘‘hot spot’’ approach under District Rule
4901, ‘‘Wood Burning Fireplaces and
Wood Burning Heaters,’’ ‘‘cannot meet
the basic control measure requirements
of the [CAA]’’ and that the emission
reductions from expanding applicability
to previously exempt areas would not be
surplus to the controls that should be
required in the San Joaquin Valley. If,
however, residential wood burning is to
be used as a contingency measure,
CVAQ contends that the contingency
measure in Rule 4901 should ban all
non-essential wood burning. CVAQ
further contends that the District must
adopt contingency measures that would
achieve OYW of RFP emission
reductions in each county of the San
80759
Joaquin Valley to protect its most
vulnerable communities. In addition,
citing comments made by residents
during 2023 District workshops that
report incidents of poor enforcement of
the rule, CVAQ asserts that Rule 4901
has no assurance of actual emission
reductions and no concrete
commitments for enforcement. CVAQ
advocates for accountability measures to
ensure actual emission reductions and
enforcement of residential wood
burning regulations.
Response to Comment 7: The EPA
maintains that the Residential Wood
Burning Contingency Measure in
SJVUAPCD Rule 4901 meets the
contingency measure requirements and
provides reasonable assurance of
emission reductions. As explained in
our proposed rule,63 Rule 4901 includes
a tiered mandatory curtailment program
that establishes different curtailment
thresholds based on the type of devices
(i.e., registered clean-burning devices
vs. unregistered devices) and different
counties (i.e., ‘‘hot spot’’ vs. non-hot
spot), notwithstanding narrow
exemptions (e.g., for households where
a wood burning fireplace or heater is the
sole source of heat, per section 5.7.4.2
of Rule 4901). During a ‘‘Level One
Episodic Wood Burning Curtailment,’’
operation of wood-burning fireplaces
and other unregistered wood-burning
heaters or devices is prohibited, but
properly operated, registered woodburning heaters may be used. During a
‘‘Level Two Episodic Wood Burning
Curtailment,’’ operation of any woodburning device is prohibited.
In 2019, the District lowered the
curtailment thresholds in Madera,
Fresno, and Kern counties, which the
District identified as hot spot counties,
because they were ‘‘either new areas of
gas utility or areas deemed to have
persistently poor air quality.’’ 64 Table 4
presents the wood burning curtailment
thresholds in Rule 4901, as revised in
2019.
TABLE 4—RESIDENTIAL WOOD BURNING CURTAILMENT THRESHOLDS IN RULE 4901
khammond on DSKJM1Z7X2PROD with RULES
[as amended in 2019]
Episodic wood burning
curtailment levels
Hot spot counties
(Madera, Fresno, and Kern)
Level One (No Burning Unless Registered) .......
Level Two (No Burning for All) ...........................
12 μg/m3 ..........................................................
35 μg/m3 ..........................................................
Contrary to the commenters’ assertion
that the hot spot approach cannot meet
the basic control measure requirements
63 88
FR 87988, 87995.
PM2.5 Plan, Appendix J, 60.
64 2018
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
of the CAA, the EPA approved the
State’s demonstration for Rule 4901
(2019 amendments) as BACM and MSM
65 85
66 86
PO 00000
Non-hot spot counties
(San Joaquin, Stanislaus, Merced, Kings, and
Tulare)
20 μg/m3.
65 μg/m3.
for the 2006 24-hour PM2.5 NAAQS,65 as
RACM for the 2012 annual PM2.5
NAAQS,66 and as BACM for the 1997
FR 44192.
FR 67343.
Frm 00045
Fmt 4700
Sfmt 4700
E:\FR\FM\04OCR1.SGM
04OCR1
80760
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
khammond on DSKJM1Z7X2PROD with RULES
annual PM2.5 NAAQS.67 In 2022, the
Ninth Circuit upheld the EPA’s
approval of the State’s BACM and MSM
demonstration for the 2006 24-hour
PM2.5 NAAQS, including those relating
to residential wood burning.68
Therefore, the hot spot approach in Rule
4901 (2019 amendments), as applied to
the particular facts and circumstances of
the San Joaquin Valley for the 1997
annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS, meets the applicable
control requirements for controlling
direct PM2.5 emissions from residential
wood burning.
The Residential Wood Burning
Contingency Measure (i.e., the 2023
amendments to Rule 4901) would, upon
a first triggering event, lower the
thresholds for the five non-hot spot
counties to match those of the hot spot
counties (i.e., 12 mg/m3 for Level One
Curtailment and 35 mg/m3 for a Level
Two Curtailment) and the emission
reductions in those five counties would
be surplus because lowering the
thresholds for the five non-hot spot
counties would go beyond the
requirements of Rule 4901, as amended
in 2019, that the EPA has approved as
meeting RACM, BACM, and MSM.
Furthermore, upon a second triggering
event, the Level One Curtailment
threshold would be further lowered to
11 mg/m3 for all eight counties in the
San Joaquin Valley, resulting in further
emission reductions that would be
surplus to the already implemented
measure and surplus to the reductions
from the first triggering event.
We note that the Residential Wood
Burning Contingency Measure would
alone, if triggered, achieve 0.5793 tpd
direct PM2.5 emission reductions, which
would exceed OYW of RFP (per EPA’s
long-standing approach) and OYW of
progress (per EPA’s draft revised
approach) for direct PM2.5 emissions in
the San Joaquin Valley. Given that the
Residential Wood Burning Contingency
Measure is primarily a control for direct
PM2.5,69 and that it would achieve the
recommended amount of reductions for
that pollutant (in terms of OYW of RFP
or OYW of progress), the District was
not required to restrict residential wood
burning further than what the District
has chosen to do for the purposes of
meeting the contingency measure SIP
requirements for the relevant PM2.5
67 88
FR 86581.
Advocates for Healthy Air v. EPA, Case
No. 20–72780, Dkt. #58–1 (9th Cir., April 13, 2022),
pp. 8–9.
69 Based on the estimates included in Table 2
(revised) in this final rule, NOX reductions from the
Residential Wood Burning Contingency Measure
would be approximately 14% of the reductions of
direct PM2.5.
68 Medical
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
NAAQS. Thus, the District was not
required to include a ban on all nonessential wood burning to meet the
contingency measure SIP requirements.
Furthermore, in reviewing the District’s
evaluation of potential control measures
for residential wood burning,70 we
relied heavily on the EPA’s detailed
evaluation of source categories and
measures that we considered as
potential additional contingency
measures as part of our federal
implementation plan (FIP) proposal but
determined to be infeasible or otherwise
unsuitable for contingency measures.71
Regarding the commenters’
contention that the District must adopt
contingency measures that would
achieve OYW of RFP emission
reductions in each county of the San
Joaquin Valley, we reiterate that CAA
section 172(c)(9) does not specify what
amount of emission reductions
contingency measures should achieve,
much less whether contingency
measures should achieve particular
amounts of emission reductions within
geographical regions within a
nonattainment area (e.g., in each
county). In both our long-standing
interpretation and draft revised
interpretation of the contingency
measure requirement, the amount of
emission reductions (e.g., OYW of
progress) should be estimated for the
nonattainment area as a whole,
consistent with the emissions
inventories for the base year, RFP years,
and attainment year that are based on
the whole area.72
Regarding comments on the
enforceability of Rule 4901 and
assurance of actual emission reductions,
we note that the District included
responses to similar comments received
during the District’s public comment
process on the public draft SJV PM2.5
Contingency Measure SIP.73 We
maintain that Rule 4901 is adequately
enforceable and that the emission
reductions are reasonably estimated, for
the following reasons. The District
explains the method it used to estimate
the emission reductions from the
70 SJV PM
2.5 Contingency Measure SIP, section
4.2 (‘‘District Feasibility Analysis’’), pp. 26–31.
71 88 FR 87988, 88005–88006, and the EPA’s
Reasoned Justification TSD. For our discussion of
the EPA’s evaluation of a potential wood burning
ban, see p. 82 of the EPA’s Reasoned Justification
TSD.
72 EPA’s Draft Revised Contingency Measures
Guidance, pp. 23–24. Notwithstanding, for
informational purposes we note that the EPA
considered the geographic scope of each of the three
contingency measures proposed for approval,
including the Residential Wood Burning
Contingency Measure. 88 FR 87988, 88010–88011.
73 SJV PM
2.5 Contingency Measure SIP, Appendix
J (‘‘Comments and Response’’).
PO 00000
Frm 00046
Fmt 4700
Sfmt 4700
Residential Wood Burning Contingency
Measure, including its use of an 80%
compliance rate.74 In calculating these
estimates, the District incorporates data
by county, device type (wood stoves and
fireplaces), registration (unregistered vs.
registered, which incorporates
certification of cleaner-burning devices),
fuel type (e.g., natural gas, wood,
pellets), and average curtailment days
with and without the contingency
provisions.
In evaluating the emission reductions
estimates from the District, and as part
of the EPA’s FIP proposal for PM2.5
contingency measures in the San
Joaquin Valley,75 we found that an 80%
control efficiency rate is reasonable in
this case given the District’s extensive
public outreach and enforcement of its
curtailment program.76 The EPA
concludes that the District’s method is
a detailed and reasonable means to
estimate the emission reductions from
the Residential Wood Burning
Contingency Measure.
Regarding enforcement, the District
states that it dedicates staff to both
compliance assistance and enforcement
and describes several aspects of its
enforcement efforts.77 On curtailment
days, District staff surveil
neighborhoods, focus on areas where
non-compliance is historically high or
the subject of common complaints, and
respond to complaints from the public.
The District responds to complaints
during business hours, weekends,
holidays, and night-time hours and uses
technology such as global positioning
system (GPS) and low-light imaging
cameras (for night-time enforcement) to
assist their response. During the most
recent wood burning season (November
2023-February 2024), District staff spent
approximately 3,500 hours on proactive
monitoring and enforcement and issued
470 notices of violation of Rule 4901.78
The EPA concludes that the District
implements a reasonably robust
enforcement program to ensure
compliance with the wood burning
74 SJV PM
2.5 Contingency Measure SIP, Appendix
C (‘‘Emission Reduction Analysis for Rule 4901’’),
C–7.
75 EPA’s Reasoned Justification TSD, section II
(‘‘Combustion: Residential Wood Burning’’), pp. 5–
6.
76 See, e.g. SJVUAPCD, ‘‘Report On 2021–2022
Winter Residential Woodsmoke Reduction,’’ April
21, 2022 (‘‘District’s 2022 Report’’), pp. 19–28.
77 District’s 2022 Report, pp. 26–28.
78 SJVUAPCD, ‘‘Report on 2023–2024 Winter
Residential Woodsmoke Reduction Strategy,’’
PowerPoint presentation prepared for SJVUAPCD
Citizens Advisory Committee, June 4, 2024, slide
16. For summary information concerning
enforcement of Rule 4901 in previous seasons, see
SJVUAPCD, ‘‘Report On 2022–2023 Winter
Residential Woodsmoke Reduction,’’ April 20,
2023, p. 28.
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
prohibitions required when a Level One
or Level Two Curtailment is called by
the District.
In sum, neither the District nor the
EPA has assumed perfect compliance
with the provisions of the Residential
Wood Burning Contingency Measure
(i.e., 100% control efficiency when a
‘‘No Burn’’ day is called for a given
geographic region within San Joaquin
Valley); the District has provided
reasonable assurance of 80% control
efficiency based on its outreach,
enforcement, and performance analyses;
and the District reasonably estimates the
amount of emission reductions to follow
either a first triggering event (0.5793 tpd
direct PM2.5 and 0.0817 tpd NOX) or a
second triggering event (0.1078 tpd
direct PM2.5 and 0.0148 tpd NOX).
Therefore, we continue to find that the
Residential Wood Burning Contingency
Measure is adequately enforceable and
its associated emission reductions are
reasonably estimated.
Comment 8: CVAQ states that the
Rural Open Areas Contingency Measure
is ‘‘essentially meaningless given that
agricultural operations are exempt.’’
They note that agricultural operations
can implement a Fugitive PM10
Management Plan (FPMP) as an
alternative to compliance requirements
and that a more meaningful contingency
measure would enforce these FPMPs for
all agricultural operations.
Response to Comment 8: While the
estimated emission reductions of 0.008
tpd direct PM2.5 from the Rural Open
Areas Contingency Measure are small,
we disagree with the commenters’
characterization of the measure’s value.
Specifically, section 7.0 (‘‘Contingency
Provision’’) of Rule 8051, ‘‘Open Areas’’
(2023 amendments) would, if triggered,
lower the applicability threshold for
rural open areas from 3.0 acres to 1.0
acre, and owners and operators of those
1.0 to 3.0-acre parcels would be newly
subject to the fugitive dust control
requirements of Rule 8051.79 This
measure, if triggered, would affect
entities such as construction, oilfield,
truck stop, and equipment and vehicle
storage owners/operators, as identified
in the District’s ‘‘Regulation VIII
Recordkeeping Reporting Forms’’
(revised June 1, 2009), as well as other
residential, industrial, institutional,
governmental, or commercial lot
owners/operators. When such entities
disturb 1,000 or more square feet of
79 The definition of open areas is provided in
Rule 8011, ‘‘General Requirements,’’ section 3.36
(‘‘. . . vacant portions of residential or commercial
lots and contiguous parcels that are immediately
adjacent to and owned and/or operated by the same
individual or entity are considered one open
area. . .’’).
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
surface area within a 1.0 to 3.0-acre
parcel, they would be required to apply
fugitive dust control measures,
consistent with the control requirements
of section 5.0 of Rule 8051. Moreover,
while the emission reductions from the
Rural Open Areas Contingency Measure
are small on a regional basis, they will
be more meaningful for residents and
workers in the immediate vicinities of
the open areas to which Rule 8051
would apply if and when the
contingency measure is triggered.
With respect to agricultural
operations in the San Joaquin Valley
and FPMPs, fugitive dust control
requirements are governed by Rule
8081, ‘‘Agricultural Sources,’’ which
covers off-field sources like unpaved
roads, unpaved vehicle and equipment
traffic areas, and bulk materials.80
Under section 7.0 of Rule 8081, an
agricultural operator may implement an
FPMP for unpaved roads and unpaved
vehicle/equipment traffic areas as a
compliance alternative to the control
requirements in sections 5.2.2, 5.3.1,
and 5.3.2 of the rule. An FPMP must
achieve 50% control efficiency for
fugitive dust (PM10) and go through a
review and approval process prior to
being implemented. It must be
implemented on all days that vehicle
traffic exceeds the applicable vehicle
trip thresholds in sections 5.2.2, 5.3.1,
and 5.3.2. Under section 7.4 of Rule
8081, failure to comply with an
approved FPMP is deemed a violation of
the rule.
By comparison, sections 5.2.2, 5.3.1,
and 5.3.2 require that visible dust
emissions (VDE) be limited to a 20%
opacity standard and comply with
requirements for stabilization of
unpaved roads 81 by application of at
least one of a discrete set of control
techniques (e.g., watering, uniform layer
of washed gravel, chemical/organic dust
stabilizers/suppressants). Section 5.2.2
applies to unpaved roads based on
vehicle daily trips; sections 5.3.1 and
5.3.2 apply to unpaved vehicle/
equipment traffic areas with thresholds
based on annual and daily vehicle trips,
respectively.
80 We note that Rule 4550, ‘‘Conservation
Management Practices’’ includes fugitive dust
control requirements for on-field agricultural
operations in the San Joaquin Valley, but does not
include provisions for FPMPs, unlike Rule 8081.
Also, while there are provisions for FPMPs in Rule
8061, ‘‘Paved and Unpaved Roads’’ and Rule 8071,
‘‘Unpaved Vehicle/Equipment Traffic Areas,’’ those
rules pertain to non-agricultural roads and vehicle/
equipment traffic areas, respectively, rather than the
agricultural operations referenced in the comments.
81 By definition under section 3.59 of Rule 8011,
stabilization of unpaved roads and unpaved
vehicle/equipment traffic areas requires that VDE be
limited to 20% opacity.
PO 00000
Frm 00047
Fmt 4700
Sfmt 4700
80761
If, as the commenters suggest, all
agricultural operations were required,
following a contingency measure
triggering event, to implement an FPMP,
it is unclear whether such contingency
measure would achieve emission
reductions that are surplus to those that
are being achieved under the existing
rule. For agricultural operations already
implementing an FPMP, such
contingency measure would result in no
change in emission reductions. For
agricultural operations implementing
controls under section 5.2.2, 5.3.1, and
5.3.2 of Rule 8081 (i.e., not
implementing an FPMP), it is unclear
whether an FPMP would achieve more
emission reductions than the standard
control provisions (limit VDE to 20%
opacity). Consistent with our final rule
approving the 2003 San Joaquin Valley
attainment plan for the 1987 PM10
NAAQS into the California SIP,82 we
believe that the FPMP’s 50% control
efficiency requirement is equivalent to
the minimum control efficiency
expected from compliance with surface
stabilization requirements in the rule
that otherwise apply.
Furthermore, within the SJV PM2.5
Contingency Measure SIP, the District
states that it evaluated potential
additional controls (including those
implemented by other jurisdictions)
within the application of Regulation
VIII, ‘‘Fugitive PM10 Prohibitions,’’ and
that the existing fugitive dust controls
(including those under Rule 8081) meet
or exceed the requirements for RACM,
BACM, and MSM, and did not identify
any further potential contingency
measure, with the exception of the
potential measure in Rule 8051 (i.e., the
measure ultimately adopted as the Rural
Open Areas Contingency Measure).83 In
the EPA’s review of potential control
measures (including those implemented
by other jurisdictions), we similarly did
not identify additional measures for
unpaved roads that would be suitable as
contingency measures.84 Therefore, we
82 69 FR 30006 (May 26, 2004). We note that, at
that time, EarthJustice compared the 20% opacity
and other aspects of the control requirements in
section 5.0 of Rule 8081 to the 50% control
efficiency requirement and lack of 20% opacity
requirement in the compliance alternative in
section 7.0 of Rule 8081 and asserted that the FPMP
compliance alternative should not be included. 69
FR 30006, 30018. While we agreed that the FPMP
alternative does not contain an explicit requirement
for sources to comply with 20% opacity, it is
unclear whether compliance with 20% opacity
would necessarily increase control efficiency for
unpaved roads or unpaved vehicle/equipment
traffic areas above the minimum 50% control
required under the FPMP provisions of Rule 8081.
83 SJV PM
2.5 Contingency Measure SIP, p. 25.
84 EPA’s Reasoned Justification TSD, pp. 109–
114.
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
80762
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
disagree with the commenters that
enforcing FPMPs on all agricultural
operations would qualify as a
contingency measure. Nonetheless, we
recommend that the District continue to
explore potential contingency measures
for dust emissions from agricultural
sources, whether within the construct of
the FPMP framework in Rule 8081 or
more broadly, e.g., within the construct
of other rules such as Rule 4550,
‘‘Conservation Management Practices.’’
Comment 9: The Valley EJ
Organizations state that the EPA’s
proposed approval of the State’s
contingency measures ignores
Presidential orders that direct the EPA
and other federal agencies to prioritize
environmental justice, including
Executive Order 14008, ‘‘Tackling the
Climate Crisis at Home and Abroad’’
(January 27, 2021) and Executive Order
14096, ‘‘Revitalizing our Nation’s
Commitment to Environmental Justice
for All’’ (April 21, 2023).85 They further
argue that the EPA exacerbates the
‘‘environmental justice crisis’’ by
denying the residents of the San Joaquin
Valley meaningful pollution reductions.
To convey the magnitude of this
concern, the commenters cite to
American Lung Association rankings of
counties for PM2.5 and ozone pollution
(where many San Joaquin Valley
counties rank among the worst in the
nation) and the EPA’s review of
environmental justice indices (where
many San Joaquin Valley counties
exceed the 90th percentile) and describe
the sequence of failures to attain the
NAAQS by the applicable attainment
dates in San Joaquin Valley, as well as
recent air quality design values for the
1997 8-hour ozone NAAQS and the
1997 annual PM2.5 NAAQS that portend
the same.
In addition, CVAQ argues that the
EPA’s proposed approval goes against
the Biden Administration’s
environmental justice priorities by
‘‘refusing to hold the region’s largest
polluters accountable, discounting
community priorities and continuing
racist polluting practices.’’ They state
that EPA is only looking at
technological feasibility and costs to
industry and is not analyzing social and
health impacts in determining the cost
of not taking action.
Response to Comment 9: We agree
that the San Joaquin Valley has many
communities with EJ concerns that are
disproportionately impacted by PM2.5
and other kinds of air pollution.
85 Valley EJ Organizations Comment Letter, pp. 4–
6. See also, 86 FR 7619 (February 1, 2021)
(Executive Order 14008) and 88 FR 25251 (April 26,
2023) (Executive Order 14096).
