Ashuelot River Hydro, Inc.; Notice of Reasonable Period of Time for Water Quality Certification Application, 77128 [2024-21595]
Download as PDF
77128
Federal Register / Vol. 89, No. 183 / Friday, September 20, 2024 / Notices
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP16–116–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field, excluding the last three digits (i.e.,
CP16–116). Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: September 13, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–21474 Filed 9–19–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
[Project No. P–7887–019]
Ashuelot River Hydro, Inc.; Notice of
Reasonable Period of Time for Water
Quality Certification Application
On August 27, 2024, the New
Hampshire Department of
Environmental Services (New
Hampshire DES) submitted to the
Federal Energy Regulatory Commission
VerDate Sep<11>2014
16:44 Sep 19, 2024
Jkt 262001
(Commission) notice that it received a
request for a Clean Water Act section
401(a)(1) water quality certification as
defined in 40 CFR 121.5, from Ashuelot
River Hydro, Inc., in conjunction with
the above captioned project on July 8,
2024. Pursuant to section 4.34(b) of the
Commission’s regulations,1 we hereby
notify New Hampshire DES of the
following:
Date of Receipt of the Certification
Request: July 8, 2024.
Reasonable Period of Time to Act on
the Certification Request: One year, July
8, 2025.
If New Hampshire DES fails or refuses
to act on the water quality certification
request on or before the above date, then
the certifying authority is deemed
waived pursuant to section 401(a)(1) of
the Clean Water Act, 33 U.S.C.
1341(a)(1).
Dated: September 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–21595 Filed 9–19–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2232–893]
Duke Energy Carolinas, LLC; Notice of
Application for Non-Project Use of
Project Land and Waters Accepted for
Filing, Soliciting Comments, Motions
To Intervene, and Protests
September 16, 2024.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Project Use
of Project Lands and Waters.
b. Project No: 2232–893.
c. Date Filed: July 31, 2024.
d. Applicant: Duke Energy Carolinas,
LLC.
e. Name of Project: Catawba-Wateree
Hydroelectric Project.
f. Location: Bridgewater Development
(Lake James) in McDowell County,
North Carolina.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Dennis
Whitaker, 704–382–1594,
dennis.whitaker@duke-energy.com.
i. FERC Contact: Shana High, 202–
502–8674, shana.high@ferc.gov.
j. Cooperating agencies: With this
notice, the Commission is inviting
1
PO 00000
18 CFR [4.34(b)(5)].
Frm 00054
Fmt 4703
Sfmt 4703
Federal, State, local, and Tribal agencies
with jurisdiction and/or special
expertise with respect to environmental
issues affected by the proposal, that
wish to cooperate in the preparation of
any environmental document, if
applicable, to follow the instructions for
filing such requests described in item k
below. Cooperating agencies should
note the Commission’s policy that
agencies that cooperate in the
preparation of any environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Deadline for filing comments,
motions to intervene, and protests:
October 16, 2024.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The first page of any filing should
include the docket number P–2232–893.
Comments emailed to Commission staff
are not considered part of the
Commission record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
l. Description of Request: The
licensee’s application requests
Commission authorization to permit
The Reserve at Barefoot Landing on
Lake James, LLC (The Reserve) to
construct a residential marina. Within
the project boundary, The Reserve’s
marina would consist of seven floating
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 89, Number 183 (Friday, September 20, 2024)]
[Notices]
[Page 77128]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-21595]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-7887-019]
Ashuelot River Hydro, Inc.; Notice of Reasonable Period of Time
for Water Quality Certification Application
On August 27, 2024, the New Hampshire Department of Environmental
Services (New Hampshire DES) submitted to the Federal Energy Regulatory
Commission (Commission) notice that it received a request for a Clean
Water Act section 401(a)(1) water quality certification as defined in
40 CFR 121.5, from Ashuelot River Hydro, Inc., in conjunction with the
above captioned project on July 8, 2024. Pursuant to section 4.34(b) of
the Commission's regulations,\1\ we hereby notify New Hampshire DES of
the following:
---------------------------------------------------------------------------
\1\ 18 CFR [4.34(b)(5)].
---------------------------------------------------------------------------
Date of Receipt of the Certification Request: July 8, 2024.
Reasonable Period of Time to Act on the Certification Request: One
year, July 8, 2025.
If New Hampshire DES fails or refuses to act on the water quality
certification request on or before the above date, then the certifying
authority is deemed waived pursuant to section 401(a)(1) of the Clean
Water Act, 33 U.S.C. 1341(a)(1).
Dated: September 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-21595 Filed 9-19-24; 8:45 am]