Federal Register / Vol. 89, No. 183 / Friday, September 20, 2024 / Notices
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, 385.211,
385.214, respectively. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
p. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
q. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
VerDate Sep<11>2014
16:44 Sep 19, 2024
Jkt 262001
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: September 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–21594 Filed 9–19–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Southwestern Power Administration
Integrated System Rate Schedules
Southwestern Power
Administration, DOE.
ACTION: Notice of rate order.
AGENCY:
The Administrator of the
Southwestern Power Administration
(Southwestern) has approved and
implemented Rate Order No. SWPA–85,
which grants a temporary extension of
Southwestern’s current Integrated
System rate schedules (P–13B, NFTS–
13A, and EE–13) through September 30,
2025, unless superseded.
DATES: Extension of the rate schedules
is effective October 1, 2024.
FOR FURTHER INFORMATION CONTACT: Ms.
Fritha Ohlson, Senior Vice President
and Chief Operating Officer, Office of
Corporate Operations, (918) 595–6684,
fritha.ohlson@swpa.gov.
SUPPLEMENTARY INFORMATION: Rate Order
No. SWPA–85, as provided herein, has
been approved and implemented by the
Administrator of Southwestern. It
extends the Integrated System Rate
Schedule P–13B, Wholesale Rates for
Hydro Peaking Power; Rate Schedule
NFTS–13A, Wholesale Rates for NonFederal Transmission/Interconnection
Facilities Service; and Rate Schedule
EE–13, Wholesale Rates for Excess
Energy, until September 30, 2025,
unless otherwise replaced.
SUMMARY:
UNITED STATES OF AMERICA
DEPARTMENT OF ENERGY
ADMINISTRATOR, SOUTHWESTERN
POWER ADMINISTRATION
In the matter of: Southwestern Power
Administration, Integrated System Rate
Schedules
Rate Order No. SWPA–85
Order Approving Extension of Rate
Schedules on a Temporary Basis (9/13/
2024)
Pursuant to Sections 301(b) and
302(a) of the Department of Energy
Organization Act, 42 U.S.C. 7151(b) and
7152(a), the functions of the Secretary of
the Interior and the Federal Power
Commission under Section 5 of the
Flood Control Act of 1944, 16 U.S.C.
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
77143
825s, relating to the Southwestern
Power Administration (Southwestern),
were transferred to and vested in the
Secretary of Energy. By Delegation
Order No. S1–DEL–RATES–2016,
effective November 19, 2016, the
Secretary of Energy delegated: (1) the
authority to develop power and
transmission rates to Southwestern’s
Administrator; (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy; and (3) the
authority to confirm, approve, and place
into effect on a final basis, or to remand
or disapprove such rates, to the Federal
Energy Regulatory Commission (FERC).
By Delegation Order No. S1–DEL–S3–
2024, effective August 30, 2024, the
Secretary of Energy also delegated the
authority to confirm, approve, and place
such rates into effect on an interim basis
to the Under Secretary for
Infrastructure. By Redelegation Order
No. S3–DEL–SWPA1–2023, effective
April 10, 2023, the Under Secretary for
Infrastructure redelegated the authority
to confirm, approve, and place such
rates into effect on an interim basis to
the Southwestern Administrator.
Background
On September 30, 2013, in Rate Order
No. SWPA–66, the Deputy Secretary of
Energy placed into effect
Southwestern’s Integrated System rate
schedules (P–13, NFTS–13, and EE–13)
on an interim basis for the period
October 1, 2013 to September 30, 2017.
FERC confirmed and approved
Southwestern’s interim Integrated
System rates on a final basis on January
9, 2014 for a period ending September
30, 2017.
Southwestern re-designated Integrated
System rate schedule ‘‘NFTS–13’’ as
‘‘NFTS–13A’’ with no revenue
adjustment. In Rate Order No. SWPA–
71, the Deputy Secretary of Energy
placed into effect Southwestern’s rate
schedule NFTS–13A on an interim basis
beginning January 1, 2017. FERC
confirmed and approved NFTS–13A on
a final basis on March 9, 2017.