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
However, we disagree that the EPA’s
proposed approval ignores Presidential
orders to prioritize environmental
justice. First, the Residential Wood
Burning Contingency Measure and the
Rural Open Area Contingency Measure,
as well as the Smog Check Contingency
Measure, would, following a triggering
event, reduce emissions from residential
wood burning, rural open areas, and
light-duty vehicles across the San
Joaquin Valley, including minority and
low-income populations, as described in
section VI (‘‘Environmental Justice
Considerations’’) of our proposed rule.86
While not a comprehensive solution
to address the disproportionately high
PM2.5 concentrations to which these
populations are exposed, the three
contingency measures would achieve
more than OYW of emission reductions
for direct PM2.5 and a portion of the
OYW of emission reductions for NOX, as
described in our proposed rule 87 and
updated in section I.B of this document.
Therefore, our proposed approval of
these measures is directionally
consistent with Executive Orders 14008
and 14096, as well as Executive Order
12898, ‘‘Federal Actions to Address
Environmental Justice in Minority and
Low-Income Populations’’ (February 11,
1994).88
To the extent that the commenters
disagree with the EPA’s Draft Revised
Contingency Measure Guidance or our
application thereof to the facts and
circumstances of the San Joaquin
Valley, we maintain that the CARB and
the District’s 2023 SIP Submissions
meet the requirements of CAA section
172(c)(9) and 40 CFR 51.1014 and are
approving the submissions on that basis.
The EPA carefully reviewed the
extensive recommendations put forward
by environmental, public health, and
community organizations regarding
additional potential control measures on
86 88 FR 87988, 88009–88011. In section VI of our
proposed rule, we discuss environmental justice
considerations in the context of Executive Order
12898 (‘‘Federal Actions To Address Environmental
Justice in Minority Populations and Low-Income
Populations’’) rather than by reference to Executive
Orders 14008 or 14096. Executive Order 12898
directs federal agencies ‘‘to identify and address
disproportionately high and adverse human health
or environmental effects of their actions on
minority and low-income populations, to the
greatest extent practicable and permitted by law.’’
Executive Order 14008 directs federal agencies to
take certain actions directed toward ‘‘disadvantaged
communities’’ that are described as ‘‘historically
marginalized and overburdened.’’ Executive Order
14096 builds upon and supplements Executive
Orders 12898 and 14008. All three Executive Orders
direct federal agencies to identify and address
disproportionate environmental effects, even while
the particular directives and protected classes vary
among the three orders.
87 88 FR 87988, 88003–88005.
88 59 FR 7629 (February 16, 1994).
PO 00000
Frm 00048
Fmt 4700
Sfmt 4700
stationary and area sources in the San
Joaquin Valley 89 and documented our
analyses thereof in the EPA’s Reasoned
Justification TSD.90 We relied heavily
on that TSD in our evaluation of the
CARB and the District’s 2023 SIP
Submissions and, where our
conclusions differed from CARB or the
District’s conclusions with respect to
the basis of a potential additional
control measure not meeting the
contingency measure requirements, we
explained those differences, as noted in
the latter part of Response to Comment
4 of this document. Nevertheless, those
control measure recommendations
retain their value for consideration as
CARB and the District develop, and the
EPA reviews, further SIPs for the San
Joaquin Valley, even while we conclude
that they are not required to meet the
contingency measure requirements for
the PM2.5 NAAQS in the San Joaquin
Valley at this time.
Regarding CVAQ’s comments
regarding technological feasibility and
costs to industry versus social and
health impacts, we agree that the State,
in its 2023 SIP Submissions, and the
EPA, in our review thereof, considered
the technological feasibility of potential
control measures and reviewed
available information regarding the
economic feasibility of potential control
measures (i.e., which captures costs to
industry). However, we did not assess
the public health and social costs of not
requiring potential control measures
during our review of the State’s 2023
SIP Submissions because such an
assessment is not required for the
contingency measure requirements of
the CAA, nor the related control
89 See letter dated October 22, 2021, from
environmental organizations to Michael S. Regan,
Administrator, EPA, Subject: ‘‘Meeting Request to
Discuss PM–2.5 Crisis in the San Joaquin Valley,’’
and letter dated May 18, 2022, from environmental
organizations to Michael S. Regan, Administrator,
Environmental Protection Agency, Subject:
‘‘Meeting Request to Discuss PM–2.5 Crisis in the
San Joaquin Valley’’ (referred to in the EPA’s
Reasoned Justification TSD as the ‘‘EarthJustice
Letters’’).
90 EPA’s Reasoned Justification TSD, p. 6 (within
section II (‘‘Control Measure Identification and
Evaluation Methodology’’)), pp. 13–17 (large
boilers, steam generators, and process heaters), 29
(non-road, reciprocal internal combustion engines),
pp. 58–59 (flares), pp. 73–76 (glass and related
products), 80–84 (residential fuel combustion), p.
85 (fugitive dust controls), pp. 129–131 (managed
burning and disposal), pp. 134–136 (commercial
cooking), p. 147 (new source review), pp. 149–151
(indirect source review), and pp. 151–152 (soil
NOX). We also noted that we did not review the
environmental organizations’ recommendations for
primarily VOC-related controls, as the EPA has
approved the State’s demonstrations that VOCs are
not significant precursors for 1997 annual, 2006 24hour, and 2012 annual PM2.5 NAAQS in the San
Joaquin Valley. See, e.g., p. 53 (petroleum
production and marketing), and p. 88 (confined
animal facilities).
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
measure requirements (e.g., RACM/
RACT, BACM/BACT, or MSM) upon
which contingency measures build.91
In addition, while the EPA may in
certain circumstances have discretion to
consider environmental justice in
implementing the requirements of the
Act, Executive Orders 12898, 14008,
and 14096 do not provide any
independent authority for action. The
EPA has determined that this action
satisfies the requirements of CAA
section 172(c)(9) for the 1997 annual,
2006 24-hour, and 2012 annual PM2.5
NAAQS in the San Joaquin Valley.
Under the CAA, the EPA is required to
approve a SIP submission that meets the
requirements of the CAA and applicable
federal regulations.
Although these Executive Orders do
not provide us with an independent
basis to disapprove CARB and the
District’s SIP submission, we conducted
an environmental justice analysis to
provide additional context and
information about this rulemaking to the
public, as described in section III of this
document and section VI of our
proposed rule. Overall, we expect that
this action and the codification of the
Residential Wood Burning Contingency
Measure and the Rural Open Areas
Contingency Measure, as well as the
codification of the Smog Check
Contingency Measure in our separate
final action, will contribute to reduced
negative environmental and health
impacts on all populations in the San
Joaquin Valley, including communities
with EJ concerns. For these reasons, this
action is not expected to have a
disproportionately high or adverse
human health or environmental effect
on a particular group of people. The
EPA remains committed to working
with CARB and the District to ensure
that the PM2.5 attainment requirements
for this area satisfy applicable CAA
requirements and thereby protect all
populations in the area, including
communities with EJ concerns, from
disproportionately high or adverse air
pollution impacts.
Comment 10: The Valley EJ
Organizations allege that, following the
2021 Ninth Circuit Court decision in
AIR v. EPA, the EPA began colluding
with CARB and California air districts to
weaken the contingency measure
requirement. The Valley EJ
Organizations further state that, during
meetings of a workgroup called the
91 Nevertheless, beyond the scope of this
rulemaking, the public may be interested in the
EPA’s estimates of the monetized benefit per ton of
reducing PM2.5 and ozone precursor emissions for
certain emission sectors; available at https://
www.epa.gov/benmap/sector-based-pm25-benefitton-estimates.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
‘‘Padilla Contingency Measures
Subgroup,’’ the EPA committed to revise
its long-standing interpretation of the
contingency measure requirements,
including specific elements that would
relax emission reduction requirements
and contend that the EPA’s commitment
yielded the Draft Revised Contingency
Measure Guidance.92 The commenters
also contend that the EPA now
proposes, as it allegedly agreed to
during the Padilla Contingency
Measures subgroup proceedings, to
‘‘eviscerate the amount of contingency
measure emission reductions’’ and that
the ‘‘EPA has predetermined the
outcome of these proposed rulemakings
in an agreement with CARB and the air
districts during the Padilla Contingency
Measures Subgroup proceedings,’’
thereby violating the procedural due
process clause of the Fifth Amendment
to the U.S. Constitution, CAA section
307, the Administrative Procedure Act,
and Executive Orders 14008 and
14096.93
The Valley EJ Organizations include
several documents obtained from the
EPA via a Freedom of Information Act
request to support their allegation of
collusion.94 These include, among other
things, documents relating to EPA
engagement in 2021–2023 with the
California Air Pollution Control Officers
Association (CAPCOA), the ‘‘Padilla
Contingency Measures Subgroup,’’ a
letter from South Coast Air Quality
Management District, discussions with
California air districts and CARB senior
staff, and an email from EPA Region IX
to SJVUAPCD. The commenters state
that these documents indicate that the
EPA worked closely with California air
agencies to fashion an agreement to
weaken the contingency measure
requirement and that the EPA shared its
revised guidance with the California
agencies several months before releasing
the revised guidance to the general
public without regard for the public
health consequences from weakening
the contingency measure requirement.95
Response to Comment 10: We
disagree that the EPA colluded with
California air agencies to weaken the
contingency measure requirement
following the 2021 AIR v. EPA decision
by the Ninth Circuit Court of Appeals.
In this context, collusion refers to a
secret agreement for an illegal purpose.
The process we followed to reconsider
and revise preexisting contingency
92 Valley
EJ Organizations Comment Letter, p. 2.
EJ Organizations Comment Letter, p. 11.
94 Valley EJ Organizations Comment Letter,
Exhibits 4 through 12.
95 Valley EJ Organizations Comment Letter, pp. 8–
11.
93 Valley
PO 00000
Frm 00049
Fmt 4700
Sfmt 4700
80763
measure guidance was not secret, nor
was our agreement to reconsider and
revise the guidance made for an illegal
purpose.
The Clean Air Act is referred to as a
model of cooperative federalism. Under
the CAA, the EPA is responsible for
establishing the NAAQS, and the states
are responsible for developing SIPs and
SIP revisions to provide for
implementation, maintenance, and
enforcement of the NAAQS. In turn, the
EPA is responsible for promulgating
regulations establishing SIP
requirements and for providing
guidance to the states in developing
SIPs and SIP revisions to meet the
various requirements under the CAA
and our implementing regulations.
In that capacity, it is appropriate for
the EPA to reconsider previously-issued
guidance in the wake of court decisions
that bear on EPA actions on SIPs that
relied on that guidance.96 In this
instance, as discussed in the Draft
Revised Contingency Measure
Guidance, we issued the draft revised
guidance document because recent
court decisions had invalidated key
aspects of EPA’s historical approach to
implementing the contingency measure
requirement, and these court decisions
had the effect of prohibiting an
approach that many air agencies have
historically used to meet the
contingency measure requirement.97
The EPA developed the Draft Revised
Contingency Measure Guidance based
on the recommendations of an ad hoc
internal working group, referred to as
the Contingency Measure Task Force,
that the EPA assembled soon after the
D.C. Circuit Court of Appeals decision
in Sierra Club v. EPA.98 The
Contingency Measure Task Force was
comprised of EPA program staff and
attorneys from both the EPA regions and
headquarters. During the process of
developing options for EPA
management consideration and
preparing the Draft Revised Contingency
96 See, for example, EPA Office of Transportation
and Air Quality, ‘‘Implementing Clean Air Act
Section 182(d)(1)(A): Transportation Control
Measures and Transportation Control Strategies to
Offset Growth in Emissions Due to Growth in
Vehicle Miles Travelled,’’ EPA–420–B–12–053,
August 2012 (revised guidance in light of the Ninth
Circuit Court of Appeals decision in Association of
Irritated Residents v. EPA, 632 F.3d 584, at 596–597
(9th Cir. 2011), reprinted as amended on January
27, 2012).
97 Draft Revised Contingency Measure Guidance,
p. 2.
98 The Sierra Club v. EPA decision adopted the
rationale of an earlier decision by the Ninth Circuit
Court of Appeals in Bahr v. EPA that invalidated
already-implemented measures as contingency
measures for the purposes of CAA section 172(c)(9).
Sierra Club v. EPA, 21 F.4th 815, 827–28 (D.C. Cir.
2021) and Bahr v. EPA, 836 F.3d 1218 (9th Cir.
2016).
E:\FR\FM\04OCR1.SGM
04OCR1
80764
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
khammond on DSKJM1Z7X2PROD with RULES
Measure Guidance, California air
agencies made their views known to the
EPA, but those agencies played no part
in the drafting or review of the
recommendations made by the
Contingency Measure Task Force to EPA
management or the substance of the
Draft Revised Contingency Measure
Guidance itself.
Also in the spirit of cooperative
federalism, the EPA routinely
communicates with state and local air
agencies responsible for SIPs and SIP
revisions regarding compliance with SIP
requirements. Again, the states are
responsible for adoption and
submission of SIPs and SIP revisions
and there are consequences for failure to
meet SIP submission deadlines.
In this instance, the EPA engaged
with state and local air agencies to hear
their concerns over meeting the
contingency measure SIP requirements
and to provide a description of the types
of revisions to the contingency measure
guidance that EPA staff were developing
for consideration by EPA management.
The impetus for heightened interest on
the part of state and local air agencies
was the need to meet near-term
deadlines for submission of SIP
revisions addressing the contingency
measure SIP requirements for multiple
ozone and PM2.5 NAAQS. Documents
cited by the commenter as evidence of
collusion simply reveal that the EPA
was responsive to state and local agency
requests for insight as to what the
contingency measure guidance revisions
might entail if and when approved by
EPA management. Thus the air agencies
that developed SIP revisions in reliance
on the descriptions by EPA staff of notyet-approved revisions to the
contingency measure guidance were
taking a risk that the guidance, once
made publicly available, would differ in
material ways from what EPA staff had
described.
With respect to the commitments that
the EPA made in connection with the
Padilla Contingency Measures
Subgroup,99 the EPA did not commit to
making any specific revisions to the
contingency measure guidance or to
making any revisions to the guidance
that are inconsistent with the CAA or
case law. Rather, the Agency committed
‘‘to explore interpretations and
approaches that are consistent with the
court decisions’’ and, among other
99 The Padilla Contingency Measures Subgroup
was one of several such ad hoc groups assembled
in response to an inquiry from U.S. Senator Padilla.
See the letter dated December 3, 2021, from Joseph
Goffman, Principal Deputy Assistant Administrator
to U.S. Senator Alex Padilla, responding to letter
dated October 19, 2021, from U.S. Senator Alex
Padilla to Michael Regan, Administrator, EPA.
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
things, ‘‘to revisit’’ the general bases for
calculating the amount of emission
reductions that contingency measures
should provide, but as noted previously,
the EPA did not commit to any
particular outcome. The Contingency
Measure Task Force followed through
on these commitments through meetings
and review of draft documents that were
internal to the EPA and eventual
publication of notice in the Federal
Register of the availability of the Draft
Revised Contingency Measure Guidance
for public review and comment. We
believe the revised draft guidance
provides an approach that state and
local air agencies may use to meet the
contingency measure SIP requirements
under the CAA.
The EPA issued the Draft Revised
Contingency Measure Guidance on
March 17, 2023, and sought public
comment on section 3 (‘‘Showing that
the CMs Achieve Sufficient
Reductions’’), section 4 (‘‘Reasoned
Justification for Less Than OYW of
Progress’’), and section 5 (‘‘Guidance on
Timing of Reductions from CMs’’) of the
draft guidance over a 30-day period
ending April 24, 2023.100 We applied
the underlying concepts of the draft
guidance in our evaluation of the SJV
PM2.5 Contingency Measure SIP,
described as much in our proposed rule,
and provided a 30-day comment period
ending January 9, 2024, consistent with
the public notice requirements of the
CAA and the Administrative Procedure
Act.101
For this action, we evaluated the two
individual District contingency
measures, the Residential Wood
Burning Contingency Measure and the
Rural Open Areas Contingency Measure,
to determine whether they met the
requirements for such measures under
the CAA and the EPA’s regulations. We
also considered the sum of the emission
reductions from the two individual
District contingency measures plus
CARB’s Smog Check Contingency
Measure relative to the recommended
amount we have indicated contingency
measures should achieve. Because the
measures, considered together, would
not achieve the recommended amount
of emission reductions for NOX, CARB
and the District submitted infeasibility
demonstrations documenting the
unavailability of additional feasible
contingency measures for that PM2.5
precursor.
We reviewed and evaluated the
infeasibility demonstrations and in our
proposed rule provided the rationale for
our conclusion that the individual
100 88
101 88
PO 00000
FR 17571.
FR 87988.
Frm 00050
Fmt 4700
Sfmt 4700
District contingency measures met the
applicable requirements for such
measures and that CARB and the
District had provided a reasoned
justification, through the infeasibility
demonstrations, for not adopting
contingency measures sufficient to
achieve the recommended amount of
emission reductions for NOX. In this
action, we are finalizing our approval of
the SJV PM2.5 Contingency Measure SIP
for the reasons given in the proposed
rule, as clarified and supplemented in
responses to comments. While the
Valley EJ Organizations object to the
consideration of feasibility in
connection with the contingency
measure SIP requirement, the
commenters have raised no specific
objection our evaluation of the
infeasibility demonstrations from CARB
and the District upon which our final
approval rests.
In summary, in our proposed rule on
the State’s contingency measure SIP
submissions for the PM2.5 NAAQS in the
San Joaquin Valley, as well as our Draft
Revised Contingency Measures
Guidance, we articulated a reasoned
justification for the change in EPA
policy on the contingency measure
requirements and respond in this
document to comments opposing those
policy changes, and we explained how
we were reviewing the 2023 SIP
Submissions in light of the new
guidance. The EPA believes that such
actions satisfy the applicable
requirements for public process under
the CAA and Administrative Procedure
Act, as well as our responsibilities to
engage state and local air agencies on
CAA requirements and the development
of SIP revisions in the wake of
applicable court decisions.
III. Environmental Justice
Considerations
As described in detail in our proposal,
the EPA reviewed environmental and
demographic data for the San Joaquin
Valley using the EPA’s EJ screening and
mapping tool (‘‘EJSCREEN’’) and
compared the data to the corresponding
data for the United States as a whole,
and to California as a whole.102 The
results of the analysis are provided for
102 EJSCREEN provides a nationally consistent
dataset and approach for combining environmental
and demographic indicators. EJSCREEN is available
at https://www.epa.gov/ejscreen/what-ejscreen. The
EPA used EJSCREEN to obtain environmental and
demographic indicators representing each of the
eight counties in the San Joaquin Valley. These
indicators are included in EJSCREEN reports that
are available in the rulemaking docket for this
action. EPA Region IX, ‘‘EJSCREEN Analysis for the
Eight Counties of the San Joaquin Valley
Nonattainment Area,’’ August 2022.
E:\FR\FM\04OCR1.SGM
04OCR1
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
khammond on DSKJM1Z7X2PROD with RULES
informational and transparency
purposes.
This final action approves the State’s
contingency measure SIP submissions
for the 1997 annual, 2006 24-hour, and
2012 annual PM2.5 NAAQS in the San
Joaquin Valley. Information on these
PM2.5 NAAQS and their relationship to
health impacts can be found at 62 FR
38652 (July 18, 1997), 71 FR 61144
(October 17, 2006), and 78 FR 3086
(January 15, 2013), respectively. We
expect that this action and resulting
emission reductions will generally be
neutral or contribute to reduced
environmental and health impacts on all
populations in the San Joaquin Valley,
including communities with EJ
concerns. At a minimum, this action
would not worsen existing air quality
and is expected to help ensure the area
is meeting requirements to attain and/or
maintain air quality standards. Further,
there is no information in the record
indicating that this action is expected to
have disproportionately high or adverse
human health or environmental effects
on a particular group of people.
IV. EPA Action
For the reasons described in our
proposed rule and in responses to
comments and under CAA section
110(k)(3), the EPA is taking final action
to approve SIP revisions submitted by
CARB on June 8, 2023, and October 16,
2023, for the San Joaquin Valley to
address the contingency measure SIP
requirements for San Joaquin Valley for
the 1997 annual, 2006 24-hour, and
2012 annual PM2.5 NAAQS.
The SIP submissions include the
contingency measure plan element for
San Joaquin Valley for the relevant
PM2.5 NAAQS (referred to herein as the
‘‘SJV PM2.5 Contingency Measure SIP’’)
and two specific contingency measures,
referred to herein as the Residential
Wood Burning Contingency Measure
and the Rural Open Areas Contingency
Measure. We are approving the SJV
PM2.5 Contingency Measure SIP as
meeting the applicable requirements of
CAA section 172(c)(9) and 40 CFR
51.1014 for San Joaquin Valley for the
applicable PM2.5 NAAQS based on our
approval of these two contingency
measures, the emission reductions from
the two contingency measures and the
Smog Check Contingency Measure, and
our review of the State’s infeasibility
demonstrations provided in the SJV
PM2.5 Contingency Measure SIP.
