Notice of Complaint; Murphy Oil USA, Inc. v. Colonial Pipeline Company, 77125-77126 [2024-21593]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 89, No. 183 / Friday, September 20, 2024 / Notices
generator, for a total installed capacity
of 7.75 MW; (c) an overflow section
with: (i) a 42-foot-long and 50.5-footlong spillway, each with a 3-foot-high
inflatable rubber crest gate with a
maximum crest elevation of 430.62 feet
North American Vertical Datum of 1988
(NAVD 88); and (ii) a 97.4-foot-long and
61-foot-long spillway, each with 3-foothigh flashboards that have a crest
elevation of 430.62 feet NAVD 88; and
(d) a 24.7-foot-long north non-overflow
section with a 3-foot-long sluice gate.
The dam creates an impoundment that
has a surface area of 20 acres at 430.62
feet NAVD 88. The south shoreline of
the impoundment also includes a 450foot-long retaining/flood wall between
the South Channel Dam and Beebee
Island Dam.
From the impoundment, water flows
through the powerhouse to a 15-footlong tailrace. The South Channel Dam
creates an approximately 1,000-footlong bypassed reach of the Black River.
Minimum flows are provided to the
bypassed reach through a gated, 2-footdiameter pipe in the South Channel
Dam.
The project includes a downstream
fish passage facility that consists of: (1)
the sluice gate adjacent to the intake
structure; and (2) an 8-foot-wide
sluiceway that discharges immediately
downstream of the powerhouse. The
current license requires the licensee to
provide a boat take-out site upstream of
the dam and directional signage to
downstream boat put-in locations.
The generators are connected to the
regional electric grid by a 300-foot-long,
4.8-kilovolt underground generator lead
line. The minimum and maximum
hydraulic capacities of the powerhouse
are 200 and 3,600 cubic feet per second
(cfs), respectively. The average annual
energy production of the project from
2010 through 2020, was 43,768
megawatt-hours.
Article 401 of the current license
requires Erie to operate the project in a
run-of-river mode, such that project
outflow approximates inflow to the
impoundment at any point in time and
the surface elevation of the
impoundment is maintained at no lower
than 0.5 foot below either (1) the
spillway crest elevation or (2) the crest
of the flashboards when in place. Article
404 requires a minimum flow of 14 cfs
to the bypassed reach and Article 403
requires a minimum flow of 1,000 cfs or
inflow, whichever is less, downstream
of the project.
Article 402 requires Erie to install
flashboards by May 1, or as soon
thereafter as safely possible, and to
remove the flashboards in the fall prior
to ice conditions. Article 410 requires
VerDate Sep<11>2014
16:44 Sep 19, 2024
Jkt 262001
Erie to install trashrack overlays with 1inch clear bar spacing at the top half
portion of the trashracks from May 1
through October 1. Additionally, Article
411 requires Erie to release 37 cfs
through the downstream fish passage
facility from April 1 through November
30. The current license also requires the
implementation of a Flow Monitoring
Plan to ensure compliance with the
project flow requirements and a Record
Keeping Plan to maintain records of the
impoundment elevations and discharges
from the project, in compliance with
Articles 408 and 409.
Article 414 requires 0.5-inch veiling
flows over the 97.4-foot-long spillway
from May 1 to October 31. Article 416
requires the implementation of a
Cultural Resources Management Plan to
protect historic properties.
Erie proposes to continue operating
the project as required under the current
license. In addition, Erie proposes to
develop a new minimum flow and fish
conveyance plan, streamflow and
headpond monitoring plan, recreation
plan, and historic properties
management plan.
k. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–2538).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
You may also register online at
https://ferconline.ferc.gov/FERC
Online.aspx to be notified via email of
new filings and issuances related to this
or other pending projects. For
assistance, contact FERC Online
Support.
l. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
77125
m. Procedural Schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Deficiency Letter and Additional
Information Request—September
2024
Notice of Acceptance—February 2025
n. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 13, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–21483 Filed 9–19–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. OR24–10–000]
Notice of Complaint; Murphy Oil USA,
Inc. v. Colonial Pipeline Company
Take notice that on September 12,
2024, pursuant to Rule 206 of the Rules
of Practice and Procedure of the Federal
Energy Regulatory Commission, 18 CFR
385.206 (2024), Murphy Oil USA, Inc.
(‘‘Murphy’’) filed a complaint against
Colonial Pipeline Company (‘‘Colonial’’)
challenging the justness and
reasonableness of the rates charged by
Colonial for transportation service
pursuant to certain tariffs on file with
the Commission.