On September 13, 2017, in Rate Order
No. SWPA–72, the Deputy Secretary of
Energy extended all of Southwestern’s
Integrated System rate schedules (P–13,
NTFS–13A, and EE–13) for two years,
for the period of October 1, 2017
through September 30, 2019.
Southwestern re-designated Integrated
System rate schedule ‘‘P–13’’ as ‘‘P–
13A’’ with no revenue adjustment to
incorporate a new section regarding
requirements for the peaking energy
schedule submission time. In Rate Order
No. SWPA–73, the Assistant Secretary
for Electricity placed into effect
E:\FR\FM\20SEN1.SGM
20SEN1
77144
Federal Register / Vol. 89, No. 183 / Friday, September 20, 2024 / Notices
ddrumheller on DSK120RN23PROD with NOTICES1
Southwestern’s rate schedule for P–13A
on an interim basis beginning July 1,
2019. FERC confirmed and approved P–
13A on a final basis on August 29, 2019.
On September 22, 2019, in Rate Order
No. SWPA–74, the Assistant Secretary
for Electricity extended all of
Southwestern’s Integrated System rate
schedules (P–13A, NFTS–13A, and EE–
13) for two years, for the period of
October 1, 2019 through September 30,
2021.
On August 30, 2021, in Rate Order
No. SWPA–77, the Administrator,
Southwestern, extended all of
Southwestern’s Integrated System rate
schedules (P–13A, NFTS–13A, and EE–
13) for two years, for the period of
October 1, 2021 through September 30,
2023.
Southwestern re-designated Integrated
System rate schedule ‘‘P–13A’’ as ‘‘P–
13B’’ with no revenue adjustment to
update the peaking energy schedule
submission time requirements. In Rate
Order No. SWPA–80, the Administrator,
Southwestern, placed into effect
Southwestern’s rate schedule for P–13B
on an interim basis beginning July 15,
2023. The P–13B rate schedule has been
submitted to FERC for confirmation and
approval on a final basis.
On September 25, 2023, in Rate Order
No. SWPA–81, the Administrator,
Southwestern, temporarily extended all
of Southwestern’s Integrated System
rate schedules (P–13B, NFTS–13A, and
EE–13) for one year, for the period of
October 1, 2023 through September 30,
2024.
Discussion
Southwestern’s current Integrated
System rate schedules (P–13B, NFTS–
13A, and EE–13) are based on its 2013
Power Repayment Study (PRS).
Southwestern has conducted PRSs
annually thereafter through 2023. Each
PRS from 2014 through 2022 indicated
a need for a revenue adjustment within
a plus or minus two percent range of the
revenue estimate based on the current
rate schedules. It is Southwestern’s
practice for the Administrator to defer,
on a case-by-case basis, revenue
adjustments for the Integrated System
within plus or minus two percent from
the revenue estimate based on the
current rate schedules. Thus, the
Administrator has deferred revenue
adjustments annually through 2022. The
2023 PRS indicated a need for a revenue
adjustment above two percent and
therefore Southwestern is working
towards implementation of a rate
adjustment plan including design of a
new set of Integrated System rate
schedules (P–23, NFTS–23, and EE–23).
However, that effort and the associated
VerDate Sep<11>2014
16:44 Sep 19, 2024
Jkt 262001
procedures for public participation in
accordance with 10 CFR part 903 will
not be completed in time for the new
rate schedules to be placed into effect
prior to the September 30, 2024,
expiration of the current rate schedules,
and thus temporary extension of the
current rate schedules is necessary.
Pursuant to 10 CFR 903.23(b) and
Redelegation Order No. S3–DEL–
SWPA1–2023, Southwestern’s
Administrator may extend existing rates
on a temporary basis without advance
notice or comment pending further
action. In such a circumstance, the
Administrator shall publish notice of
said extension in the Federal Register
and promptly advise FERC of the
extension. The revenue collection
associated with the extension of the
current rates will be considered in the
development of the new rates based on
the 2023 PRS such that repayment
obligations are met consistent with the
provisions of U.S. Department of Energy
(DOE) Order No. RA 6120.2.