The Residential Wood Burning
Contingency Measure and the Rural
Open Areas Contingency Measure are
included in amendments to SJVUAPCD
Rule 4901 (‘‘Wood Burning Fireplaces
and Wood Burning Heaters’’) and Rule
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
8051 (‘‘Open Areas’’), respectively. We
are taking final action to approve the
two specific contingency measures
because they meet the requirements
under CAA section 172(c)(9) and 40
CFR 51.1014 for such measures.
As discussed in Section I.B of the
proposed rule, on November 26, 2021,
the EPA disapproved the contingency
measure SIP elements submitted for the
2006 24-hour and 2012 annual PM2.5
NAAQS for San Joaquin Valley.103
These disapprovals were effective on
December 27, 2021. In a separate action
published on November 26, 2021, also
effective December 27, 2021, the EPA
disapproved the contingency measure
element for the 1997 annual PM2.5
NAAQS for San Joaquin Valley.104
In our November 26, 2021 final
disapprovals, we noted that offset and
highway sanctions under CAA sections
179(b)(2) and 179(b)(1), respectively,
would not apply if California submits,
and the EPA approves, a SIP submission
or submissions that correct the
deficiencies identified in our final
actions prior to the imposition of
sanctions.105 Through this final
approval action, we find that California
has corrected the deficiencies associated
with the contingency measure elements
for the 1997 annual, 2006 24-hour and
2012 annual PM2.5 NAAQS for San
Joaquin Valley. Thus, upon the effective
date of this final rule, all sanctions and
any sanctions clocks associated with the
disapprovals of the contingency
measure elements for the 1997 annual,
2006 24-hour and 2012 annual PM2.5
NAAQS for San Joaquin Valley will be
permanently terminated.106
Lastly, based on this final action, we
find that our FIP obligation arising from
our December 6, 2018 finding of failure
to submit is terminated, and thus, we
will not be taking final action on our
August 8, 2023 proposed PM2.5
contingency measure FIP for San
Joaquin Valley.107
V. Incorporation by Reference
In this rule, the EPA is finalizing
regulatory text that includes
incorporation by reference. In
103 86
FR 67343.
FR 67329.
105 86 FR 67329, 67341 and 86 FR 67343, 67346–
67347. We note that, concurrent with our proposed
rules to approve the State’s 2023 SIP submissions,
the EPA issued an interim final determination that
stayed offset sanctions and deferred highway
sanctions. 88 FR 87934 (December 20, 2023).
106 In addition, our CAA section 110(c) FIP
obligations arising from the disapprovals of the
contingency measure elements will be permanently
terminated.
107 See our December 20, 2023 proposed rule at
88 FR 87991 for a discussion of the finding of
failure to submit and related FIP obligation.
104 86
PO 00000
Frm 00051
Fmt 4700
Sfmt 4700
80765
accordance with requirements of 1 CFR
51.5, the EPA is finalizing the
incorporation by reference of
SJVUAPCD Rule 4901 (‘‘Wood Burning
Fireplaces and Wood Burning Heaters’’),
amended May 18, 2023, which regulates
emissions from wood burning
fireplaces, wood burning heaters, and
outdoor wood burning devices, and
Rule 8051 (‘‘Open Areas’’), amended
September 21, 2023, which regulates
fugitive dust from open areas. The May
18, 2023 version of Rule 4901 and the
September 21, 2023 version of Rule
8051 will replace the previously
approved versions of these rules,
respectively, in the California SIP. The
EPA has made, and will continue to
make, these documents available
through www.regulations.gov and at the
EPA Region IX Office (please contact the
person identified in the FOR FURTHER
INFORMATION CONTACT section of this
preamble for more information).
VI. Statutory and Executive Order
Reviews
Under the Clean Air Act, the
Administrator is required to approve a
SIP submission that complies with the
provisions of the Clean Air Act and
applicable Federal regulations. 42
U.S.C. 7410(k); 40 CFR 52.02(a). Thus,
in reviewing SIP submissions, the EPA’s
role is to approve state choices,
provided that they meet the criteria of
the Clean Air Act. Accordingly, this
action merely approves a state plan and
related measures as meeting Federal
requirements and does not impose
additional requirements beyond those
imposed by state law. For that reason,
this action:
• Is not a significant regulatory action
subject to review by the Office of
Management and Budget under
Executive Orders 12866 (58 FR 51735,
October 4, 1993) and 14094 (88 FR
21879, April 11, 2023);
• Does not impose an information
collection burden under the provisions
of the Paperwork Reduction Act (44
U.S.C. 3501 et seq.);
• Is certified as not having a
significant economic impact on a
substantial number of small entities
under the Regulatory Flexibility Act (5
U.S.C. 601 et seq.);
• Does not contain any unfunded
mandate or significantly or uniquely
affect small governments, as described
in the Unfunded Mandates Reform Act
of 1995 (Pub. L. 104–4);
• Does not have federalism
implications as specified in Executive
Order 13132 (64 FR 43255, August 10,
1999);
E:\FR\FM\04OCR1.SGM
04OCR1
khammond on DSKJM1Z7X2PROD with RULES
80766
Federal Register / Vol. 89, No. 193 / Friday, October 4, 2024 / Rules and Regulations
• Is not subject to Executive Order
13045 (62 FR 19885, April 23, 1997)
because it approves a state program;
• Is not a significant regulatory action
subject to Executive Order 13211 (66 FR
28355, May 22, 2001); and
• Is not subject to requirements of
Section 12(d) of the National
Technology Transfer and Advancement
Act of 1995 (15 U.S.C. 272 note) because
application of those requirements would
be inconsistent with the Clean Air Act.
In addition, the SIP is not approved
to apply on any Indian reservation land
or in any other area where the EPA or
an Indian tribe has demonstrated that a
tribe has jurisdiction. In those areas of
Indian country, the final rule does not
have tribal implications and will not
impose substantial direct costs on tribal
governments or preempt tribal law as
specified by Executive Order 13175 (65
FR 67249, November 9, 2000).
Executive Order 12898 (Federal
Actions To Address Environmental
Justice in Minority Populations and
Low-Income Populations, 59 FR 7629,
February 16, 1994) directs Federal
agencies to identify and address
‘‘disproportionately high and adverse
human health or environmental effects’’
of their actions on communities with EJ
concerns to the greatest extent
practicable and permitted by law. The
EPA defines EJ as ‘‘the fair treatment
and meaningful involvement of all
people regardless of race, color, national
origin, or income with respect to the
development, implementation, and
enforcement of environmental laws,
regulations, and policies.’’ The EPA
further defines the term fair treatment to
mean that ‘‘no group of people should
bear a disproportionate burden of
environmental harms and risks,
including those resulting from the
negative environmental consequences of
industrial, governmental, and
commercial operations or programs and
policies.’’
CARB and the District did not
evaluate EJ considerations as part of the
SIP submissions addressed in this
action; the CAA and applicable
implementing regulations neither
prohibit nor require such an evaluation.
The EPA performed an EJ analysis, as
described in section III of this document
and section VI of the EPA’s proposed
rule, entitled ‘‘Environmental Justice
Considerations.’’ The EPA conducted
this analysis for the purpose of
providing additional context and
information about this rulemaking to the
public, and the EPA does not rely on
this analysis as a basis for this final
action. In addition, the EPA has
addressed comments on Executive
Orders relating to EJ in Response to
VerDate Sep<11>2014
17:03 Oct 03, 2024
Jkt 265001
Comment 9 of this document. Due to the
nature of the action being taken here,
this action is expected to have a neutral
to positive impact on the air quality of
the affected area. In addition, there is no
information in the record upon which
this decision is based inconsistent with
the stated goal of E.O. 12898 of
achieving EJ for communities with EJ
concerns.
This action is subject to the
Congressional Review Act, and the EPA
will submit a rule report to each House
of the Congress and to the Comptroller
General of the United States. This action
is not a ‘‘major rule’’ as defined by 5
U.S.C. 804(2).
Under section 307(b)(1) of the Clean
Air Act, petitions for judicial review of
this action must be filed in the United
States Court of Appeals for the
appropriate circuit by December 3,
2024. Filing a petition for
reconsideration by the Administrator of
this final rule does not affect the finality
of this action for the purposes of judicial
review, nor does it extend the time
within which a petition for judicial
review may be filed, and it shall not
postpone the effectiveness of such rule
or action. This action may not be
challenged later in proceedings to
enforce its requirements. (See section
307(b)(2).)
List of Subjects in 40 CFR Part 52
Environmental protection, Air
pollution control, Ammonia,
Incorporation by reference,
Intergovernmental relations, Nitrogen
oxides, Particulate matter, Reporting
and recordkeeping requirements, Sulfur
oxides, Volatile organic compounds.
Dated: September 25, 2024.
Martha Guzman Aceves,
Regional Administrator, Region IX.
For the reasons discussed in the
preamble, part 52, chapter I, title 40 of
the Code of Federal Regulations is
amended as follows:
PART 52—APPROVAL AND
PROMULGATION OF
IMPLEMENTATION PLANS
1. The authority citation for Part 52
continues to read as follows:
■
Authority: 42 U.S.C. 7401 et seq.
Subpart F—California
2. Section 52.220 is amended by
adding paragraphs (c)(334)(i)(B)(3),
(c)(535)(i)(A)(2), (c)(618) and (619) to
read as follows:
■
§ 52.220
*
PO 00000
Identification of plan—in part.
*
*
(c) * * *
Frm 00052
*
*
(334) * * *
(i) * * *
(B) * * *
(3) Previously approved on February
17, 2006, in paragraph (c)(334)(i)(B)(2)
of this section and now deleted with
replacement in paragraph
(c)(619)(i)(A)(1) of this section: Rule
8051, ‘‘Open Areas,’’ amended on
August 19, 2004.
*
*
*
*
*
(535) * * *
(i) * * *
(A) * * *
(2) Previously approved on July 22,
2020, in paragraph (c)(535)(i)(A)(1) of
this section and now deleted with
replacement in paragraph
(c)(618)(i)(A)(1) of this section: Rule
4901, ‘‘Wood Burning Fireplaces and
Wood Burning Heaters,’’ amended on
June 20, 2019.
*
*
*
*
*
(618) The following plan revisions
were submitted electronically on June 8,
2023, by the Governor’s designee, as an
attachment to a letter dated June 7,
2023.
(i) Incorporation by reference. (A) San
Joaquin Valley Unified Air Pollution
Control District.
(1) Rule 4901, ‘‘Wood Burning
Fireplaces and Wood Burning Heaters,’’
amended on May 18, 2023.
(2) [Reserved]
(B) [Reserved]
(ii) Additional materials. (A) San
Joaquin Valley Unified Air Pollution
Control District.
(1) ‘‘PM2.5 Contingency Measure State
Implementation Plan Revision (May 18,
2023),’’ adopted on May 18, 2023,
excluding Rule 4901, ‘‘Wood Burning
Fireplaces and Wood Burning Heaters.’’
(2) [Reserved]
(B) [Reserved]
(619) The following plan revision was
submitted electronically on October 16,
2023, by the Governor’s designee, as an
attachment to a letter dated October 13,
2023.
(i) Incorporation by reference. (A) San
Joaquin Valley Unified Air Pollution
Control District.
(1) Rule 8051, ‘‘Open Areas,’’
amended on September 21, 2023.
(2) [Reserved]
(B) [Reserved]
(ii) [Reserved]
*
*
*
*
*
§ 52.237
[Amended]
3. Section 52.237 is amended by
removing and reserving paragraphs
(a)(9), (10) and (11).
■
[FR Doc. 2024–22681 Filed 10–3–24; 8:45 am]
BILLING CODE 6560–50–P
Fmt 4700
Sfmt 4700
E:\FR\FM\04OCR1.SGM
04OCR1
Agencies
[Federal Register Volume 89, Number 193 (Friday, October 4, 2024)]
[Rules and Regulations]
[Pages 80749-80766]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-22681]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[EPA-R09-OAR-2023-0477; FRL-11532-03-R9]
Clean Air Plans; Contingency Measures for the Fine Particulate
Matter Standards; San Joaquin Valley, California
AGENCY: Environmental Protection Agency (EPA).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Environmental Protection Agency (EPA) is taking final
action to approve two state implementation plan (SIP) submissions under
the Clean Air Act (CAA) that address the contingency measure
requirements for the 1997 annual, 2006 24-hour, and 2012 annual fine
particulate matter (PM2.5) national ambient air quality
standards (NAAQS or ``standards'') for the San Joaquin Valley
PM2.5 nonattainment area in California. The two SIP
submissions include the area's contingency measure plan element and two
specific contingency measures that would apply to residential wood
burning heaters and fireplaces and to non-agricultural, rural open
areas. A third contingency measure, applicable to light-duty on-road
motor vehicles, has been approved into the California SIP in a separate
action by the EPA, and the related emission reductions from the third
measure are accounted for in this final rule. The EPA is finalizing
approval of the SIP submissions because the Agency has determined that
they are in accordance with the applicable requirements for such SIP
submissions under the CAA and the EPA's implementing regulations for
the PM2.5 NAAQS.
DATES: This rule is effective November 4, 2024.
ADDRESSES: The EPA has established a docket for this action under
Docket ID No. EPA-R09-OAR-2023-0477. All documents in the docket are
listed on the https://www.regulations.gov website. Although listed in
the index, some information is not publicly available, e.g.,
Confidential Business Information (CBI) or other information whose
disclosure is restricted by statute. Certain other material, such as
copyrighted material, is not placed on the internet and will be
publicly available only in hard copy form. Publicly available docket
materials are
[[Page 80750]]
available through https://www.regulations.gov, or please contact the
person identified in the FOR FURTHER INFORMATION CONTACT section for
additional availability information. If you need assistance in a
language other than English or if you are a person with a disability
who needs a reasonable accommodation at no cost to you, please contact
the person identified in the FOR FURTHER INFORMATION CONTACT section.
FOR FURTHER INFORMATION CONTACT: Rory Mays, Planning and Analysis
Branch (AIR-2), Air and Radiation Division, EPA Region IX, 75 Hawthorne
St., San Francisco, CA 94105; phone: (415) 972-3227; email:
[email protected].
SUPPLEMENTARY INFORMATION: Throughout this document, ``we,'' ``us'' and
``our'' refer to the EPA.
Table of Contents
I. Background
A. Proposed Action
B. Changes to Proposed Action
II. Public Comments and EPA Responses
III. Environmental Justice Considerations
IV. EPA Action
V. Incorporation by Reference
VI. Statutory and Executive Order Reviews
I. Background
A. Proposed Action
On December 20, 2023 (88 Federal Register (FR) 87988), the EPA
proposed to approve California's contingency measure SIP submissions
for the 1997 annual, 2006 24-hour, and 2012 annual PM2.5
NAAQS submitted by the California Air Resources Board (CARB) for the
San Joaquin Valley nonattainment area in California. Specifically, the
SIP submissions include the ``PM2.5 Contingency Measure
State Implementation Plan Revision (May 18, 2023)'' (herein referred to
as the ``SJV PM2.5 Contingency Measure SIP''), revisions to
San Joaquin Valley Unified Air Pollution Control District (SJVUAPCD or
``District'') Rule 4901 (amended May 18, 2023) \1\ that add
PM2.5 NAAQS contingency provisions that we refer to herein
as the ``Residential Wood Burning Contingency Measure,'' and revisions
to Rule 8051 (amended September 21, 2023) \2\ that add PM2.5
NAAQS contingency provisions that we refer to herein as the ``Rural
Open Areas Contingency Measure.'' CARB submitted the SJV
PM2.5 Contingency Measure SIP and the Residential Wood
Burning Contingency Measure on June 8, 2023,\3\ and the Rural Open
Areas Contingency Measure on October 16, 2023,\4\ as revisions to the
California SIP.
---------------------------------------------------------------------------
\1\ SJVUAPCD Rule 4901 is titled ``Wood Burning Fireplaces and
Wood Burning Heaters.''
\2\ SJVUAPCD Rule 8051 is titled ``Open Areas.''
\3\ CARB adopted the SJV PM2.5 Contingency Measure
SIP and Residential Wood Burning Contingency Measure as SIP
revisions on June 7, 2023, through Executive Order S-23-010 and
submitted the SIP revisions to the EPA electronically on June 8,
2023, as attachments to a letter dated June 7, 2023, from Steven S.
Cliff, Ph.D., Executive Officer, CARB to Martha Guzman, Regional
Administrator, EPA Region IX.
\4\ CARB adopted the Rural Open Areas Contingency Measure as a
SIP revision on October 13, 2023, through Executive Order S-23-014
and submitted the SIP revision to the EPA electronically on October
16, 2023, as an attachment to a letter dated October 13, 2023, from
Steven S. Cliff, Ph.D., Executive Officer, CARB to Martha Guzman,
Regional Administrator, EPA Region IX.
---------------------------------------------------------------------------
In addition, in a separate proposed rule also published on December
20, 2023, the EPA proposed approval of a third contingency measure,
applicable to light-duty on-road motor vehicles, and the related
emission reductions from the third measure are accounted for in this
final rule.\5\ We refer to the third contingency measure as the ``Smog
Check Contingency Measure.''
---------------------------------------------------------------------------
\5\ 88 FR 87981 (December 20, 2023). We note that the EPA
finalized approval of the Smog Check Contingency Measure. 89 FR
56222 (July 9, 2024).
---------------------------------------------------------------------------
We proposed to approve the SJV PM2.5 Contingency Measure
SIP, the Residential Wood Burning Contingency Measure, and the Rural
Open Areas Contingency Measure because we determined that they, along
with emission reductions from the Smog Check Contingency Measure,
comply with the contingency measure SIP requirements of CAA section
172(c)(9) and EPA's implementing regulations at 40 CFR 51.1014. We
collectively refer herein to CARB's contingency measure SIP submissions
for the 1997 annual, 2006 24-hour, and 2012 annual PM2.5
NAAQS for the San Joaquin Valley as the State's ``2023 SIP
Submissions.''
In sections I and II of the proposed rule, we presented background
information on the 1997 annual and 24-hour, the 2006 24-hour and 2012
annual PM2.5 NAAQS, the nonattainment designations and
classifications of the San Joaquin Valley for these PM2.5
NAAQS, and the resultant contingency measure SIP obligations;
summarized our prior PM2.5 contingency measure findings of
failure to submit \6\ and disapprovals for the San Joaquin Valley; \7\
described the SIP submissions at issue in this action; and provided the
basis for our preliminary conclusion that the SIP submissions met
applicable procedural requirements.\8\ In section III of the proposed
rule, we summarized the contingency measure SIP requirements under the
CAA and the EPA's implementing regulations, relevant EPA guidance, and
legal precedent, including a brief discussion of relevant decisions by
the Ninth Circuit Court of Appeals \9\ and the D.C. Circuit Court of
Appeals.\10\ \11\
---------------------------------------------------------------------------
\6\ 83 FR 62720 (December 6, 2018). In response to our finding
of failure to submit, the EPA proposed a Federal Implementation Plan
(FIP) to address the contingency measure requirements for the 1997
annual, 2006 24-hour and 2012 annual PM2.5 NAAQS at 88 FR
53431 (August 8, 2023).
\7\ 86 FR 67343 (November 26, 2021) and 86 FR 67329 (November
26, 2021).
\8\ 88 FR 87988, 87989-87993 (December 20, 2023).
\9\ Bahr v. EPA, 836 F.3d 1218, 1235-1237 (9th Cir. 2016) and
Assoc. of Irritated Residents v. EPA, 10 F.4th 937, 946-47 (9th Cir.
2021) (``AIR v. EPA'' or ``AIR'').
\10\ Sierra Club v. EPA, 21 F.4th 815, 827-828 (D.C. Cir. 2021).
\11\ 88 FR 87988, 87993-87994.
---------------------------------------------------------------------------
In addition, we described the EPA's long-standing approach to
contingency measures and the EPA's revised approach for addressing the
contingency measure SIP requirements, as presented in the EPA's draft
guidance, entitled ``Draft: Guidance on the Preparation of State
Implementation Plan Provisions that Address the Nonattainment Area
Contingency Measure Requirements for Ozone and Particulate Matter
(DRAFT--3/17/23--Public Review Version),'' herein referred to as the
``Draft Revised Contingency Measure Guidance.'' \12\ Two principal
differences between the draft revised guidance and existing guidance on
contingency measures relate to the EPA's recommendations concerning the
specific amount of emission reductions that implementation of
contingency measures should achieve \13\ and the timing for when the
emission reductions from the contingency measures should occur. The
Draft Revised Contingency Measure Guidance also provides recommended
procedures for developing a demonstration, if applicable, that the area
lacks sufficient feasible measures to achieve one year's worth (OYW) of
reductions, building on existing guidance that the state should provide
a reasoned justification for why the smaller amount of emission
reductions is appropriate.
---------------------------------------------------------------------------
\12\ 88 FR 87988, 87994. See also, 88 FR 17571 (March 23, 2023)
(notice of availability of the EPA's Draft Revised Contingency
Measure Guidance).
\13\ The EPA's long-standing recommendation was that states
should adopt contingency measures sufficient to provide emission
reductions equivalent to one year's worth (OYW) of reasonable
further progress (RFP). In the Draft Revised Contingency Measure
Guidance, the EPA recommends a different amount that contingency
measures should achieve--one that is defined in terms of OYW of
``progress'' rather than OYW of RFP.