The Complainant certifies that copies
of the complaint were served on the
contacts listed for Respondents in the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
E:\FR\FM\20SEN1.SGM
20SEN1
77126
Federal Register / Vol. 89, No. 183 / Friday, September 20, 2024 / Notices
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
To access this document in eLibrary,
type the docket number excluding the
last three digits of this document in the
docket number field. User assistance is
available for eLibrary and the
Commission’s website during normal
business hours from FERC Online
Support at 202–502–6652 (toll free at 1–
866–208–3676) or email at
ferconlinesupport@ferc.gov, or the
Public Reference Room at (202) 502–
8371, TTY (202) 502–8659. Email the
Public Reference Room at
public.referenceroom@ferc.gov.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on October 12, 2024.
Dated: September 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–21593 Filed 9–19–24; 8:45 am]
ddrumheller on DSK120RN23PROD with NOTICES1
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–116–000]
Notice of Intent To Prepare a
Supplemental Environmental Impact
Statement for the Proposed Texas LNG
Brownsville LLC Texas LNG Project,
Request for Comments on
Environmental Issues, and Schedule
for Environmental Review
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare a
supplemental environmental impact
statement (supplemental EIS) for the
Texas LNG Project, proposed by Texas
LNG Brownsville LLC (Texas LNG) in
Cameron County, Texas.1 On August 6,
2024, the U.S. Court of Appeals for the
District of Columbia Circuit issued an
opinion vacating and remanding the
Commission’s November 22, 2019 Order
Granting Authorization under Section 3
of the Natural Gas Act and its April 21,
2023 Order on Remand that approved
the liquefied natural gas (LNG)
terminal.2 On remand, the Commission
will consider whether to grant a Natural
Gas Act (NGA) section 3(a)
authorization for the Texas LNG Project.
The schedule for preparation of the
supplemental EIS is discussed in the
Schedule for Environmental Review
section of this notice.
The Commission must determine
whether to authorize the project under
the NGA, taking into consideration the
factors discussed in the court’s decision.
The supplemental EIS will tier off
Commission staff’s analysis and
conclusions as documented in staff’s
March 15, 2019 final EIS for the project.
The focus of the supplemental EIS will
be the issues identified by the court as
requiring further analyses (i.e.,
environmental justice impacts and air
quality). The Commission will use this
supplemental EIS in its decision-making
process to determine whether to
authorize the Texas LNG Project in light
of the court’s vacatur and remand.
As part of the National Environmental
Policy Act (NEPA) review process, the
Commission takes into account
concerns the public may have about
proposals and the environmental
impacts that could result from its action
whenever it considers the issuance of an
1 In accordance with the Council on
Environmental Quality’s regulations, the unique
identification number for documents relating to this
environmental review is SEIS–019–20–000–
1726224938. 40 CFR 1502.4(e)(10) (2024).
2 City of Port Isabel v. FERC, 111 F.4th 1198 (D.C.
Cir. 2024).
VerDate Sep<11>2014
16:44 Sep 19, 2024
Jkt 262001
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
authorization. This notice announces
the opening of the scoping process the
Commission will use to gather input
from the public and interested agencies
regarding the issues that will be
analyzed in the supplemental EIS.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and the Supplemental EIS section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the supplemental
EIS. To ensure that your comments are
timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00 p.m.
Eastern Time on October 15, 2024.
Comments may be submitted in written
form. Further details on how to submit
comments are provided in the Public
Participation section of this notice.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. The Commission
encourages electronic filing of
comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is also located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP16–116–00)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 89, Number 183 (Friday, September 20, 2024)]
[Notices]
[Pages 77125-77126]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-21593]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. OR24-10-000]
Notice of Complaint; Murphy Oil USA, Inc. v. Colonial Pipeline
Company
Take notice that on September 12, 2024, pursuant to Rule 206 of the
Rules of Practice and Procedure of the Federal Energy Regulatory
Commission, 18 CFR 385.206 (2024), Murphy Oil USA, Inc. (``Murphy'')
filed a complaint against Colonial Pipeline Company (``Colonial'')
challenging the justness and reasonableness of the rates charged by
Colonial for transportation service pursuant to certain tariffs on file
with the Commission.
The Complainant certifies that copies of the complaint were served
on the contacts listed for Respondents in the Commission's list of
Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to
[[Page 77126]]
view and/or print the contents of this document via the internet
through the Commission's Home Page (https://www.ferc.gov) using the
``eLibrary'' link. To access this document in eLibrary, type the docket
number excluding the last three digits of this document in the docket
number field. User assistance is available for eLibrary and the
Commission's website during normal business hours from FERC Online
Support at 202-502-6652 (toll free at 1-866-208-3676) or email at
[email protected], or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
[email protected].
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically may mail
similar pleadings to the Federal Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426. Hand delivered submissions in
docketed proceedings should be delivered to Health and Human Services,
12225 Wilkins Avenue, Rockville, Maryland 20852.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Comment Date: 5:00 p.m. Eastern Time on October 12, 2024.
Dated: September 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-21593 Filed 9-19-24; 8:45 am]
BILLING CODE 6717-01-P