Availability of Information
Information regarding the extension of
these rate schedules is available for
public review in the offices of
Southwestern Power Administration,
One West Third Street Suite 1500,
Tulsa, Oklahoma 74103. The rate
schedules are available on the
Southwestern website at
www.energy.gov/swpa/rates-andrepayment.
Order
In view of the foregoing and pursuant
to the authority delegated to me by the
Secretary of Energy, I hereby extend,
effective October 1, 2024, the Integrated
System Rate Schedule P–13B, Wholesale
Rates for Hydro Peaking Power; Rate
Schedule NFTS–13A, Wholesale Rates
for Non-Federal Transmission/
Interconnection Facilities Service; and
Rate Schedule EE–13, Wholesale Rates
for Excess Energy. The rate schedules
shall remain in effect on a temporary
basis through September 30, 2025,
unless superseded.
Signing Authority
This document of the Department of
Energy was signed on September 13,
2024, by Michael S. Wech,
Administrator for Southwestern Power
Administration, pursuant to delegated
authority from the Secretary of Energy.
That document, with the original
signature and date, is maintained by
DOE. For administrative purposes only,
and in compliance with requirements of
the Office of the Federal Register, the
undersigned DOE Federal Register
Liaison Officer has been authorized to
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
sign and submit the document in
electronic format for publication, as an
official document of DOE. This
administrative process in no way alters
the legal effect of this document upon
publication in the Federal Register.
Signed in Washington, DC, on September
17, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
[FR Doc. 2024–21529 Filed 9–19–24; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Southwestern Power Administration
Robert D. Willis Hydropower Project
Rate Schedule
Southwestern Power
Administration, DOE.
ACTION: Notice of rate order.
AGENCY:
The Administrator,
Southwestern Power Administration
(Southwestern), has approved and
placed into effect Rate Order No.
SWPA–86, which provides a temporary
extension of Southwestern’s current
Robert D. Willis Hydropower Project
rate schedule (RDW–15) through
September 30, 2025, unless superseded.
DATES: Extension of the rate schedule is
effective October 1, 2024.
FOR FURTHER INFORMATION CONTACT: Ms.
Fritha Ohlson, Senior Vice President,
Chief Operating Officer, Office of
Corporate Operations, (918) 595–6684,
fritha.ohlson@swpa.gov.
SUPPLEMENTARY INFORMATION: Rate Order
No. SWPA–86, as provided herein, has
been approved and implemented by the
Administrator of Southwestern. It
extends the Robert D. Willis
Hydropower Project Rate Schedule
RDW–15, Wholesale Rates for Hydro
Power and Energy, until September 30,
2025, unless otherwise replaced.
SUMMARY:
UNITED STATES OF AMERICA
DEPARTMENT OF ENERGY
ADMINISTRATOR, SOUTHWESTERN
POWER ADMINISTRATION
In the matter of: Southwestern Power
Administration, Robert D. Willis
Hydropower Project Rate Schedule
Rate Order No. SWPA–86
Order Approving Extension of Rate
Schedule on a Temporary Basis (9/13/
2024)
Pursuant to Sections 301(b) and
302(a) of the Department of Energy
Organization Act, 42 U.S.C. 7151(b) and
7152(a), the functions of the Secretary of
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 89, Number 183 (Friday, September 20, 2024)]
[Notices]
[Pages 77143-77144]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-21529]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Southwestern Power Administration
Integrated System Rate Schedules
AGENCY: Southwestern Power Administration, DOE.
ACTION: Notice of rate order.
-----------------------------------------------------------------------
SUMMARY: The Administrator of the Southwestern Power Administration
(Southwestern) has approved and implemented Rate Order No. SWPA-85,
which grants a temporary extension of Southwestern's current Integrated
System rate schedules (P-13B, NFTS-13A, and EE-13) through September
30, 2025, unless superseded.
DATES: Extension of the rate schedules is effective October 1, 2024.
FOR FURTHER INFORMATION CONTACT: Ms. Fritha Ohlson, Senior Vice
President and Chief Operating Officer, Office of Corporate Operations,
(918) 595-6684, [email protected].