---------------------------------------------------------------------------
In section IV of the proposed rule, we described the two specific
District PM2.5 contingency measures proposed for approval in
this action (i.e., the District's Residential Wood Burning
[[Page 80751]]
Contingency Measure and Rural Open Areas Contingency Measure) and
provided our evaluation of the measures relative to the requirements of
CAA section 172(c)(9) and 40 CFR 51.1014. In short, we preliminarily
concluded that the contingency measures met the requirements for such
measures because both measures are designed to be both prospective and
conditional, include appropriate triggering mechanisms for
requirements, and are structured to be implemented in a timely manner
without significant further action by the District, CARB, or the EPA
and to achieve the estimated emission reductions within roughly a year
or two of the triggering event.\14\ Furthermore, both requirements that
would be triggered are not required for any other CAA purpose, and the
emission reductions from the measures are not included in any
reasonable further progress (RFP) or attainment demonstration for the
PM2.5 NAAQS in the San Joaquin Valley. For these reasons, we
proposed to approve District's Residential Wood Burning Contingency
Measure and Rural Open Areas Contingency Measure.\15\
---------------------------------------------------------------------------
\14\ 88 FR 87988, 87995-87998.
\15\ Id.
---------------------------------------------------------------------------
In section V of the proposed rule, we summarized how the District
and CARB had applied the revised approach to fulfilling the contingency
measure SIP requirement in the context of the PM2.5 NAAQS in
the San Joaquin Valley, and we presented our evaluation thereof.\16\
Specifically, we discussed our evaluation of the District's and CARB's
identification and evaluation of potential control measures, adoption
of certain contingency measures, comparison of those contingency
measures against OYW of emission reductions, and reasoned justification
for not adopting further contingency measures, which we recap in the
following paragraphs.
---------------------------------------------------------------------------
\16\ 88 FR 87988, 87999-88009.
---------------------------------------------------------------------------
In the SJV PM2.5 Contingency Measure SIP, the District
described its ongoing stationary source regulatory efforts, identified
potential control measures as candidate contingency measures, and
analyzed the technological and/or economic feasibility of each
candidate measure, including the feasibility of implementing such
measures within 60 days and achieving the resulting emission reductions
within one to two years of the triggering event.\17\ The District also
provided more in-depth analysis of potential control measures for five
source categories, ultimately adopting measures for two source
categories (wood burning fireplaces/heaters and rural open areas) and
providing a justification in the form of an infeasibility demonstration
for not adopting contingency measures for the other three source
categories (commercial charbroiling, almond harvesting, and oil and gas
production combustion equipment).
---------------------------------------------------------------------------
\17\ SJV PM2.5 Contingency Measure SIP, pp. 9-11.
---------------------------------------------------------------------------
Similarly, CARB identified potential mobile source control
measures, assessed whether each candidate measure could be implemented
within 60 days of a triggering event and achieve emission reductions
within one to two years, and then analyzed their technological and/or
economic feasibility.\18\ Regarding timing of emission reductions from
mobile sources, CARB concluded that new engine standards and fleet
regulations are not appropriate for contingency measures given the time
needed for manufacturers to design, develop, and deploy cleaner engines
or equipment at scale, especially for zero-emission equipment.
---------------------------------------------------------------------------
\18\ SJV PM2.5 Contingency Measure SIP, section 5.3
(``Measure Analysis''); and Smog Check Contingency Measure, Appendix
A (``Infeasibility Analysis'').
---------------------------------------------------------------------------
The District and CARB ultimately adopted three contingency measures
identified through their respective evaluation processes: the
Residential Wood Burning Contingency Measure, the Rural Open Areas
Contingency Measure, and the Smog Check Contingency Measure. Each of
these measures can be implemented without further action by the
District, CARB, or the EPA and achieve emission reductions within one
to two years of the triggering event, consistent with the contingency
measure requirements under CAA section 172(c)(9) and the EPA's
recommendations regarding timing in the Draft Revised Contingency
Measures Guidance.\19\ In addition, the revisions to SJVUAPCD Rule 4901
establishing the Residential Wood Burning Contingency Measure resolved
deficiencies identified in the EPA's disapproval of prior contingency
provisions in Rule 4901, thereby ensuring that the direct
PM2.5 and NOX emission reductions will be
achieved, irrespective of which county may exceed the applicable
PM2.5 NAAQS at the time of any finding of failure to attain
or other applicable determination.\20\
---------------------------------------------------------------------------
\19\ Draft Revised Contingency Measures Guidance, pp. 40-42.
\20\ 88 FR 87988, 87996.
---------------------------------------------------------------------------
The District then assessed how the emission reductions from the
Residential Wood Burning Contingency Measure would compare against OYW
of progress as defined in the Draft Revised Contingency Measure
Guidance. As part of our evaluation and for the proposed rule, we
prepared an independent assessment of the emission reductions to
include the two additional contingency measures that were adopted and
submitted after the submission of the SJV PM2.5 Contingency
Measure SIP and to provide a comparison of the emission reductions
relative to OYW of progress to the long-standing recommendation of OYW
of RFP. In our proposed rule, we found that the combined 0.5873 tons
per day (tpd) of direct PM2.5 emission reductions from the
District contingency measures (for residential wood burning and for
rural open areas) would exceed both OYW of RFP (0.44-0.58 tpd,
depending on the applicable PM2.5 NAAQS) and OYW of progress
(0.41-0.52 tpd, depending on the applicable PM2.5
NAAQS).\21\
---------------------------------------------------------------------------
\21\ 88 FR 87988, 88004-88005, Table 2 and Table 3. Note that
CARB did not estimate any direct PM2.5 emission
reductions from implementation of the Smog Check Contingency
Measure.
---------------------------------------------------------------------------
With respect to NOX emissions, the combined 0.1647-
0.1977 tpd emission reductions from all three contingency measures
would provide a portion of the reductions toward OYW of emission
reductions and, after consideration of interpollutant trading of excess
direct PM2.5 emission reductions from the two District
contingency measures for equivalent NOX emission reductions,
would amount to 1.3 percent (%) to 6.3% of OYW of RFP or 8.8% to 15.7%
of OYW of progress for NOX.\22\
---------------------------------------------------------------------------
\22\ 88 FR 87988, 88005.
---------------------------------------------------------------------------
[[Page 80752]]
As the NOX emission reductions fall short of OYW of
progress, CARB and the District documented their control measure
analyses across the wide range of source categories under each agency's
respective jurisdiction (e.g., on-road sources, off-road sources,
stationary point sources, and area sources) for NOX
emissions. We described the District's and CARB's infeasibility
demonstrations, and our evaluation thereof, in detail and proposed that
they adequately justify the contingency measures selected by CARB and
the District for the 1997 annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS in the San Joaquin Valley. In light of the three
adopted contingency measures and reasoned justifications for not
adopting additional contingency measures, we proposed to approve the
SJV PM2.5 Contingency Measure SIP, the Residential Wood
Burning Contingency Measure, and the Rural Open Areas Contingency
Measure, taking into account the emission reductions from the Smog
Check Contingency Measure (as applied to the San Joaquin Valley), as
meeting the contingency measure requirements of CAA section 172(c)(9)
and 40 CFR 51.1014 for these PM2.5 NAAQS in the San Joaquin
Valley.
See our December 20, 2023 proposed rule (88 FR 87988) for more
information on the SIP submissions and our evaluation thereof.
B. Changes to Proposed Action
In our proposed rule, we evaluated the SIP submissions for
compliance with contingency measure SIP requirements, in part, by
comparing the emission reductions from the contingency measures with
OYW of progress and OYW of RFP. In so doing, we relied on emissions
estimates for the three individual contingency measures--two (the
Residential Wood Burning Contingency Measure and the Rural Open Areas
Contingency Measure) that we proposed to approve in the proposed rule
(and that we are finalizing in this action) and one (the Smog Check
Contingency Measure) that we proposed to approve in a separate
action.\23\ In Table 2 of the proposed rule, we summarized the
estimated emission reductions from the contingency measures, and in
Table 3 of the proposed rule, we presented the estimated emission
reductions as percentages of OYW of RFP and OYW of progress both with
and without trading emission reductions between direct PM2.5
and NOX.
---------------------------------------------------------------------------
\23\ We proposed to approve the Smog Check Contingency Measure
SIP at 88 FR 87981.
---------------------------------------------------------------------------
In both of these tables in the proposed rule, we discounted the
emission reductions from implementation of the Smog Check Contingency
Measure by an amount calculated by CARB to reflect the effect of a
decrease in Moyer Program funding in the San Joaquin Valley if the Smog
Check Contingency Measure were triggered.\24\ However, in our final
rule approving the Smog Check Contingency Measure SIP, we indicated
that we agreed with comments challenging the discount that we had
applied and concluded that the discount was inappropriate due to timing
considerations.\25\ By no longer discounting the emission reductions
attributed to the Smog Check Contingency Measure, the estimates for
total emission reductions for implementation of all three contingency
measures are slightly greater than had been presented in the proposed
rule. The change in emissions estimates and percentages is minor and
does not change any of the preliminary conclusions that we made in
connection with our proposed action on the SJV PM2.5
Contingency Measure SIP. Nonetheless, in the interest of presenting the
most accurate information available, we are republishing Tables 2 and 3
to reflect the updated estimates of emission reductions from the Smog
Check Contingency Measure.
---------------------------------------------------------------------------
\24\ The Carl Moyer Program distributes incentive grants to fund
the incremental cost of cleaner-than-required engines, equipment,
and other technology and is funded, in part, by abatement fees that
are assessed on vehicles exempted from Smog Check testing.
\25\ 89 FR 56222, 56225.
Table 2--Revised Annual Average Emission Reductions From District and CARB Contingency Measures
[tpd]
----------------------------------------------------------------------------------------------------------------
1997 Annual PM2.5 NAAQS 2006 24-Hour PM2.5 NAAQS 2012 Annual PM2.5 NAAQS
Contingency measure -----------------------------------------------------------------------------
Direct Direct Direct
PM2.5 NOX PM2.5 NOX PM2.5 NOX
----------------------------------------------------------------------------------------------------------------
District: Residential Wood Burning 0.5793 0.0817 0.5793 0.0817 0.5793 0.0817
(first triggering event).........
District: Non-agricultural Rural 0.008 ........... 0.008 ........... 0.008 ...........
Open Areas.......................
CARB: Smog Check (first triggering ........... 0.117 ........... 0.120 ........... 0.086
event)...........................
-----------------------------------------------------------------------------
Total......................... 0.5873 0.1987 0.5873 0.2017 0.5873 0.1677
----------------------------------------------------------------------------------------------------------------
Table 3--Revised EPA Evaluation of District and CARB Contingency Measures as Percentage of One Year's Worth of RFP and One Year's Worth of Progress
--------------------------------------------------------------------------------------------------------------------------------------------------------
One year's worth of RFP One year's worth of progress
-----------------------------------------------------------------------------------------
PM2.5 NAAQS Pollutant Reductions % OYW (no % OYW (with Reductions % OYW (no % OYW (with
target trading) trading) \a\ target trading) trading) \a\
--------------------------------------------------------------------------------------------------------------------------------------------------------
1997 Annual.......................... Direct PM2.5........... 0.44 132 100 0.41 142 100
NOX.................... 16.7 1.2 6.3 7.9 2.5 \b\ 15.8
2006 24-hour......................... Direct PM2.5........... 0.58 101 100 0.52 112 100
NOX.................... 18.4 1.1 1.3 6.7 3.0 \b\ 8.9
2012 Annual.......................... Direct PM2.5........... 0.46 129 100 0.43 138 100
NOX.................... 15.3 1.1 6.3 8.7 1.9 13.1
--------------------------------------------------------------------------------------------------------------------------------------------------------
\a\ The EPA has calculated % OYW (With Trading) for NOX based on the 6:1 ratio presented in the SJV PM2.5 Contingency Measure SIP.
[[Page 80753]]
\b\ The percentage of OYW of Progress (With Trading) is 0.1% higher in this table for NOX for the 1997 annual and 2006 24-hour PM2.5 NAAQS relative to
Table 3 of our proposed rule.
II. Public Comments and EPA Responses
The EPA's proposed action provided a 30-day public comment period.
During this period, we received comment letters from three
organizations or groups. CARB submitted a letter supporting the EPA's
proposed approval.\26\ A group of four environmental, public health,
and community organizations (collectively referred to herein as
``Valley EJ Organizations'') submitted adverse comments,\27\ and a
separate group of five environmental, public health, and community
organizations (collectively referred to herein as ``CVAQ'') submitted
adverse comments.\28\ To the extent that certain comments by the Valley
EJ Organizations solely pertain to the Smog Check Contingency Measure
and the State's commitments to submit attainment contingency measures
for the 1997 ozone NAAQS, we have addressed those comments in a
separate final rule on the Smog Check Contingency Measure.\29\
---------------------------------------------------------------------------
\26\ Letter dated January 17, 2024, from Steven S. Cliff,
Executive Officer, CARB, to Martha Guzman, Regional Administrator,
EPA Region IX.
\27\ Letter dated January 19, 2024, from Brent Newell, Attorney
for Central California Environmental Justice Network, Committee for
a Better Arvin, Medical Advocates for Healthy Air, and Healthy
Environment for All Lives, to Jeffrey Buss and Rory Mays, Air and
Radiation Division, EPA Region IX, including 16 exhibits (``Valley
EJ Organizations Comment Letter'').
\28\ Letter dated January 19, 2024, from Central Valley Air
Quality Coalition, National Parks Conservation Association, Little
Manila Rising, Valley Improvement Projects, and Leadership Counsel
for Justice and Accountability, to Rory Mays, Air and Radiation
Division, EPA Region IX (``CVAQ Comment Letter'').
\29\ 89 FR 56222, 56224-56229.
---------------------------------------------------------------------------
Comment 1: The Valley EJ Organizations assert that the EPA's
proposed approval of the PM2.5 contingency measures departs
from the EPA's long-standing interpretation requiring OYW of RFP. They
further state that the proposed approvals based on the Draft Revised
Contingency Measure Guidance violate CAA section 172(c)(9) by severing
the amount of required emission reductions from the parallel and
related RFP requirement when the EPA shifts from its OYW of RFP to its
new OYW of progress interpretation. The Valley EJ Organizations further
assert that the plain meaning does not allow, and the EPA cannot
provide a reasoned justification for, an interpretation that requires
less than that which the Act requires for RFP and that, here, the
PM2.5 contingency measures plainly provide reductions far
less than OYW of RFP. The CVAQ Comment Letter echoes these points,
stating that the emission reductions from the Residential Wood Burning
Contingency Measure and the Rural Open Areas Contingency Measure would
``fall well short of the emission reductions needed to comply with the
weakened average annual reduction requirement in EPA's draft guidance
even when allowing for the interpollutant substitution of excess direct
PM2.5 emissions for NOX emissions.'' \30\
---------------------------------------------------------------------------
\30\ CVAQ Comment Letter, p. 2.
---------------------------------------------------------------------------
Response to Comment 1: Regarding emission reduction metrics (i.e.,
the recommended amount of emission reductions that contingency measures
should achieve), we disagree with commenters as to what is required
under the CAA and with the commenters' broader framing of contingency
measures within the overall planning requirements for nonattainment
areas. While there is a statutory link between RFP and the contingency
measure requirements of CAA section 172(c)(9), it does not function as
the commenter suggests (i.e., to establish an amount of emission
reductions that contingency measures should achieve). The statutory
text of this provision is as follows:
CAA section 172(c)(9) (``Contingency measures'')--``Such plan
shall provide for the implementation of specific measures to be
undertaken if the area fails to make reasonable further progress, or
to attain the national primary ambient air quality standard by the
attainment date applicable under this part. Such measures shall be
included in the plan revision as contingency measures to take effect
in any such case without further action by the State or the
Administrator.''
Thus, while section 172(c)(9) requires contingency measures where
an area fails to make RFP, the language does not specify what amount of
emission reductions such measures should achieve (i.e., does not
explicitly tie the amount of reductions to RFP). Moreover, the
statutory text also has a link to attainment, but it too does not
specify what amount of emission reductions contingency measures should
achieve.
While Congress did not specify an amount that contingency measures
must achieve to comply with CAA section 172(c)(9), Congress must have
intended the amount to be material because, without a specified amount,
a state would not know how to comply with the requirement. Thus
Congress must have at least implicitly delegated to the EPA the
authority to determine an amount of emissions reductions that
contingency measures should achieve and thereby give meaning to the
requirement and provide states with a basis to comply with CAA section
172(c)(9) for a given nonattainment area. The EPA has taken a policy
approach to this question, and in the past, the EPA has indicated that
the recommended amount is OYW of RFP but allowed states to provide a
reasoned justification for adopting contingency measures that would
provide less than the recommended amount. Under the Draft Revised
Contingency Measure Guidance, the EPA is continuing to take a policy
approach but is recommending OYW of progress and describing a specific
analytical framework that states may use to develop a reasoned
justification if the state is unable to identify and adopt contingency
measures that can achieve the recommended amount of emissions
reductions.\31\
---------------------------------------------------------------------------
\31\ OYW of RFP is calculated differently for ozone and
particular matter (PM). For ozone, annual RFP is essentially defined
as three percent of the base year emissions inventory (EI). For PM,
annual RFP is the average annual reductions between the base year EI
and the projected attainment year EI (i.e., the projected attainment
inventory for the nonattainment area). In contrast, OYW of progress
is calculated the same way for ozone and PM: by determining the
average annual reductions between the base year EI and the projected
attainment year EI, determining what percentage of the base year EI
this amount represents, then applying that percentage to the
projected attainment year EI to determine the amount of reductions
needed to ensure ongoing progress if contingency measures are
triggered. See also 88 FR 87988, 87994 and the EPA's Draft Revised
Contingency Measure Guidance, pp. 21-23.
---------------------------------------------------------------------------
In support of our revised approach, we first note that, for both
RFP and attainment purposes, contingency measures are intended to
provide for continued progress in the event that an area fails to meet
an RFP milestone or fails to attain the NAAQS by the applicable
attainment date. They are not themselves expected to provide for either
RFP or attainment. With respect to RFP, the CAA provides certain
remedies if the contingency measures do not make up the shortfall for a
given RFP milestone.\32\ With respect to a failure to attain by the
applicable attainment date, the CAA too provides a remedy by requiring
a new attainment plan.\33\
---------------------------------------------------------------------------
\32\ See CAA sections 182(g)(3) and 189(c)(3).
\33\ See CAA section 179(d).
---------------------------------------------------------------------------
[[Page 80754]]
In reviewing our long-standing approach to contingency measures,
the EPA observed that basing the amount of emission reductions on the
annual amount of reductions needed to meet the separate RFP
requirement--OYW of RFP--may in some cases lead to an amount that is
greater than what typically would be needed to make up for a shortfall
in RFP or for attainment purposes.\34\ The OYW of RFP approach was
unnecessarily conservative for estimating the amount of emission
reductions needed for contingency measure purposes because a given
percentage of the base year inventory tends to represent a much more
significant portion of the attainment projected inventory.
---------------------------------------------------------------------------
\34\ EPA's Draft Revised Contingency Measures Guidance, pp. 21-
23.
---------------------------------------------------------------------------
In shifting to the OYW of progress approach, the EPA recognizes
attainment of the NAAQS as the primary objective of the nonattainment
plan requirements, and thus the appropriate metric should be
attainment-focused. In the absence of a CAA-specified amount of
emission reductions required for contingency measures, the EPA's new
approach is a better reading of the contingency measure SIP requirement
given our understanding of the statutory purpose of contingency
measures following a failure to attain or to meet an RFP milestone,
which is to ensure uninterrupted progress toward attainment while the
next steps unfold in response to the failure. In addition, unlike the
previous approach, the EPA's new approach takes into account the
declining emissions inventories between the base year and attainment
year for a given nonattainment area and aligns the metric for
determining the amount of emission reductions that contingency measures
should achieve for ozone and particulate matter (PM). The alignment
between ozone and PM is a better reading of the statute considering
that the relevant statutory provision, CAA section 172(c)(9), applies
to all the NAAQS.
As to the specific SIP submission addressed in this document, we
acknowledge that CARB and the District used the newly-recommended
metric in preparing the SJV PM2.5 Contingency Measure SIP
for which the EPA is now finalizing approval but, in this instance, the
SIP submission and the EPA's evaluation thereof would have been the
same in substance if the previous metric (i.e., OYW of RFP) had been
used instead. This is because, using either metric, the SIP submissions
include contingency measures that collectively provide for OYW of
progress or RFP for direct PM2.5 and a portion of OYW of
progress or RFP for NOX.\35\ The only difference is the
extent to which the emission reductions from the contingency measures
fall short of each metric for NOX reductions. Using the OYW
of progress metric (with trading), the contingency measures are
estimated to achieve between 8.9% and 15.8% of OYW of progress for
NOX as compared to between 1.3% and 6.3% of OYW of RFP for
NOX using the previously-recommended metric (with
trading).\36\ Using either metric, the EPA would have expected the
State to provide a reasoned justification for not adopting contingency
measures sufficient to achieve greater NOX emission
reductions; consistent with the EPA's recommendations in the Draft
Revised Contingency Measure Guidance, CARB and the District provided
such reasoned justification in their infeasibility demonstrations.
---------------------------------------------------------------------------
\35\ See Table 3 of this final rule.
\36\ See Table 3 of this final rule.
---------------------------------------------------------------------------
Comment 2: The Valley EJ Organizations assert that the EPA's
proposed approval of the State's 2023 SIP Submissions circumvents three
recent court decisions \37\ and unlawfully and arbitrarily (a) lowers
the amount of emission reductions required for contingency measures
(``by severing the statutory link to [RFP],'' i.e., by shifting from
OYW of RFP under the EPA's prior interpretation to OYW of progress
under the EPA's revised interpretation), (b) extends implementation of
contingency measures from one year to two years, and (c) invents a new
feasibility exemption that does not appear in CAA section 172(c)(9).
The commenters state that the EPA's proposed approval relies on the
Draft Revised Contingency Measures Guidance ``to replicate the
arbitrary and capricious interpretation the [AIR] court invalidated.''
---------------------------------------------------------------------------
\37\ The commenter cites Bahr v. EPA, 836 F.3d 1218 (9th Cir.
2016) (``Bahr''); Sierra Club v. EPA, 21 F.4th 815 (D.C. Cir. 2021)
(``Sierra Club''); AIR v. EPA, 10 F.4th 937 (9th Cir. 2021)
(``AIR'').
---------------------------------------------------------------------------
Response to Comment 2: In relevant part, the Bahr and Sierra Club
decisions stand for the proposition that contingency measures under CAA
section 172(c)(9) must be conditional and prospective, and thus,
already-implemented control measures cannot serve as contingency
measures. The AIR decision stands for the proposition that surplus
emission reductions from already-implemented measures cannot be relied
upon as a justification for adoption of contingency measures that
provide for less than the recommended amount of emission reductions for
such measures. However, none of the cited court decisions bear on the
questions of the amount of emission reductions that contingency
measures should achieve, the timeline for achieving the emission
reductions from contingency measures, or the consideration of
feasibility of additional measures as justification for not adopting
contingency measures sufficient to achieve the recommended amount of
such measures.
Moreover, our proposed approval of the SJV PM2.5
Contingency Measure SIP is consistent with the three cited decisions in
that the SIP relies on contingency measures (Residential Wood Burning
Contingency Measure, the Rural Open Areas Contingency Measures, and the
Smog Check Contingency Measure) that are designed to be conditional and
prospective. In addition, as discussed further in the following
paragraph, the State has not relied on emission reductions from
already-implemented measures.
The rationale for our approval of the SJV PM2.5
Contingency Measure SIP is not the same as the rationale for our
approval, later withdrawn in response to the AIR decision, of the
contingency measure element for San Joaquin Valley for the 2008 ozone
NAAQS that was at issue in the AIR case. In the case of the contingency
measure element for the 2008 ozone NAAQS, the EPA took into account the
surplus emission reductions from already-implemented measures in the
milestone years and the years following the attainment date, not as
constituting contingency measures per se, but rather, as justification
for approving a contingency measure element that included a single
contingency measure that would provide for far less than the
recommended amount.
The Court found that, by doing so, the EPA had ``severed the
relationship between the requirement of contingency measures and the
benchmark of reasonable further progress, without an adequate
explanation of why the new--and far more modest--contingency measure is
reasonable.'' \38\ The Court did not indicate that the Agency could not
depart from previous guidance but cautioned that the EPA ``must give a
reasoned explanation for departing from agency practice or policy.''
\39\ The Court concluded that ``[I]f already-implemented measures
cannot themselves be contingency measures--and Bahr makes clear that
they cannot--then neither can they be a basis for declining to
establish contingency measures that would otherwise be
[[Page 80755]]
appropriate.'' \40\ The Court rejected the EPA's rationale for allowing
consideration of surplus emission reductions from already-implemented
measures, reasoning that the EPA could not approve a contingency
measure element ``lacking robust contingency measures by assuming that
they will not be needed. Because the agency did not provide a reasoned
explanation for approving the state plan, the rule is arbitrary and
capricious.'' \41\
---------------------------------------------------------------------------
\38\ AIR v. EPA, 10 F.4th 937, 946 (9th Cir. 2021).
\39\ Id.
\40\ Id.
\41\ Id. at 947.
---------------------------------------------------------------------------
In the wake of the AIR decision, and other case law interpreting
the contingency measure SIP requirement, the EPA undertook an internal
process to reconsider previous guidance provided by the Agency to
states for preparation of SIP submissions to meet the contingency
measure requirements--a process that led to the publication of the
Draft Revised Contingency Measure Guidance. Among other things, in the
Draft Revised Contingency Measure Guidance, the EPA explains why the
Agency believes that it is appropriate to update its prior guidance
with respect to the recommended amount of emission reductions that
contingency measures should achieve and the considerations that states
could use to justify adoption of contingency measures that do not
provide for the recommended amount of emission reductions.\42\ We found
that an update to our contingency measures guidance was justified in
light of changed factual circumstances \43\ and a current understanding
of what remaining controls may be available for states to adopt as
contingency measures. For a more detailed explanation of our rationale
for updating the metric, see Response to Comment 1, and for a more
detailed explanation for allowing for consideration of feasibility, see
Response to Comment 4.
---------------------------------------------------------------------------
\42\ EPA's Draft Revised Contingency Measure Guidance, pp. 21-28
(revised metric) and pp. 29-40 (reasoned justification for adoption
of contingency measures that provide for less than the recommended
amount of emission reductions).
\43\ By ``changed circumstances,'' we are referring to recent
court decisions that have invalidated key aspects of EPA's
historical approach to implementing the contingency measure
requirement and the evolution toward more stringent control programs
in the 30 years since the EPA first articulated its contingency
measure guidance where, as described in Response to Comments 3, the
progressively stringent control measures adopted to meet prior
attainment and RFP planning requirements are already implemented
measures and therefore ineligible to serve as contingency measures
and result in a narrowing pool of candidate contingency measures.
---------------------------------------------------------------------------
With respect to this action, CARB and the District have adopted a
contingency measure element that includes three contingency measures
that would collectively achieve the recommended amount of emission
reductions for one of the two pollutants or precursors at issue, and
they have provided a reasoned justification in the form of
infeasibility demonstrations for adopting contingency measures that
provide for less than the recommended amount for the other relevant
pollutant or precursor. The EPA's approval of a contingency measure
element that relies, in part, on CARB and the District's infeasibility
demonstrations, rather than relying on surplus emission reductions from
already-implemented measures, stands in contrast to the EPA action on
the SIP submission at issue in AIR. The EPA does not assume that
contingency measures would not be needed for San Joaquin Valley but
rather that CARB and the District have adequately demonstrated that
there are no feasible contingency measures for that particular
pollutant or precursor that are left to adopt or that could be
implemented within one to two years of the triggering event.
Comment 3: For areas with more severe air pollution, such as
Serious PM2.5 nonattainment areas, the commenters state that
the EPA has not articulated a reasoned justification for why OYW of
progress is consistent with the CAA remedial scheme that imposes more
stringent requirements on such areas. They suggest that a voluntary
reclassification of an area (e.g., from ``Moderate'' to ``Serious'' for
PM2.5) would lower the average annual reductions needed for
contingency measures (e.g., if the same attainment year inventory
applied for a Moderate or Serious areas, then the annual average
reduction would be lower due to averaging over more years).
In addition, the commenters illustrate a purported fatal flaw in
the EPA's interpretation of OYW of progress using a table that shows
OYW of progress for NOX in a hypothetical ozone
reclassification from Serious to Extreme (in tons per day of
NOX) and state that a lesser amount of emission reductions
for contingency measures for such hypothetical Extreme ozone
nonattainment area runs contrary to the structure of the Act.
Response to Comment 3: As explained in more detail in our Response
to Comment 1, with respect to this specific action, the use of the new
OYW of progress metric here does not materially impact our approval
where the SJV PM2.5 Contingency Measure SIP falls short of
the emissions reductions recommended under either metric. However, we
note that, contrary to commenters' assertions, the EPA's interpretation
of the contingency measure requirement under CAA section 172(c)(9) is
consistent with the CAA's general scheme of subjecting areas with
higher classifications to more stringent requirements. More
specifically, the increased stringency relates to the types of measures
that qualify as contingency measures rather than the amount of emission
reductions that such measures must achieve.
Under the EPA's interpretation of the contingency measure
requirement, contingency measures must be designed to provide emission
reductions (if triggered) that are not otherwise required to meet other
attainment plan requirements and not relied upon to demonstrate RFP nor
attainment. Thus, for example, contingency measures in PM2.5
nonattainment areas classified as Moderate, which are thereby subject
to the reasonably available control measures (RACM) requirement, must
be measures that go beyond the RACM requirement, whereas contingency
measures in PM2.5 nonattainment areas classified as Serious
(and thus subject to the best available control measures (BACM)
requirement) must be measures that go beyond the BACM requirement. In
other words, reclassification of an area to a higher classification
shrinks the pool of candidate contingency measures because some of the
candidate contingency measures will be required to be adopted and
implemented in the reclassified area to meet the specific control
requirements for that classification and, thus, will be unavailable for
adoption as contingency measures. The candidate contingency measures
that remain eligible to meet the contingency measure SIP requirement
under the higher classification are different, and potentially more
stringent, than those that had been available to meet the requirement
under the lower classification. While more stringent measures would
achieve further emission reductions, if triggered, they may achieve a
smaller scale of emission reductions than the prior iterations of
increasingly stringent control measures on a given emission source;
stringency (a relative measure) is not the same as tons per day of
emission reductions (an absolute measure).
Regarding the commenters' assertion that areas with more severe air
pollution should have contingency measures that achieve a larger amount
of emission reductions (i.e., OYW of RFP), we look once more to the
broader framing of contingency measures within the overall planning
requirements for nonattainment areas. The EPA finds that the statutory
and regulatory
[[Page 80756]]
requirements to demonstrate attainment as expeditiously as practicable,
and the absence of a specific statutory metric for how much emission
reductions contingency measures should achieve, give priority to
adopting control measures to attain in the first place, even if that
leaves fewer options for contingency measures in the event of a failure
to attain or to make RFP.
In the SJV PM2.5 Contingency Measure SIP, the State
elaborates further on using an attainment-focused metric by
highlighting the scarcity of potential control measures that would
qualify as contingency measures given the facts and circumstances of
the San Joaquin Valley,\44\ where the progressively stringent set of
control measures adopted to meet prior attainment and RFP planning
requirements are already implemented measures and therefore ineligible
to serve as contingency measures.\45\ This scarcity concept echoes the
tension between the CAA requirements for attainment and contingency
measures, and the prioritization of adopting measures to attain in the
first place. Notwithstanding, the EPA does not endorse the scarcity
concept as a starting point, but rather recommends the detailed
analytical approach to identifying and evaluating potential control
measures that can serve as contingency measures, as described in the
Draft Revised Contingency Measures Guidance, and that the State
employed in developing the PM2.5 Contingency Measure SIP.
---------------------------------------------------------------------------
\44\ SJV PM2.5 Contingency Measure SIP, section 4.1
(``Stringency of District's Regulatory Program'') and section 5.2
(``CARB's Opportunities for Contingency Measures'').
\45\ SJV PM2.5 Contingency Measure SIP, pp. 53-54.
---------------------------------------------------------------------------
Regarding the commenters' suggestion that a state could reduce the
amount of emission reductions needed for contingency measures by
requesting a voluntary reclassification that would extend the amount of
time to attain while relying on the same level of emission reductions,
we disagree that such an action runs contrary to the general remedial
scheme of the CAA that imposes more stringent requirements on
reclassified areas. Under the statutory and regulatory requirements for
PM2.5, a State may request reclassification from Moderate to
Serious, but only where it can show that it is impracticable to attain
by the Moderate area attainment year.\46\ Thus, a combination of direct
PM2.5 and plan precursor emission reductions that would
achieve attainment would constrain the ability of the State to seek
such reclassification--it would instead be practicable to attain by the
Moderate area attainment date. Similarly, if the Moderate area
attainment year were approaching and air quality for two of three
design value years indicated that the area would not achieve the
standard, then the air quality basis resulting from prior attainment
planning would be insufficient to attain. In either case, the State
would need to develop a Serious area plan that achieves additional
emission reductions and also addresses the additional control
requirements for Serious areas (e.g., tighter new source review
requirements, BACM and best available control technology (BACT), and,
if the State were to seek an attainment date extension under CAA
section 188(e), most stringent measures (MSM)).
---------------------------------------------------------------------------
\46\ CAA section 188(b)(1) and 40 CFR 51.1002(b)(1).
---------------------------------------------------------------------------
For these reasons, as well as those described in Response to
Comment 1 of this document, we conclude that the EPA's revised metric
for contingency measure emission reductions (OYW of progress) does not
run contrary to the general remedial scheme of the CAA that imposes
more stringent requirements on areas reclassified to a higher
classification. Lastly, the EPA finds that the comment on a
hypothetical scenario for an ozone nonattainment area is outside the
scope of this rulemaking because we are not acting on ozone contingency
measure SIP submissions in this action.
Comment 4: Regarding feasibility assessments, the Valley EJ
Organizations state that the CAA does not subject the contingency
measure requirements to a feasibility standard and reject the State's
and the EPA's proposed reliance on infeasibility demonstrations. The
commenters argue that Congress made no exceptions to the contingency
measure requirements nor did it provide authority to relax those
requirements based on technological or economic challenges. They state
that the CAA requirements for RACM or reasonably available control
technology (RACT) include a ``reasonably available'' qualifier and that
those for MSM are expressly limited to ``feasible'' measures, while
such terms do not appear in the CAA requirements for contingency
measures. They contend that the EPA conflates the contingency measure
requirements with the primary requirements to attain the NAAQS in the
first place. They further state that Congress expressly provided
limited authority to relax the CAA requirements for RFP but did not do
so for contingency measures.
The commenters state that the RACM requirements (under CAA sections
172(c)(1), 181(a)(1), and 188(c)(1)) require that the primary
attainment strategy include ``all'' RACM and other available control
measures that would expedite attainment and that the MSM provision (for
Serious PM2.5 nonattainment areas that cannot attain the
standards within 10 years, under CAA section 188(e)) requires
additional control measure implementation. They argue that contingency
measures should not comprise the same controls that the CAA already
requires for attainment and that failed to attain the NAAQS in the
first place and that the EPA unlawfully and arbitrarily excuses
contingency measures needed when the feasible measures the State has
already adopted result in a failure to attain the NAAQS (citing AIR, 10
F.4th at 946).
Given these alleged flaws in the EPA's interpretation, the
commenters state that the EPA's proposed approval violates the plain
meaning of the CAA contingency measure requirement, fails to reasonably
explain the Agency's relaxation of the emission reductions that
contingency measures must provide, and is therefore arbitrary and
capricious.
Response to Comment 4: As discussed in Response to Comment 1,
Congress must have at least implicitly delegated to the EPA the
authority to determine an amount of emissions reductions that
contingency measures should achieve and thereby give meaning to the
requirement and provide states with a basis to comply with CAA section
172(c)(9) for a given nonattainment area. The EPA is continuing to take
a policy approach to this question and is recommending OYW of progress
and describing a specific analytical framework that states may use to
develop a reasoned justification if the state is unable to identify and
adopt contingency measures that can achieve the recommended amount of
emissions reductions. More specifically, as stated in our proposed rule
and the EPA's Draft Revised Contingency Measures Guidance, where a
state is unable to identify contingency measures that would provide
approximately OYW of emission reductions, the state should provide a
reasoned justification (referred to herein as an ``infeasibility
demonstration'') that explains and documents how it has evaluated all
existing and potential control measures relevant to the appropriate
source categories and pollutants in the nonattainment area and has
reached reasonable conclusions regarding whether such measures are
feasible.\47\ Thus, while the EPA acknowledges that
[[Page 80757]]
CAA section 172(c)(9) does not explicitly provide for consideration of
whether specific measures are feasible, the EPA does not read the
statute to require air agencies to adopt and impose infeasible
measures.\48\
---------------------------------------------------------------------------
\47\ 88 FR 87988, 87994 and EPA's Draft Revised Contingency
Measure Guidance, p. 29.
\48\ Id.
---------------------------------------------------------------------------
As stated in the proposed rule, the statutory provisions applicable
to other nonattainment area plan control measure requirements,
including RACM/RACT, BACM/BACT, and MSM, allow air agencies to exclude
certain control measures that are deemed unreasonable or infeasible
(depending on the requirement).\49\ For example, the MSM provision in
CAA section 188(e) requires plans to include ``the most stringent
measures that are included in the implementation plan of any state or
are achieved in practice in any state, and can feasibly be implemented
in the area.'' While the contingency measures provisions do not include
such caveats, the EPA does not conclude that the contingency measures
provisions should be read to require plans to include infeasible
measures. Thus, the EPA anticipates that a demonstrated lack of
feasible measures would be a reasoned justification for adopting
contingency measures that achieve less than the recommended amount of
emission reductions.\50\
---------------------------------------------------------------------------
\49\ Id.
\50\ Moreover, we note that contingency measures under CAA
section 172(c)(9), once triggered, are generally permanent and
become one of the baseline control measures for the next milestone
demonstration or the new attainment plan that must be adopted and
submitted by the state for an area that has failed to attain the
NAAQS by the applicable attainment date. As noted in this document,
technological and economic feasibility is a hallmark of such control
measures. In contrast, CAA section 110(a)(2)(G) requires states to
adopt and submit contingency plans to address emergency episodes as
part of their SIPs, and the contingency plans for emergency episodes
identify emission control actions to be taken at different episode
levels, which are much higher than the NAAQS, without consideration
of economic or technological feasibility. See, generally, 40 CFR
51.150-51.152 and appendix L to 40 CFR part 51. One significant
difference, however, between the emission control actions for
emergency episode plans under CAA section 110(a)(2)(G) and the
control measures relied upon for RFP and attainment is that the
former are temporary and are implemented only while the emergency
episode persists whereas the latter are, as noted, permanent
controls for the area.
---------------------------------------------------------------------------
The EPA does not, as the commenters suggest, simply conflate the
contingency measure requirements with other control requirements (e.g.,
RACM/RACT, BACM/BACT, and MSM) that are integral to demonstrating
attainment of the ozone and/or PM2.5 NAAQS. Rather, while
the analytical approach to identifying and evaluating existing and
potential control measures may be similar to those used for RACM/RACT,
BACM/BACT, and MSM (e.g., identifying the universe of control devices
that can reduce NOX emissions from combustion equipment and
whether they are technologically and economically feasible as applied
to a specific type of emission source in the area), the EPA expects
that the state ``should not simply repeat the control strategy's
infeasibility showing.'' \51\ The contingency measure requirement is in
addition to the other control measure requirements.
---------------------------------------------------------------------------
\51\ EPA's Draft Revised Contingency Measure Guidance, p. 31.
---------------------------------------------------------------------------
A conclusion that a measure is not reasonable or feasible, for
example, for RACM does not automatically disqualify it as a potential
contingency measure. If the state identifies control measures that it
determines are not needed to attain nor to collectively advance
attainment, those measures would not be required to satisfy the RACM
requirement but would remain as candidates for contingency measures. To
the extent that the adopted contingency measures achieve a small amount
of emission reductions, the state should provide a more robust
infeasibility showing that there are no additional feasible contingency
measures that could achieve the recommended amount of reductions.\52\
Furthermore, to the extent that the state's analyses and development of
contingency measures occur after the state's analyses and development
of the SIP submissions to meet the attainment control strategy
requirements of the CAA (including associated control requirements and
RFP), the state should update their analyses to reflect the latest
potential control measures.
---------------------------------------------------------------------------
\52\ EPA's Draft Revised Contingency Measure Guidance, p. 31.
---------------------------------------------------------------------------
In the case of the SJV PM2.5 Contingency Measure SIP,
submitted in 2023, CARB and the District documented their analyses to
identify and evaluate potential control measures that might serve as
contingency measures. These analyses are updated relative to their 2021
submission of the Serious area attainment plan for the 1997 annual
PM2.5 NAAQS and to their 2019 submissions of the Serious
area attainment plan for the 1997 24-hour PM2.5 NAAQS
(including BACM demonstration), Serious area plan for the 2006 24-hour
PM2.5 NAAQS (including demonstrations for BACM and MSM), and
Moderate area plan for the 2012 annual PM2.5 NAAQS
(including RACM demonstration). The EPA has approved these attainment
plan control strategies in successive actions \53\ and they represent
an overall stringent set of control requirements. The State did not set
aside measures for lack of their ability to collectively advance
attainment (as might be possible in theory, e.g., for RACM for an ozone
nonattainment area).