SUPPLEMENTARY INFORMATION: Rate Order No. SWPA-85, as provided herein,
has been approved and implemented by the Administrator of Southwestern.
It extends the Integrated System Rate Schedule P-13B, Wholesale Rates
for Hydro Peaking Power; Rate Schedule NFTS-13A, Wholesale Rates for
Non-Federal Transmission/Interconnection Facilities Service; and Rate
Schedule EE-13, Wholesale Rates for Excess Energy, until September 30,
2025, unless otherwise replaced.
UNITED STATES OF AMERICA
DEPARTMENT OF ENERGY
ADMINISTRATOR, SOUTHWESTERN POWER ADMINISTRATION
In the matter of: Southwestern Power Administration, Integrated
System Rate Schedules
Rate Order No. SWPA-85
Order Approving Extension of Rate Schedules on a Temporary Basis (9/13/
2024)
Pursuant to Sections 301(b) and 302(a) of the Department of Energy
Organization Act, 42 U.S.C. 7151(b) and 7152(a), the functions of the
Secretary of the Interior and the Federal Power Commission under
Section 5 of the Flood Control Act of 1944, 16 U.S.C. 825s, relating to
the Southwestern Power Administration (Southwestern), were transferred
to and vested in the Secretary of Energy. By Delegation Order No. S1-
DEL-RATES-2016, effective November 19, 2016, the Secretary of Energy
delegated: (1) the authority to develop power and transmission rates to
Southwestern's Administrator; (2) the authority to confirm, approve,
and place such rates into effect on an interim basis to the Deputy
Secretary of Energy; and (3) the authority to confirm, approve, and
place into effect on a final basis, or to remand or disapprove such
rates, to the Federal Energy Regulatory Commission (FERC). By
Delegation Order No. S1-DEL-S3-2024, effective August 30, 2024, the
Secretary of Energy also delegated the authority to confirm, approve,
and place such rates into effect on an interim basis to the Under
Secretary for Infrastructure. By Redelegation Order No. S3-DEL-SWPA1-
2023, effective April 10, 2023, the Under Secretary for Infrastructure
redelegated the authority to confirm, approve, and place such rates
into effect on an interim basis to the Southwestern Administrator.
Background
On September 30, 2013, in Rate Order No. SWPA-66, the Deputy
Secretary of Energy placed into effect Southwestern's Integrated System
rate schedules (P-13, NFTS-13, and EE-13) on an interim basis for the
period October 1, 2013 to September 30, 2017. FERC confirmed and
approved Southwestern's interim Integrated System rates on a final
basis on January 9, 2014 for a period ending September 30, 2017.
Southwestern re-designated Integrated System rate schedule ``NFTS-
13'' as ``NFTS-13A'' with no revenue adjustment. In Rate Order No.
SWPA-71, the Deputy Secretary of Energy placed into effect
Southwestern's rate schedule NFTS-13A on an interim basis beginning
January 1, 2017. FERC confirmed and approved NFTS-13A on a final basis
on March 9, 2017.
On September 13, 2017, in Rate Order No. SWPA-72, the Deputy
Secretary of Energy extended all of Southwestern's Integrated System
rate schedules (P-13, NTFS-13A, and EE-13) for two years, for the
period of October 1, 2017 through September 30, 2019.
Southwestern re-designated Integrated System rate schedule ``P-13''
as ``P-13A'' with no revenue adjustment to incorporate a new section
regarding requirements for the peaking energy schedule submission time.
In Rate Order No. SWPA-73, the Assistant Secretary for Electricity
placed into effect
[[Page 77144]]
Southwestern's rate schedule for P-13A on an interim basis beginning
July 1, 2019. FERC confirmed and approved P-13A on a final basis on
August 29, 2019.
On September 22, 2019, in Rate Order No. SWPA-74, the Assistant
Secretary for Electricity extended all of Southwestern's Integrated
System rate schedules (P-13A, NFTS-13A, and EE-13) for two years, for
the period of October 1, 2019 through September 30, 2021.