---------------------------------------------------------------------------
\53\ 88 FR 86581 (December 14, 2023) (approving the State's
demonstrations for BACM and five percent annual emission reductions
under CAA section 189(d) for the 1997 annual PM2.5
NAAQS); 87 FR 4503 (January 28, 2022) (approving the State's BACM
demonstration for the 1997 24-hour PM2.5 NAAQS); and 85
FR 44192 (July 22, 2020) (approving the State's demonstrations for
BACM and MSM for the 2006 24-hour PM2.5 NAAQS).
---------------------------------------------------------------------------
In their updated analyses, CARB and the District considered the
wide range of emission sources under their primary jurisdiction,
identified potential control measures, analyzed their technological and
economic feasibility, and assessed whether they could achieve emission
reductions within one to two years of a triggering event, consistent
with the EPA's discussion of the timing objective inherent to the
contingency measure requirement.\54\ For the potential control measures
identified through this process, the District further analyzed possible
contingency measures for wood burning fireplaces and wood burning
heaters, rural open areas, commercial charbroiling, almond harvesting,
and oil and gas production combustion equipment, and ultimately adopted
the Residential Wood Burning Contingency Measure and the Rural Open
Areas Contingency Measure.
---------------------------------------------------------------------------
\54\ 88 FR 87988, 88000-88001 (summary of State's feasibility
analyses), and 88005-88009 (the EPA's evaluation of the State's
feasibility analyses). See also Draft Revised Contingency Measures
Guidance, pp. 40-42.
---------------------------------------------------------------------------
CARB, in turn, made a reasonable case that new engine standards and
new fleet requirements require more time to implement than would be
appropriate for contingency measures (i.e., would exceed one to two
years after a triggering event) and that the State's technology-forcing
and zero-emission-based nature of its mobile source regulations reduce
or eliminate opportunities for yet-further emission reductions that
could qualify as contingency measures.\55\ Nevertheless, through its
process CARB ultimately adopted the Smog Check Contingency Measure.
---------------------------------------------------------------------------
\55\ 88 FR 87988, 88008-88009.
---------------------------------------------------------------------------
The three contingency measures proposed for approval stand in
contrast to the commenters' argument that the feasibility assessment
process put forward in the EPA's Draft Revised Contingency Measure
Guidance, in the State's 2023 SIP Submissions, and the EPA's proposed
approval thereof would simply re-employ the control measures originally
employed to attain the PM2.5 NAAQS in the San Joaquin
Valley. Furthermore, in many instances the
[[Page 80758]]
reason for which the EPA agreed with the State for not adopting a
potential control measure as a contingency measure was not based on any
affirmation that a measure was economically infeasible, but rather was
based on other reasons. In evaluating CARB and the District's
infeasibility demonstrations in the SJV PM2.5 Contingency
Measure SIP, we relied heavily on the ``EPA Source Category and Control
Measure Assessment and Reasoned Justification Technical Support
Document, Proposed Contingency Measures Federal Implementation Plan for
the Fine Particulate Matter Standards for San Joaquin Valley,
California,'' July 2023 (``EPA's Reasoned Justification TSD'') given
its breadth and depth, as well as the expertise of EPA Region IX staff,
to review the State's demonstrations, understand where the State's
analyses and the EPA's analyses draw largely similar conclusions, and
identify those source categories where the control measure analyses
differ.
For example, for the potential control measure of requiring
electric water heaters and furnaces at point of sale, the EPA
determined that such a measure would not be feasible because we expect
that it would result in negligible emission reductions within two years
after trigger, consistent with the District's suggestion that the
attrition-based nature of implementation of this contingency measure
option deem the measure infeasible.\56\ For the potential control
measure of requiring low-dust almond harvesters, the EPA determined
that such a measure would be infeasible based only on the timing of
emission reductions.\57\
---------------------------------------------------------------------------
\56\ 88 FR 87988, 88007, and EPA's Reasoned Justification TSD,
pp. 43-51.
\57\ 88 FR 87988, 88007, and EPA's Reasoned Justification TSD,
pp. 43-51.
---------------------------------------------------------------------------
For the potential control measure of requiring the installation of
control devices on commercial under-fired charbroilers, the EPA
determined that such measure would be infeasible based on fire safety
certification concerns and lack of demonstrated implementation of
controls.\58\ For the potential control measure of lower NOX
emission limits on oil and gas production equipment with a total rated
heat input of greater than 5.0 million Btu per hour, the EPA determined
that it would be technologically infeasible to meet the lower limits
within the two-year timeframe for contingency measures due to the
likely requirement that affected units would need to install selective
catalytic reduction (SCR) devices to meet the lower limits (i.e., the
planning, engineering, and installation of SCR would take more than two
years).\59\ Similarly, for the potential control measure of lower
NOX emission limits for boilers, steam generators, and
process heaters with a total rated heat input of 5.0 million Btu per
hour or less, the EPA expects that units required to meet lower limits
than those already adopted in Rules 4307 and 4308 would require
installation of SCR, which cannot be feasibly achieved within the two-
year timeframe for contingency measures.\60\
---------------------------------------------------------------------------
\58\ 88 FR 87988, 88008, and EPA's Reasoned Justification TSD,
chapter V.
\59\ 88 FR 87988, 88008, and EPA's Reasoned Justification TSD,
pp. 9-22.
\60\ 88 FR 87988, 88008, and EPA's Reasoned Justification TSD,
pp. 9-22.
---------------------------------------------------------------------------
In sum, the EPA maintains that it does not read the statute to
require air agencies to adopt and impose infeasible measures.
Furthermore, as applied to the SIP submissions subject to this
rulemaking, we continue to find that the State's three contingency
measures for the San Joaquin Valley for the 1997 annual, 2006 24-hour,
and 2012 annual PM2.5 NAAQS, in conjunction with the State's
infeasibility demonstrations that adequately justify the contingency
measures selected by the State, meet the contingency measure
requirement under CAA section 172(c)(9) and 40 CFR 51.1014.
Comment 5: The Valley EJ Organizations assert that the EPA
unlawfully and arbitrarily proposes approval of the PM2.5
contingency measures based on the Agency's new interpretation in the
Draft Revised Contingency Measures Guidance by extending the
implementation period from one year to two years.
Response to Comment 5: With respect to the issue of extending the
period in which the emission reductions from contingency measures can
be considered in meeting the contingency measure SIP requirement, we
note that the commenters raise this particular objection to the EPA's
proposed approval in a single sentence and fail to elaborate on how
extending the time period for achieving the emission reductions from
contingency measures from one to two years conflicts with the CAA or
the EPA's implementing regulations.
In this instance, we proposed, and are now taking final action, to
approve two specific contingency measures (the Residential Wood Burning
Contingency Measures and the Rural Open Areas Contingency Measures),
both of which, if triggered, will achieve emission reductions within a
year of the triggering event. Our approval of the 2023 SIP Submissions
as meeting the contingency measure SIP requirement for San Joaquin
Valley for the relevant PM2.5 NAAQS also relies on emission
reductions from a third contingency measure (the Smog Check Contingency
Measure) that we have approved in a separate action.
As explained in the EPA's final rule on CARB's Smog Check
Contingency Measure, the emission reductions from the Smog Check
Contingency Measure may not be fully achieved until the second year
after the triggering event.\61\ However, as further explained in that
final rule, and consistent with the Draft Revised Contingency Measure
Guidance, in instances where there are insufficient contingency
measures available to achieve the recommended amount of emission
reductions within one year of the triggering event, contingency
measures that provide reductions within two years of the triggering
event could be appropriate to consider toward achieving the recommended
amount of emission reductions.\62\ Contingency measures that result in
additional emission reductions during the second year following the
triggering event, as contemplated by the Draft Revised Contingency
Measure Guidance, can still serve the important purpose of contingency
measures to continue progress toward attainment, as the State develops
and submits, and the EPA acts on, a SIP submission to address the
underlying condition (e.g., failure to make RFP or to attain by the
applicable attainment date) that triggered the contingency measures in
the first place.
---------------------------------------------------------------------------
\61\ 89 FR 56222, 56224-56225.
\62\ Id.
---------------------------------------------------------------------------
Comment 6: The Valley EJ Organizations state that, after a first
triggering event, the EPA unlawfully and arbitrarily allows California
discretion in adopting further contingency measures, fails to evaluate
whether the emission reductions to follow a second triggering event
would meet either OYW of RFP or OYW of progress, and allows California
to `` `double dip' for contingency measure purposes'' without
enforceable provisions that would require adoption and submission of
additional contingency measures.
Response to Comment 6: Our approval relates to the SIP requirements
for contingency measures under CAA section 172(c)(9) and 40 CFR 51.1014
for the 1997 annual, 2006 24-hour and 2012 annual PM2.5
NAAQS. Under the applicable requirements, states with PM2.5
nonattainment areas must provide contingency measures that can be
[[Page 80759]]
triggered in the event of a failure to meet any RFP requirement in an
attainment plan, to meet any quantitative milestone in an attainment
plan, to submit a quantitative milestone report, or to attain the
applicable PM2.5 NAAQS by the applicable attainment date.
Neither the CAA nor the EPA's regulations specify a minimum number
of contingency measures or prescribe separate contingency measures for
different contingency measure triggers. The CAA and the EPA's
regulations also do not preclude the reliance on the same contingency
measures for separate NAAQS, and the commenter does not identify any
specific statutory or regulatory requirement that does so. Moreover, it
is not uncommon for a state or district to rely on a core set of
control measures for multiple NAAQS. For example, the State and
District rely on a core set of NOX control measures as part
of the control strategies for demonstrating RFP and attainment for both
ozone and PM2.5 in the San Joaquin Valley. Regardless, we
acknowledge that neither the State nor District has submitted an
enforceable commitment to submit additional contingency measures in
response to the triggering of the contingency measures. The EPA does
not believe that such commitment is required.
In this instance, the 2023 SIP Submissions rely on three
contingency measures, all of which provide for an initial triggering
event and two of which provide for a second triggering event. In other
words, all three contingency measures provide for implementation of
more stringent requirements upon a first triggering event, and two of
the contingency measures also provide for implementation of yet more
stringent requirements upon a second triggering event (i.e., further
tightening of the requirements beyond that triggered by the first
event).
While the EPA is not requiring CARB or the District to provide
separate contingency measures for each of the triggering events or
separate contingency measures for different PM2.5 NAAQS in
San Joaquin Valley, we find that a SIP deficiency would arise upon the
first triggering event notwithstanding the existence of the built-in
provisions for further reductions upon a second triggering event. This
is because the adequacy of the contingency measure SIP depended on
measures that are now being implemented as a result of the first
triggering event, meaning they can no longer be used to satisfy the
contingency measure requirements for subsequent triggering events. In
response, we expect that CARB and the District would adopt and submit a
SIP revision within one year of the triggering event to demonstrate
that the SIP continues to meet contingency measure requirements. We
would also expect the SIP revision to take into account the emission
reductions from the two remaining contingency measures and to include
additional contingency measures as needed to ensure that the San
Joaquin Valley continues to meet the contingency measure requirements
of CAA section 172(c)(9) and 40 CFR 51.1014.
Comment 7: CVAQ asserts that the ``hot spot'' approach under
District Rule 4901, ``Wood Burning Fireplaces and Wood Burning
Heaters,'' ``cannot meet the basic control measure requirements of the
[CAA]'' and that the emission reductions from expanding applicability
to previously exempt areas would not be surplus to the controls that
should be required in the San Joaquin Valley. If, however, residential
wood burning is to be used as a contingency measure, CVAQ contends that
the contingency measure in Rule 4901 should ban all non-essential wood
burning. CVAQ further contends that the District must adopt contingency
measures that would achieve OYW of RFP emission reductions in each
county of the San Joaquin Valley to protect its most vulnerable
communities. In addition, citing comments made by residents during 2023
District workshops that report incidents of poor enforcement of the
rule, CVAQ asserts that Rule 4901 has no assurance of actual emission
reductions and no concrete commitments for enforcement. CVAQ advocates
for accountability measures to ensure actual emission reductions and
enforcement of residential wood burning regulations.
Response to Comment 7: The EPA maintains that the Residential Wood
Burning Contingency Measure in SJVUAPCD Rule 4901 meets the contingency
measure requirements and provides reasonable assurance of emission
reductions. As explained in our proposed rule,\63\ Rule 4901 includes a
tiered mandatory curtailment program that establishes different
curtailment thresholds based on the type of devices (i.e., registered
clean-burning devices vs. unregistered devices) and different counties
(i.e., ``hot spot'' vs. non-hot spot), notwithstanding narrow
exemptions (e.g., for households where a wood burning fireplace or
heater is the sole source of heat, per section 5.7.4.2 of Rule 4901).
During a ``Level One Episodic Wood Burning Curtailment,'' operation of
wood-burning fireplaces and other unregistered wood-burning heaters or
devices is prohibited, but properly operated, registered wood-burning
heaters may be used. During a ``Level Two Episodic Wood Burning
Curtailment,'' operation of any wood-burning device is prohibited.
---------------------------------------------------------------------------
\63\ 88 FR 87988, 87995.
---------------------------------------------------------------------------
In 2019, the District lowered the curtailment thresholds in Madera,
Fresno, and Kern counties, which the District identified as hot spot
counties, because they were ``either new areas of gas utility or areas
deemed to have persistently poor air quality.'' \64\ Table 4 presents
the wood burning curtailment thresholds in Rule 4901, as revised in
2019.
---------------------------------------------------------------------------
\64\ 2018 PM2.5 Plan, Appendix J, 60.
Table 4--Residential Wood Burning Curtailment Thresholds in Rule 4901
[as amended in 2019]
------------------------------------------------------------------------
Non-hot spot
Hot spot counties counties (San
Episodic wood burning (Madera, Fresno, and Joaquin, Stanislaus,
curtailment levels Kern) Merced, Kings, and
Tulare)
------------------------------------------------------------------------
Level One (No Burning Unless 12 [mu]g/m\3\....... 20 [mu]g/m\3\.
Registered).
Level Two (No Burning for 35 [mu]g/m\3\....... 65 [mu]g/m\3\.
All).
------------------------------------------------------------------------
Contrary to the commenters' assertion that the hot spot approach
cannot meet the basic control measure requirements of the CAA, the EPA
approved the State's demonstration for Rule 4901 (2019 amendments) as
BACM and MSM for the 2006 24-hour PM2.5 NAAQS,\65\ as RACM
for the 2012 annual PM2.5 NAAQS,\66\ and as BACM for the
1997
[[Page 80760]]
annual PM2.5 NAAQS.\67\ In 2022, the Ninth Circuit upheld
the EPA's approval of the State's BACM and MSM demonstration for the
2006 24-hour PM2.5 NAAQS, including those relating to
residential wood burning.\68\ Therefore, the hot spot approach in Rule
4901 (2019 amendments), as applied to the particular facts and
circumstances of the San Joaquin Valley for the 1997 annual, 2006 24-
hour, and 2012 annual PM2.5 NAAQS, meets the applicable
control requirements for controlling direct PM2.5 emissions
from residential wood burning.
---------------------------------------------------------------------------
\65\ 85 FR 44192.
\66\ 86 FR 67343.
\67\ 88 FR 86581.
\68\ Medical Advocates for Healthy Air v. EPA, Case No. 20-
72780, Dkt. #58-1 (9th Cir., April 13, 2022), pp. 8-9.
---------------------------------------------------------------------------
The Residential Wood Burning Contingency Measure (i.e., the 2023
amendments to Rule 4901) would, upon a first triggering event, lower
the thresholds for the five non-hot spot counties to match those of the
hot spot counties (i.e., 12 [mu]g/m\3\ for Level One Curtailment and 35
[mu]g/m\3\ for a Level Two Curtailment) and the emission reductions in
those five counties would be surplus because lowering the thresholds
for the five non-hot spot counties would go beyond the requirements of
Rule 4901, as amended in 2019, that the EPA has approved as meeting
RACM, BACM, and MSM. Furthermore, upon a second triggering event, the
Level One Curtailment threshold would be further lowered to 11 [mu]g/
m\3\ for all eight counties in the San Joaquin Valley, resulting in
further emission reductions that would be surplus to the already
implemented measure and surplus to the reductions from the first
triggering event.
We note that the Residential Wood Burning Contingency Measure would
alone, if triggered, achieve 0.5793 tpd direct PM2.5
emission reductions, which would exceed OYW of RFP (per EPA's long-
standing approach) and OYW of progress (per EPA's draft revised
approach) for direct PM2.5 emissions in the San Joaquin
Valley. Given that the Residential Wood Burning Contingency Measure is
primarily a control for direct PM2.5,\69\ and that it would
achieve the recommended amount of reductions for that pollutant (in
terms of OYW of RFP or OYW of progress), the District was not required
to restrict residential wood burning further than what the District has
chosen to do for the purposes of meeting the contingency measure SIP
requirements for the relevant PM2.5 NAAQS. Thus, the
District was not required to include a ban on all non-essential wood
burning to meet the contingency measure SIP requirements. Furthermore,
in reviewing the District's evaluation of potential control measures
for residential wood burning,\70\ we relied heavily on the EPA's
detailed evaluation of source categories and measures that we
considered as potential additional contingency measures as part of our
federal implementation plan (FIP) proposal but determined to be
infeasible or otherwise unsuitable for contingency measures.\71\
---------------------------------------------------------------------------
\69\ Based on the estimates included in Table 2 (revised) in
this final rule, NOX reductions from the Residential Wood
Burning Contingency Measure would be approximately 14% of the
reductions of direct PM2.5.
\70\ SJV PM2.5 Contingency Measure SIP, section 4.2
(``District Feasibility Analysis''), pp. 26-31.
\71\ 88 FR 87988, 88005-88006, and the EPA's Reasoned
Justification TSD. For our discussion of the EPA's evaluation of a
potential wood burning ban, see p. 82 of the EPA's Reasoned
Justification TSD.
---------------------------------------------------------------------------
Regarding the commenters' contention that the District must adopt
contingency measures that would achieve OYW of RFP emission reductions
in each county of the San Joaquin Valley, we reiterate that CAA section
172(c)(9) does not specify what amount of emission reductions
contingency measures should achieve, much less whether contingency
measures should achieve particular amounts of emission reductions
within geographical regions within a nonattainment area (e.g., in each
county). In both our long-standing interpretation and draft revised
interpretation of the contingency measure requirement, the amount of
emission reductions (e.g., OYW of progress) should be estimated for the
nonattainment area as a whole, consistent with the emissions
inventories for the base year, RFP years, and attainment year that are
based on the whole area.\72\
---------------------------------------------------------------------------
\72\ EPA's Draft Revised Contingency Measures Guidance, pp. 23-
24. Notwithstanding, for informational purposes we note that the EPA
considered the geographic scope of each of the three contingency
measures proposed for approval, including the Residential Wood
Burning Contingency Measure. 88 FR 87988, 88010-88011.
---------------------------------------------------------------------------
Regarding comments on the enforceability of Rule 4901 and assurance
of actual emission reductions, we note that the District included
responses to similar comments received during the District's public
comment process on the public draft SJV PM2.5 Contingency
Measure SIP.\73\ We maintain that Rule 4901 is adequately enforceable
and that the emission reductions are reasonably estimated, for the
following reasons. The District explains the method it used to estimate
the emission reductions from the Residential Wood Burning Contingency
Measure, including its use of an 80% compliance rate.\74\ In
calculating these estimates, the District incorporates data by county,
device type (wood stoves and fireplaces), registration (unregistered
vs. registered, which incorporates certification of cleaner-burning
devices), fuel type (e.g., natural gas, wood, pellets), and average
curtailment days with and without the contingency provisions.
---------------------------------------------------------------------------
\73\ SJV PM2.5 Contingency Measure SIP, Appendix J
(``Comments and Response'').
\74\ SJV PM2.5 Contingency Measure SIP, Appendix C
(``Emission Reduction Analysis for Rule 4901''), C-7.
---------------------------------------------------------------------------
In evaluating the emission reductions estimates from the District,
and as part of the EPA's FIP proposal for PM2.5 contingency
measures in the San Joaquin Valley,\75\ we found that an 80% control
efficiency rate is reasonable in this case given the District's
extensive public outreach and enforcement of its curtailment
program.\76\ The EPA concludes that the District's method is a detailed
and reasonable means to estimate the emission reductions from the
Residential Wood Burning Contingency Measure.
---------------------------------------------------------------------------
\75\ EPA's Reasoned Justification TSD, section II (``Combustion:
Residential Wood Burning''), pp. 5-6.
\76\ See, e.g. SJVUAPCD, ``Report On 2021-2022 Winter
Residential Woodsmoke Reduction,'' April 21, 2022 (``District's 2022
Report''), pp. 19-28.
---------------------------------------------------------------------------
Regarding enforcement, the District states that it dedicates staff
to both compliance assistance and enforcement and describes several
aspects of its enforcement efforts.\77\ On curtailment days, District
staff surveil neighborhoods, focus on areas where non-compliance is
historically high or the subject of common complaints, and respond to
complaints from the public. The District responds to complaints during
business hours, weekends, holidays, and night-time hours and uses
technology such as global positioning system (GPS) and low-light
imaging cameras (for night-time enforcement) to assist their response.
During the most recent wood burning season (November 2023-February
2024), District staff spent approximately 3,500 hours on proactive
monitoring and enforcement and issued 470 notices of violation of Rule
4901.\78\ The EPA concludes that the District implements a reasonably
robust enforcement program to ensure compliance with the wood burning
[[Page 80761]]
prohibitions required when a Level One or Level Two Curtailment is
called by the District.
---------------------------------------------------------------------------
\77\ District's 2022 Report, pp. 26-28.
\78\ SJVUAPCD, ``Report on 2023-2024 Winter Residential
Woodsmoke Reduction Strategy,'' PowerPoint presentation prepared for
SJVUAPCD Citizens Advisory Committee, June 4, 2024, slide 16. For
summary information concerning enforcement of Rule 4901 in previous
seasons, see SJVUAPCD, ``Report On 2022-2023 Winter Residential
Woodsmoke Reduction,'' April 20, 2023, p. 28.
---------------------------------------------------------------------------
In sum, neither the District nor the EPA has assumed perfect
compliance with the provisions of the Residential Wood Burning
Contingency Measure (i.e., 100% control efficiency when a ``No Burn''
day is called for a given geographic region within San Joaquin Valley);
the District has provided reasonable assurance of 80% control
efficiency based on its outreach, enforcement, and performance
analyses; and the District reasonably estimates the amount of emission
reductions to follow either a first triggering event (0.5793 tpd direct
PM2.5 and 0.0817 tpd NOX) or a second triggering
event (0.1078 tpd direct PM2.5 and 0.0148 tpd
NOX). Therefore, we continue to find that the Residential
Wood Burning Contingency Measure is adequately enforceable and its
associated emission reductions are reasonably estimated.
Comment 8: CVAQ states that the Rural Open Areas Contingency
Measure is ``essentially meaningless given that agricultural operations
are exempt.'' They note that agricultural operations can implement a
Fugitive PM10 Management Plan (FPMP) as an alternative to
compliance requirements and that a more meaningful contingency measure
would enforce these FPMPs for all agricultural operations.
Response to Comment 8: While the estimated emission reductions of
0.008 tpd direct PM2.5 from the Rural Open Areas Contingency
Measure are small, we disagree with the commenters' characterization of
the measure's value. Specifically, section 7.0 (``Contingency
Provision'') of Rule 8051, ``Open Areas'' (2023 amendments) would, if
triggered, lower the applicability threshold for rural open areas from
3.0 acres to 1.0 acre, and owners and operators of those 1.0 to 3.0-
acre parcels would be newly subject to the fugitive dust control
requirements of Rule 8051.\79\ This measure, if triggered, would affect
entities such as construction, oilfield, truck stop, and equipment and
vehicle storage owners/operators, as identified in the District's
``Regulation VIII Recordkeeping Reporting Forms'' (revised June 1,
2009), as well as other residential, industrial, institutional,
governmental, or commercial lot owners/operators. When such entities
disturb 1,000 or more square feet of surface area within a 1.0 to 3.0-
acre parcel, they would be required to apply fugitive dust control
measures, consistent with the control requirements of section 5.0 of
Rule 8051. Moreover, while the emission reductions from the Rural Open
Areas Contingency Measure are small on a regional basis, they will be
more meaningful for residents and workers in the immediate vicinities
of the open areas to which Rule 8051 would apply if and when the
contingency measure is triggered.
---------------------------------------------------------------------------
\79\ The definition of open areas is provided in Rule 8011,
``General Requirements,'' section 3.36 (``. . . vacant portions of
residential or commercial lots and contiguous parcels that are
immediately adjacent to and owned and/or operated by the same
individual or entity are considered one open area. . .'').
---------------------------------------------------------------------------
With respect to agricultural operations in the San Joaquin Valley
and FPMPs, fugitive dust control requirements are governed by Rule
8081, ``Agricultural Sources,'' which covers off-field sources like
unpaved roads, unpaved vehicle and equipment traffic areas, and bulk
materials.\80\ Under section 7.0 of Rule 8081, an agricultural operator
may implement an FPMP for unpaved roads and unpaved vehicle/equipment
traffic areas as a compliance alternative to the control requirements
in sections 5.2.2, 5.3.1, and 5.3.2 of the rule. An FPMP must achieve
50% control efficiency for fugitive dust (PM10) and go
through a review and approval process prior to being implemented. It
must be implemented on all days that vehicle traffic exceeds the
applicable vehicle trip thresholds in sections 5.2.2, 5.3.1, and 5.3.2.
Under section 7.4 of Rule 8081, failure to comply with an approved FPMP
is deemed a violation of the rule.
---------------------------------------------------------------------------
\80\ We note that Rule 4550, ``Conservation Management
Practices'' includes fugitive dust control requirements for on-field
agricultural operations in the San Joaquin Valley, but does not
include provisions for FPMPs, unlike Rule 8081. Also, while there
are provisions for FPMPs in Rule 8061, ``Paved and Unpaved Roads''
and Rule 8071, ``Unpaved Vehicle/Equipment Traffic Areas,'' those
rules pertain to non-agricultural roads and vehicle/equipment
traffic areas, respectively, rather than the agricultural operations
referenced in the comments.
---------------------------------------------------------------------------
By comparison, sections 5.2.2, 5.3.1, and 5.3.2 require that
visible dust emissions (VDE) be limited to a 20% opacity standard and
comply with requirements for stabilization of unpaved roads \81\ by
application of at least one of a discrete set of control techniques
(e.g., watering, uniform layer of washed gravel, chemical/organic dust
stabilizers/suppressants). Section 5.2.2 applies to unpaved roads based
on vehicle daily trips; sections 5.3.1 and 5.3.2 apply to unpaved
vehicle/equipment traffic areas with thresholds based on annual and
daily vehicle trips, respectively.
---------------------------------------------------------------------------
\81\ By definition under section 3.59 of Rule 8011,
stabilization of unpaved roads and unpaved vehicle/equipment traffic
areas requires that VDE be limited to 20% opacity.
---------------------------------------------------------------------------
If, as the commenters suggest, all agricultural operations were
required, following a contingency measure triggering event, to
implement an FPMP, it is unclear whether such contingency measure would
achieve emission reductions that are surplus to those that are being
achieved under the existing rule. For agricultural operations already
implementing an FPMP, such contingency measure would result in no
change in emission reductions. For agricultural operations implementing
controls under section 5.2.2, 5.3.1, and 5.3.2 of Rule 8081 (i.e., not
implementing an FPMP), it is unclear whether an FPMP would achieve more
emission reductions than the standard control provisions (limit VDE to
20% opacity). Consistent with our final rule approving the 2003 San
Joaquin Valley attainment plan for the 1987 PM10 NAAQS into
the California SIP,\82\ we believe that the FPMP's 50% control
efficiency requirement is equivalent to the minimum control efficiency
expected from compliance with surface stabilization requirements in the
rule that otherwise apply.
---------------------------------------------------------------------------
\82\ 69 FR 30006 (May 26, 2004). We note that, at that time,
EarthJustice compared the 20% opacity and other aspects of the
control requirements in section 5.0 of Rule 8081 to the 50% control
efficiency requirement and lack of 20% opacity requirement in the
compliance alternative in section 7.0 of Rule 8081 and asserted that
the FPMP compliance alternative should not be included. 69 FR 30006,
30018. While we agreed that the FPMP alternative does not contain an
explicit requirement for sources to comply with 20% opacity, it is
unclear whether compliance with 20% opacity would necessarily
increase control efficiency for unpaved roads or unpaved vehicle/
equipment traffic areas above the minimum 50% control required under
the FPMP provisions of Rule 8081.
---------------------------------------------------------------------------
Furthermore, within the SJV PM2.5 Contingency Measure
SIP, the District states that it evaluated potential additional
controls (including those implemented by other jurisdictions) within
the application of Regulation VIII, ``Fugitive PM10
Prohibitions,'' and that the existing fugitive dust controls (including
those under Rule 8081) meet or exceed the requirements for RACM, BACM,
and MSM, and did not identify any further potential contingency
measure, with the exception of the potential measure in Rule 8051
(i.e., the measure ultimately adopted as the Rural Open Areas
Contingency Measure).\83\ In the EPA's review of potential control
measures (including those implemented by other jurisdictions), we
similarly did not identify additional measures for unpaved roads that
would be suitable as contingency measures.\84\ Therefore, we
[[Page 80762]]
disagree with the commenters that enforcing FPMPs on all agricultural
operations would qualify as a contingency measure. Nonetheless, we
recommend that the District continue to explore potential contingency
measures for dust emissions from agricultural sources, whether within
the construct of the FPMP framework in Rule 8081 or more broadly, e.g.,
within the construct of other rules such as Rule 4550, ``Conservation
Management Practices.''
---------------------------------------------------------------------------
\83\ SJV PM2.5 Contingency Measure SIP, p. 25.
\84\ EPA's Reasoned Justification TSD, pp. 109-114.
---------------------------------------------------------------------------
Comment 9: The Valley EJ Organizations state that the EPA's
proposed approval of the State's contingency measures ignores
Presidential orders that direct the EPA and other federal agencies to
prioritize environmental justice, including Executive Order 14008,
``Tackling the Climate Crisis at Home and Abroad'' (January 27, 2021)
and Executive Order 14096, ``Revitalizing our Nation's Commitment to
Environmental Justice for All'' (April 21, 2023).\85\ They further
argue that the EPA exacerbates the ``environmental justice crisis'' by
denying the residents of the San Joaquin Valley meaningful pollution
reductions. To convey the magnitude of this concern, the commenters
cite to American Lung Association rankings of counties for
PM2.5 and ozone pollution (where many San Joaquin Valley
counties rank among the worst in the nation) and the EPA's review of
environmental justice indices (where many San Joaquin Valley counties
exceed the 90th percentile) and describe the sequence of failures to
attain the NAAQS by the applicable attainment dates in San Joaquin
Valley, as well as recent air quality design values for the 1997 8-hour
ozone NAAQS and the 1997 annual PM2.5 NAAQS that portend the
same.
---------------------------------------------------------------------------
\85\ Valley EJ Organizations Comment Letter, pp. 4-6. See also,
86 FR 7619 (February 1, 2021) (Executive Order 14008) and 88 FR
25251 (April 26, 2023) (Executive Order 14096).
---------------------------------------------------------------------------
In addition, CVAQ argues that the EPA's proposed approval goes
against the Biden Administration's environmental justice priorities by
``refusing to hold the region's largest polluters accountable,
discounting community priorities and continuing racist polluting
practices.'' They state that EPA is only looking at technological
feasibility and costs to industry and is not analyzing social and
health impacts in determining the cost of not taking action.
Response to Comment 9: We agree that the San Joaquin Valley has
many communities with EJ concerns that are disproportionately impacted
by PM2.5 and other kinds of air pollution. However, we
disagree that the EPA's proposed approval ignores Presidential orders
to prioritize environmental justice. First, the Residential Wood
Burning Contingency Measure and the Rural Open Area Contingency
Measure, as well as the Smog Check Contingency Measure, would,
following a triggering event, reduce emissions from residential wood
burning, rural open areas, and light-duty vehicles across the San
Joaquin Valley, including minority and low-income populations, as
described in section VI (``Environmental Justice Considerations'') of
our proposed rule.\86\
---------------------------------------------------------------------------
\86\ 88 FR 87988, 88009-88011. In section VI of our proposed
rule, we discuss environmental justice considerations in the context
of Executive Order 12898 (``Federal Actions To Address Environmental
Justice in Minority Populations and Low-Income Populations'') rather
than by reference to Executive Orders 14008 or 14096. Executive
Order 12898 directs federal agencies ``to identify and address
disproportionately high and adverse human health or environmental
effects of their actions on minority and low-income populations, to
the greatest extent practicable and permitted by law.'' Executive
Order 14008 directs federal agencies to take certain actions
directed toward ``disadvantaged communities'' that are described as
``historically marginalized and overburdened.'' Executive Order
14096 builds upon and supplements Executive Orders 12898 and 14008.
All three Executive Orders direct federal agencies to identify and
address disproportionate environmental effects, even while the
particular directives and protected classes vary among the three
orders.
---------------------------------------------------------------------------
While not a comprehensive solution to address the
disproportionately high PM2.5 concentrations to which these
populations are exposed, the three contingency measures would achieve
more than OYW of emission reductions for direct PM2.5 and a
portion of the OYW of emission reductions for NOX, as
described in our proposed rule \87\ and updated in section I.B of this
document. Therefore, our proposed approval of these measures is
directionally consistent with Executive Orders 14008 and 14096, as well
as Executive Order 12898, ``Federal Actions to Address Environmental
Justice in Minority and Low-Income Populations'' (February 11,
1994).\88\
---------------------------------------------------------------------------
\87\ 88 FR 87988, 88003-88005.
\88\ 59 FR 7629 (February 16, 1994).
---------------------------------------------------------------------------
To the extent that the commenters disagree with the EPA's Draft
Revised Contingency Measure Guidance or our application thereof to the
facts and circumstances of the San Joaquin Valley, we maintain that the
CARB and the District's 2023 SIP Submissions meet the requirements of
CAA section 172(c)(9) and 40 CFR 51.1014 and are approving the
submissions on that basis. The EPA carefully reviewed the extensive
recommendations put forward by environmental, public health, and
community organizations regarding additional potential control measures
on stationary and area sources in the San Joaquin Valley \89\ and
documented our analyses thereof in the EPA's Reasoned Justification
TSD.\90\ We relied heavily on that TSD in our evaluation of the CARB
and the District's 2023 SIP Submissions and, where our conclusions
differed from CARB or the District's conclusions with respect to the
basis of a potential additional control measure not meeting the
contingency measure requirements, we explained those differences, as
noted in the latter part of Response to Comment 4 of this document.
Nevertheless, those control measure recommendations retain their value
for consideration as CARB and the District develop, and the EPA
reviews, further SIPs for the San Joaquin Valley, even while we
conclude that they are not required to meet the contingency measure
requirements for the PM2.5 NAAQS in the San Joaquin Valley
at this time.
---------------------------------------------------------------------------
\89\ See letter dated October 22, 2021, from environmental
organizations to Michael S. Regan, Administrator, EPA, Subject:
``Meeting Request to Discuss PM-2.5 Crisis in the San Joaquin
Valley,'' and letter dated May 18, 2022, from environmental
organizations to Michael S. Regan, Administrator, Environmental
Protection Agency, Subject: ``Meeting Request to Discuss PM-2.5
Crisis in the San Joaquin Valley'' (referred to in the EPA's
Reasoned Justification TSD as the ``EarthJustice Letters'').
\90\ EPA's Reasoned Justification TSD, p. 6 (within section II
(``Control Measure Identification and Evaluation Methodology'')),
pp. 13-17 (large boilers, steam generators, and process heaters), 29
(non-road, reciprocal internal combustion engines), pp. 58-59
(flares), pp. 73-76 (glass and related products), 80-84 (residential
fuel combustion), p. 85 (fugitive dust controls), pp. 129-131
(managed burning and disposal), pp. 134-136 (commercial cooking), p.
147 (new source review), pp. 149-151 (indirect source review), and
pp. 151-152 (soil NOX). We also noted that we did not
review the environmental organizations' recommendations for
primarily VOC-related controls, as the EPA has approved the State's
demonstrations that VOCs are not significant precursors for 1997
annual, 2006 24-hour, and 2012 annual PM2.5 NAAQS in the
San Joaquin Valley. See, e.g., p. 53 (petroleum production and
marketing), and p. 88 (confined animal facilities).
---------------------------------------------------------------------------
Regarding CVAQ's comments regarding technological feasibility and
costs to industry versus social and health impacts, we agree that the
State, in its 2023 SIP Submissions, and the EPA, in our review thereof,
considered the technological feasibility of potential control measures
and reviewed available information regarding the economic feasibility
of potential control measures (i.e., which captures costs to industry).
However, we did not assess the public health and social costs of not
requiring potential control measures during our review of the State's
2023 SIP Submissions because such an assessment is not required for the
contingency measure requirements of the CAA, nor the related control
[[Page 80763]]
measure requirements (e.g., RACM/RACT, BACM/BACT, or MSM) upon which
contingency measures build.\91\
---------------------------------------------------------------------------
\91\ Nevertheless, beyond the scope of this rulemaking, the
public may be interested in the EPA's estimates of the monetized
benefit per ton of reducing PM2.5 and ozone precursor
emissions for certain emission sectors; available at https://www.epa.gov/benmap/sector-based-pm25-benefit-ton-estimates.
---------------------------------------------------------------------------
In addition, while the EPA may in certain circumstances have
discretion to consider environmental justice in implementing the
requirements of the Act, Executive Orders 12898, 14008, and 14096 do
not provide any independent authority for action. The EPA has
determined that this action satisfies the requirements of CAA section
172(c)(9) for the 1997 annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS in the San Joaquin Valley. Under the CAA, the
EPA is required to approve a SIP submission that meets the requirements
of the CAA and applicable federal regulations.
Although these Executive Orders do not provide us with an
independent basis to disapprove CARB and the District's SIP submission,
we conducted an environmental justice analysis to provide additional
context and information about this rulemaking to the public, as
described in section III of this document and section VI of our
proposed rule. Overall, we expect that this action and the codification
of the Residential Wood Burning Contingency Measure and the Rural Open
Areas Contingency Measure, as well as the codification of the Smog
Check Contingency Measure in our separate final action, will contribute
to reduced negative environmental and health impacts on all populations
in the San Joaquin Valley, including communities with EJ concerns. For
these reasons, this action is not expected to have a disproportionately
high or adverse human health or environmental effect on a particular
group of people. The EPA remains committed to working with CARB and the
District to ensure that the PM2.5 attainment requirements
for this area satisfy applicable CAA requirements and thereby protect
all populations in the area, including communities with EJ concerns,
from disproportionately high or adverse air pollution impacts.
Comment 10: The Valley EJ Organizations allege that, following the
2021 Ninth Circuit Court decision in AIR v. EPA, the EPA began
colluding with CARB and California air districts to weaken the
contingency measure requirement. The Valley EJ Organizations further
state that, during meetings of a workgroup called the ``Padilla
Contingency Measures Subgroup,'' the EPA committed to revise its long-
standing interpretation of the contingency measure requirements,
including specific elements that would relax emission reduction
requirements and contend that the EPA's commitment yielded the Draft
Revised Contingency Measure Guidance.\92\ The commenters also contend
that the EPA now proposes, as it allegedly agreed to during the Padilla
Contingency Measures subgroup proceedings, to ``eviscerate the amount
of contingency measure emission reductions'' and that the ``EPA has
predetermined the outcome of these proposed rulemakings in an agreement
with CARB and the air districts during the Padilla Contingency Measures
Subgroup proceedings,'' thereby violating the procedural due process
clause of the Fifth Amendment to the U.S. Constitution, CAA section
307, the Administrative Procedure Act, and Executive Orders 14008 and
14096.\93\
---------------------------------------------------------------------------
\92\ Valley EJ Organizations Comment Letter, p. 2.
\93\ Valley EJ Organizations Comment Letter, p. 11.
---------------------------------------------------------------------------
The Valley EJ Organizations include several documents obtained from
the EPA via a Freedom of Information Act request to support their
allegation of collusion.\94\ These include, among other things,
documents relating to EPA engagement in 2021-2023 with the California
Air Pollution Control Officers Association (CAPCOA), the ``Padilla
Contingency Measures Subgroup,'' a letter from South Coast Air Quality
Management District, discussions with California air districts and CARB
senior staff, and an email from EPA Region IX to SJVUAPCD. The
commenters state that these documents indicate that the EPA worked
closely with California air agencies to fashion an agreement to weaken
the contingency measure requirement and that the EPA shared its revised
guidance with the California agencies several months before releasing
the revised guidance to the general public without regard for the
public health consequences from weakening the contingency measure
requirement.\95\
---------------------------------------------------------------------------
\94\ Valley EJ Organizations Comment Letter, Exhibits 4 through
12.
\95\ Valley EJ Organizations Comment Letter, pp. 8-11.
---------------------------------------------------------------------------
Response to Comment 10: We disagree that the EPA colluded with
California air agencies to weaken the contingency measure requirement
following the 2021 AIR v. EPA decision by the Ninth Circuit Court of
Appeals. In this context, collusion refers to a secret agreement for an
illegal purpose. The process we followed to reconsider and revise
preexisting contingency measure guidance was not secret, nor was our
agreement to reconsider and revise the guidance made for an illegal
purpose.
The Clean Air Act is referred to as a model of cooperative
federalism. Under the CAA, the EPA is responsible for establishing the
NAAQS, and the states are responsible for developing SIPs and SIP
revisions to provide for implementation, maintenance, and enforcement
of the NAAQS. In turn, the EPA is responsible for promulgating
regulations establishing SIP requirements and for providing guidance to
the states in developing SIPs and SIP revisions to meet the various
requirements under the CAA and our implementing regulations.