On August 30, 2021, in Rate Order No. SWPA-77, the Administrator,
Southwestern, extended all of Southwestern's Integrated System rate
schedules (P-13A, NFTS-13A, and EE-13) for two years, for the period of
October 1, 2021 through September 30, 2023.
Southwestern re-designated Integrated System rate schedule ``P-
13A'' as ``P-13B'' with no revenue adjustment to update the peaking
energy schedule submission time requirements. In Rate Order No. SWPA-
80, the Administrator, Southwestern, placed into effect Southwestern's
rate schedule for P-13B on an interim basis beginning July 15, 2023.
The P-13B rate schedule has been submitted to FERC for confirmation and
approval on a final basis.
On September 25, 2023, in Rate Order No. SWPA-81, the
Administrator, Southwestern, temporarily extended all of Southwestern's
Integrated System rate schedules (P-13B, NFTS-13A, and EE-13) for one
year, for the period of October 1, 2023 through September 30, 2024.
Discussion
Southwestern's current Integrated System rate schedules (P-13B,
NFTS-13A, and EE-13) are based on its 2013 Power Repayment Study (PRS).
Southwestern has conducted PRSs annually thereafter through 2023. Each
PRS from 2014 through 2022 indicated a need for a revenue adjustment
within a plus or minus two percent range of the revenue estimate based
on the current rate schedules. It is Southwestern's practice for the
Administrator to defer, on a case-by-case basis, revenue adjustments
for the Integrated System within plus or minus two percent from the
revenue estimate based on the current rate schedules. Thus, the
Administrator has deferred revenue adjustments annually through 2022.
The 2023 PRS indicated a need for a revenue adjustment above two
percent and therefore Southwestern is working towards implementation of
a rate adjustment plan including design of a new set of Integrated
System rate schedules (P-23, NFTS-23, and EE-23). However, that effort
and the associated procedures for public participation in accordance
with 10 CFR part 903 will not be completed in time for the new rate
schedules to be placed into effect prior to the September 30, 2024,
expiration of the current rate schedules, and thus temporary extension
of the current rate schedules is necessary. Pursuant to 10 CFR
903.23(b) and Redelegation Order No. S3-DEL-SWPA1-2023, Southwestern's
Administrator may extend existing rates on a temporary basis without
advance notice or comment pending further action. In such a
circumstance, the Administrator shall publish notice of said extension
in the Federal Register and promptly advise FERC of the extension. The
revenue collection associated with the extension of the current rates
will be considered in the development of the new rates based on the
2023 PRS such that repayment obligations are met consistent with the
provisions of U.S. Department of Energy (DOE) Order No. RA 6120.2.
Availability of Information
Information regarding the extension of these rate schedules is
available for public review in the offices of Southwestern Power
Administration, One West Third Street Suite 1500, Tulsa, Oklahoma
74103. The rate schedules are available on the Southwestern website at
www.energy.gov/swpa/rates-and-repayment.
Order
In view of the foregoing and pursuant to the authority delegated to
me by the Secretary of Energy, I hereby extend, effective October 1,
2024, the Integrated System Rate Schedule P-13B, Wholesale Rates for
Hydro Peaking Power; Rate Schedule NFTS-13A, Wholesale Rates for Non-
Federal Transmission/Interconnection Facilities Service; and Rate
Schedule EE-13, Wholesale Rates for Excess Energy. The rate schedules
shall remain in effect on a temporary basis through September 30, 2025,
unless superseded.
Signing Authority
This document of the Department of Energy was signed on September
13, 2024, by Michael S. Wech, Administrator for Southwestern Power
Administration, pursuant to delegated authority from the Secretary of
Energy. That document, with the original signature and date, is
maintained by DOE. For administrative purposes only, and in compliance
with requirements of the Office of the Federal Register, the
undersigned DOE Federal Register Liaison Officer has been authorized to
sign and submit the document in electronic format for publication, as
an official document of DOE. This administrative process in no way
alters the legal effect of this document upon publication in the
Federal Register.
Signed in Washington, DC, on September 17, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2024-21529 Filed 9-19-24; 8:45 am]
BILLING CODE 6450-01-P