In that capacity, it is appropriate for the EPA to reconsider
previously-issued guidance in the wake of court decisions that bear on
EPA actions on SIPs that relied on that guidance.\96\ In this instance,
as discussed in the Draft Revised Contingency Measure Guidance, we
issued the draft revised guidance document because recent court
decisions had invalidated key aspects of EPA's historical approach to
implementing the contingency measure requirement, and these court
decisions had the effect of prohibiting an approach that many air
agencies have historically used to meet the contingency measure
requirement.\97\
---------------------------------------------------------------------------
\96\ See, for example, EPA Office of Transportation and Air
Quality, ``Implementing Clean Air Act Section 182(d)(1)(A):
Transportation Control Measures and Transportation Control
Strategies to Offset Growth in Emissions Due to Growth in Vehicle
Miles Travelled,'' EPA-420-B-12-053, August 2012 (revised guidance
in light of the Ninth Circuit Court of Appeals decision in
Association of Irritated Residents v. EPA, 632 F.3d 584, at 596-597
(9th Cir. 2011), reprinted as amended on January 27, 2012).
\97\ Draft Revised Contingency Measure Guidance, p. 2.
---------------------------------------------------------------------------
The EPA developed the Draft Revised Contingency Measure Guidance
based on the recommendations of an ad hoc internal working group,
referred to as the Contingency Measure Task Force, that the EPA
assembled soon after the D.C. Circuit Court of Appeals decision in
Sierra Club v. EPA.\98\ The Contingency Measure Task Force was
comprised of EPA program staff and attorneys from both the EPA regions
and headquarters. During the process of developing options for EPA
management consideration and preparing the Draft Revised Contingency
[[Page 80764]]
Measure Guidance, California air agencies made their views known to the
EPA, but those agencies played no part in the drafting or review of the
recommendations made by the Contingency Measure Task Force to EPA
management or the substance of the Draft Revised Contingency Measure
Guidance itself.
---------------------------------------------------------------------------
\98\ The Sierra Club v. EPA decision adopted the rationale of an
earlier decision by the Ninth Circuit Court of Appeals in Bahr v.
EPA that invalidated already-implemented measures as contingency
measures for the purposes of CAA section 172(c)(9). Sierra Club v.
EPA, 21 F.4th 815, 827-28 (D.C. Cir. 2021) and Bahr v. EPA, 836 F.3d
1218 (9th Cir. 2016).
---------------------------------------------------------------------------
Also in the spirit of cooperative federalism, the EPA routinely
communicates with state and local air agencies responsible for SIPs and
SIP revisions regarding compliance with SIP requirements. Again, the
states are responsible for adoption and submission of SIPs and SIP
revisions and there are consequences for failure to meet SIP submission
deadlines.
In this instance, the EPA engaged with state and local air agencies
to hear their concerns over meeting the contingency measure SIP
requirements and to provide a description of the types of revisions to
the contingency measure guidance that EPA staff were developing for
consideration by EPA management. The impetus for heightened interest on
the part of state and local air agencies was the need to meet near-term
deadlines for submission of SIP revisions addressing the contingency
measure SIP requirements for multiple ozone and PM2.5 NAAQS.
Documents cited by the commenter as evidence of collusion simply reveal
that the EPA was responsive to state and local agency requests for
insight as to what the contingency measure guidance revisions might
entail if and when approved by EPA management. Thus the air agencies
that developed SIP revisions in reliance on the descriptions by EPA
staff of not-yet-approved revisions to the contingency measure guidance
were taking a risk that the guidance, once made publicly available,
would differ in material ways from what EPA staff had described.
With respect to the commitments that the EPA made in connection
with the Padilla Contingency Measures Subgroup,\99\ the EPA did not
commit to making any specific revisions to the contingency measure
guidance or to making any revisions to the guidance that are
inconsistent with the CAA or case law. Rather, the Agency committed
``to explore interpretations and approaches that are consistent with
the court decisions'' and, among other things, ``to revisit'' the
general bases for calculating the amount of emission reductions that
contingency measures should provide, but as noted previously, the EPA
did not commit to any particular outcome. The Contingency Measure Task
Force followed through on these commitments through meetings and review
of draft documents that were internal to the EPA and eventual
publication of notice in the Federal Register of the availability of
the Draft Revised Contingency Measure Guidance for public review and
comment. We believe the revised draft guidance provides an approach
that state and local air agencies may use to meet the contingency
measure SIP requirements under the CAA.
---------------------------------------------------------------------------
\99\ The Padilla Contingency Measures Subgroup was one of
several such ad hoc groups assembled in response to an inquiry from
U.S. Senator Padilla. See the letter dated December 3, 2021, from
Joseph Goffman, Principal Deputy Assistant Administrator to U.S.
Senator Alex Padilla, responding to letter dated October 19, 2021,
from U.S. Senator Alex Padilla to Michael Regan, Administrator, EPA.
---------------------------------------------------------------------------
The EPA issued the Draft Revised Contingency Measure Guidance on
March 17, 2023, and sought public comment on section 3 (``Showing that
the CMs Achieve Sufficient Reductions''), section 4 (``Reasoned
Justification for Less Than OYW of Progress''), and section 5
(``Guidance on Timing of Reductions from CMs'') of the draft guidance
over a 30-day period ending April 24, 2023.\100\ We applied the
underlying concepts of the draft guidance in our evaluation of the SJV
PM2.5 Contingency Measure SIP, described as much in our
proposed rule, and provided a 30-day comment period ending January 9,
2024, consistent with the public notice requirements of the CAA and the
Administrative Procedure Act.\101\
---------------------------------------------------------------------------
\100\ 88 FR 17571.
\101\ 88 FR 87988.
---------------------------------------------------------------------------
For this action, we evaluated the two individual District
contingency measures, the Residential Wood Burning Contingency Measure
and the Rural Open Areas Contingency Measure, to determine whether they
met the requirements for such measures under the CAA and the EPA's
regulations. We also considered the sum of the emission reductions from
the two individual District contingency measures plus CARB's Smog Check
Contingency Measure relative to the recommended amount we have
indicated contingency measures should achieve. Because the measures,
considered together, would not achieve the recommended amount of
emission reductions for NOX, CARB and the District submitted
infeasibility demonstrations documenting the unavailability of
additional feasible contingency measures for that PM2.5
precursor.
We reviewed and evaluated the infeasibility demonstrations and in
our proposed rule provided the rationale for our conclusion that the
individual District contingency measures met the applicable
requirements for such measures and that CARB and the District had
provided a reasoned justification, through the infeasibility
demonstrations, for not adopting contingency measures sufficient to
achieve the recommended amount of emission reductions for
NOX. In this action, we are finalizing our approval of the
SJV PM2.5 Contingency Measure SIP for the reasons given in
the proposed rule, as clarified and supplemented in responses to
comments. While the Valley EJ Organizations object to the consideration
of feasibility in connection with the contingency measure SIP
requirement, the commenters have raised no specific objection our
evaluation of the infeasibility demonstrations from CARB and the
District upon which our final approval rests.
In summary, in our proposed rule on the State's contingency measure
SIP submissions for the PM2.5 NAAQS in the San Joaquin
Valley, as well as our Draft Revised Contingency Measures Guidance, we
articulated a reasoned justification for the change in EPA policy on
the contingency measure requirements and respond in this document to
comments opposing those policy changes, and we explained how we were
reviewing the 2023 SIP Submissions in light of the new guidance. The
EPA believes that such actions satisfy the applicable requirements for
public process under the CAA and Administrative Procedure Act, as well
as our responsibilities to engage state and local air agencies on CAA
requirements and the development of SIP revisions in the wake of
applicable court decisions.
III. Environmental Justice Considerations
As described in detail in our proposal, the EPA reviewed
environmental and demographic data for the San Joaquin Valley using the
EPA's EJ screening and mapping tool (``EJSCREEN'') and compared the
data to the corresponding data for the United States as a whole, and to
California as a whole.\102\ The results of the analysis are provided
for
[[Page 80765]]
informational and transparency purposes.
---------------------------------------------------------------------------
\102\ EJSCREEN provides a nationally consistent dataset and
approach for combining environmental and demographic indicators.
EJSCREEN is available at https://www.epa.gov/ejscreen/what-ejscreen.
The EPA used EJSCREEN to obtain environmental and demographic
indicators representing each of the eight counties in the San
Joaquin Valley. These indicators are included in EJSCREEN reports
that are available in the rulemaking docket for this action. EPA
Region IX, ``EJSCREEN Analysis for the Eight Counties of the San
Joaquin Valley Nonattainment Area,'' August 2022.
---------------------------------------------------------------------------
This final action approves the State's contingency measure SIP
submissions for the 1997 annual, 2006 24-hour, and 2012 annual
PM2.5 NAAQS in the San Joaquin Valley. Information on these
PM2.5 NAAQS and their relationship to health impacts can be
found at 62 FR 38652 (July 18, 1997), 71 FR 61144 (October 17, 2006),
and 78 FR 3086 (January 15, 2013), respectively. We expect that this
action and resulting emission reductions will generally be neutral or
contribute to reduced environmental and health impacts on all
populations in the San Joaquin Valley, including communities with EJ
concerns. At a minimum, this action would not worsen existing air
quality and is expected to help ensure the area is meeting requirements
to attain and/or maintain air quality standards. Further, there is no
information in the record indicating that this action is expected to
have disproportionately high or adverse human health or environmental
effects on a particular group of people.
IV. EPA Action
For the reasons described in our proposed rule and in responses to
comments and under CAA section 110(k)(3), the EPA is taking final
action to approve SIP revisions submitted by CARB on June 8, 2023, and
October 16, 2023, for the San Joaquin Valley to address the contingency
measure SIP requirements for San Joaquin Valley for the 1997 annual,
2006 24-hour, and 2012 annual PM2.5 NAAQS.
The SIP submissions include the contingency measure plan element
for San Joaquin Valley for the relevant PM2.5 NAAQS
(referred to herein as the ``SJV PM2.5 Contingency Measure
SIP'') and two specific contingency measures, referred to herein as the
Residential Wood Burning Contingency Measure and the Rural Open Areas
Contingency Measure. We are approving the SJV PM2.5
Contingency Measure SIP as meeting the applicable requirements of CAA
section 172(c)(9) and 40 CFR 51.1014 for San Joaquin Valley for the
applicable PM2.5 NAAQS based on our approval of these two
contingency measures, the emission reductions from the two contingency
measures and the Smog Check Contingency Measure, and our review of the
State's infeasibility demonstrations provided in the SJV
PM2.5 Contingency Measure SIP.
The Residential Wood Burning Contingency Measure and the Rural Open
Areas Contingency Measure are included in amendments to SJVUAPCD Rule
4901 (``Wood Burning Fireplaces and Wood Burning Heaters'') and Rule
8051 (``Open Areas''), respectively. We are taking final action to
approve the two specific contingency measures because they meet the
requirements under CAA section 172(c)(9) and 40 CFR 51.1014 for such
measures.
As discussed in Section I.B of the proposed rule, on November 26,
2021, the EPA disapproved the contingency measure SIP elements
submitted for the 2006 24-hour and 2012 annual PM2.5 NAAQS
for San Joaquin Valley.\103\ These disapprovals were effective on
December 27, 2021. In a separate action published on November 26, 2021,
also effective December 27, 2021, the EPA disapproved the contingency
measure element for the 1997 annual PM2.5 NAAQS for San
Joaquin Valley.\104\
---------------------------------------------------------------------------
\103\ 86 FR 67343.
\104\ 86 FR 67329.
---------------------------------------------------------------------------
In our November 26, 2021 final disapprovals, we noted that offset
and highway sanctions under CAA sections 179(b)(2) and 179(b)(1),
respectively, would not apply if California submits, and the EPA
approves, a SIP submission or submissions that correct the deficiencies
identified in our final actions prior to the imposition of
sanctions.\105\ Through this final approval action, we find that
California has corrected the deficiencies associated with the
contingency measure elements for the 1997 annual, 2006 24-hour and 2012
annual PM2.5 NAAQS for San Joaquin Valley. Thus, upon the
effective date of this final rule, all sanctions and any sanctions
clocks associated with the disapprovals of the contingency measure
elements for the 1997 annual, 2006 24-hour and 2012 annual
PM2.5 NAAQS for San Joaquin Valley will be permanently
terminated.\106\
---------------------------------------------------------------------------
\105\ 86 FR 67329, 67341 and 86 FR 67343, 67346-67347. We note
that, concurrent with our proposed rules to approve the State's 2023
SIP submissions, the EPA issued an interim final determination that
stayed offset sanctions and deferred highway sanctions. 88 FR 87934
(December 20, 2023).
\106\ In addition, our CAA section 110(c) FIP obligations
arising from the disapprovals of the contingency measure elements
will be permanently terminated.
---------------------------------------------------------------------------
Lastly, based on this final action, we find that our FIP obligation
arising from our December 6, 2018 finding of failure to submit is
terminated, and thus, we will not be taking final action on our August
8, 2023 proposed PM2.5 contingency measure FIP for San
Joaquin Valley.\107\
---------------------------------------------------------------------------
\107\ See our December 20, 2023 proposed rule at 88 FR 87991 for
a discussion of the finding of failure to submit and related FIP
obligation.
---------------------------------------------------------------------------
V. Incorporation by Reference
In this rule, the EPA is finalizing regulatory text that includes
incorporation by reference. In accordance with requirements of 1 CFR
51.5, the EPA is finalizing the incorporation by reference of SJVUAPCD
Rule 4901 (``Wood Burning Fireplaces and Wood Burning Heaters''),
amended May 18, 2023, which regulates emissions from wood burning
fireplaces, wood burning heaters, and outdoor wood burning devices, and
Rule 8051 (``Open Areas''), amended September 21, 2023, which regulates
fugitive dust from open areas. The May 18, 2023 version of Rule 4901
and the September 21, 2023 version of Rule 8051 will replace the
previously approved versions of these rules, respectively, in the
California SIP. The EPA has made, and will continue to make, these
documents available through www.regulations.gov and at the EPA Region
IX Office (please contact the person identified in the FOR FURTHER
INFORMATION CONTACT section of this preamble for more information).
VI. Statutory and Executive Order Reviews
Under the Clean Air Act, the Administrator is required to approve a
SIP submission that complies with the provisions of the Clean Air Act
and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a).
Thus, in reviewing SIP submissions, the EPA's role is to approve state
choices, provided that they meet the criteria of the Clean Air Act.
Accordingly, this action merely approves a state plan and related
measures as meeting Federal requirements and does not impose additional
requirements beyond those imposed by state law. For that reason, this
action:
Is not a significant regulatory action subject to review
by the Office of Management and Budget under Executive Orders 12866 (58
FR 51735, October 4, 1993) and 14094 (88 FR 21879, April 11, 2023);
Does not impose an information collection burden under the
provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
Is certified as not having a significant economic impact
on a substantial number of small entities under the Regulatory
Flexibility Act (5 U.S.C. 601 et seq.);
Does not contain any unfunded mandate or significantly or
uniquely affect small governments, as described in the Unfunded
Mandates Reform Act of 1995 (Pub. L. 104-4);
Does not have federalism implications as specified in
Executive Order 13132 (64 FR 43255, August 10, 1999);
[[Page 80766]]
Is not subject to Executive Order 13045 (62 FR 19885,
April 23, 1997) because it approves a state program;
Is not a significant regulatory action subject to
Executive Order 13211 (66 FR 28355, May 22, 2001); and
Is not subject to requirements of Section 12(d) of the
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272
note) because application of those requirements would be inconsistent
with the Clean Air Act.
In addition, the SIP is not approved to apply on any Indian
reservation land or in any other area where the EPA or an Indian tribe
has demonstrated that a tribe has jurisdiction. In those areas of
Indian country, the final rule does not have tribal implications and
will not impose substantial direct costs on tribal governments or
preempt tribal law as specified by Executive Order 13175 (65 FR 67249,
November 9, 2000).
Executive Order 12898 (Federal Actions To Address Environmental
Justice in Minority Populations and Low-Income Populations, 59 FR 7629,
February 16, 1994) directs Federal agencies to identify and address
``disproportionately high and adverse human health or environmental
effects'' of their actions on communities with EJ concerns to the
greatest extent practicable and permitted by law. The EPA defines EJ as
``the fair treatment and meaningful involvement of all people
regardless of race, color, national origin, or income with respect to
the development, implementation, and enforcement of environmental laws,
regulations, and policies.'' The EPA further defines the term fair
treatment to mean that ``no group of people should bear a
disproportionate burden of environmental harms and risks, including
those resulting from the negative environmental consequences of
industrial, governmental, and commercial operations or programs and
policies.''
CARB and the District did not evaluate EJ considerations as part of
the SIP submissions addressed in this action; the CAA and applicable
implementing regulations neither prohibit nor require such an
evaluation. The EPA performed an EJ analysis, as described in section
III of this document and section VI of the EPA's proposed rule,
entitled ``Environmental Justice Considerations.'' The EPA conducted
this analysis for the purpose of providing additional context and
information about this rulemaking to the public, and the EPA does not
rely on this analysis as a basis for this final action. In addition,
the EPA has addressed comments on Executive Orders relating to EJ in
Response to Comment 9 of this document. Due to the nature of the action
being taken here, this action is expected to have a neutral to positive
impact on the air quality of the affected area. In addition, there is
no information in the record upon which this decision is based
inconsistent with the stated goal of E.O. 12898 of achieving EJ for
communities with EJ concerns.
This action is subject to the Congressional Review Act, and the EPA
will submit a rule report to each House of the Congress and to the
Comptroller General of the United States. This action is not a ``major
rule'' as defined by 5 U.S.C. 804(2).
Under section 307(b)(1) of the Clean Air Act, petitions for
judicial review of this action must be filed in the United States Court
of Appeals for the appropriate circuit by December 3, 2024. Filing a
petition for reconsideration by the Administrator of this final rule
does not affect the finality of this action for the purposes of
judicial review, nor does it extend the time within which a petition
for judicial review may be filed, and it shall not postpone the
effectiveness of such rule or action. This action may not be challenged
later in proceedings to enforce its requirements. (See section
307(b)(2).)
List of Subjects in 40 CFR Part 52
Environmental protection, Air pollution control, Ammonia,
Incorporation by reference, Intergovernmental relations, Nitrogen
oxides, Particulate matter, Reporting and recordkeeping requirements,
Sulfur oxides, Volatile organic compounds.
Dated: September 25, 2024.
Martha Guzman Aceves,
Regional Administrator, Region IX.
For the reasons discussed in the preamble, part 52, chapter I,
title 40 of the Code of Federal Regulations is amended as follows:
PART 52--APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS
0
1. The authority citation for Part 52 continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
Subpart F--California
0
2. Section 52.220 is amended by adding paragraphs (c)(334)(i)(B)(3),
(c)(535)(i)(A)(2), (c)(618) and (619) to read as follows:
Sec. 52.220 Identification of plan--in part.
* * * * *
(c) * * *
(334) * * *
(i) * * *
(B) * * *
(3) Previously approved on February 17, 2006, in paragraph
(c)(334)(i)(B)(2) of this section and now deleted with replacement in
paragraph (c)(619)(i)(A)(1) of this section: Rule 8051, ``Open Areas,''
amended on August 19, 2004.
* * * * *
(535) * * *
(i) * * *
(A) * * *
(2) Previously approved on July 22, 2020, in paragraph
(c)(535)(i)(A)(1) of this section and now deleted with replacement in
paragraph (c)(618)(i)(A)(1) of this section: Rule 4901, ``Wood Burning
Fireplaces and Wood Burning Heaters,'' amended on June 20, 2019.
* * * * *
(618) The following plan revisions were submitted electronically on
June 8, 2023, by the Governor's designee, as an attachment to a letter
dated June 7, 2023.
(i) Incorporation by reference. (A) San Joaquin Valley Unified Air
Pollution Control District.
(1) Rule 4901, ``Wood Burning Fireplaces and Wood Burning
Heaters,'' amended on May 18, 2023.
(2) [Reserved]
(B) [Reserved]
(ii) Additional materials. (A) San Joaquin Valley Unified Air
Pollution Control District.
(1) ``PM2.5 Contingency Measure State Implementation
Plan Revision (May 18, 2023),'' adopted on May 18, 2023, excluding Rule
4901, ``Wood Burning Fireplaces and Wood Burning Heaters.''
(2) [Reserved]
(B) [Reserved]
(619) The following plan revision was submitted electronically on
October 16, 2023, by the Governor's designee, as an attachment to a
letter dated October 13, 2023.
(i) Incorporation by reference. (A) San Joaquin Valley Unified Air
Pollution Control District.
(1) Rule 8051, ``Open Areas,'' amended on September 21, 2023.
(2) [Reserved]
(B) [Reserved]
(ii) [Reserved]
* * * * *
Sec. 52.237 [Amended]
0
3. Section 52.237 is amended by removing and reserving paragraphs
(a)(9), (10) and (11).
[FR Doc. 2024-22681 Filed 10-3-24; 8:45 am]