Download as PDF 76824 Federal Register / Vol. 89, No. 182 / Thursday, September 19, 2024 / Notices information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate. Milestone Target date Commission issues EA ... Comments on EA ............ December 2024.1 January 2024. 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) (2023) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq., as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility Act of 2023, Pub. L. 118–5, 4336a, 137 Stat. 42. Any questions regarding this notice may be directed to Golbahar Mirhosseini at golbahar.mirhosseini@ ferc.gov. Dated: September 12, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–21294 Filed 9–18–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD24–9–000] lotter on DSK11XQN23PROD with NOTICES1 Innovations and Efficiencies in Generator Interconnection; Notice Requesting Post-Workshop Comment On September 10 and 11, 2024, Federal Energy Regulatory Commission (Commission) convened a staff-led workshop to discuss innovations and efficiencies in generator interconnection processes. All interested persons are invited to file post-workshop comments on issues raised during the workshop that they believe would benefit from further discussion. Parties are also invited to provide comments on the questions presented in the workshop agenda.1 Commenters need not respond to all topics or questions asked. Commenters may reference material previously filed in this docket but are encouraged to avoid repetition or 1 See Second Supplemental Notice of Staff-Led Workshop, Docket No. AD24–9–000 (Aug. 14, 2024). VerDate Sep<11>2014 16:59 Sep 18, 2024 Jkt 262001 replication of previous material. To facilitate the processing of comments, we urge commenters to organize their comments by panel topic and question presented at the workshop and to be brief. In addition, commenters are encouraged, when possible, to provide examples and quantitative data in support of their answers. Comments must be submitted on or before October 15, 2024. Comments may be filed electronically via the internet.2 Instructions are available on the Commission’s website https://www.ferc.gov/docs-filing/ efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, submissions sent via the U.S. Postal Service must be addressed to: Federal Energy Regulatory Commission, Office of the Secretary, 888 First Street NE, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Federal Energy Regulatory Commission, Office of the Secretary, 12225 Wilkins Avenue, Rockville, MD 20852. For more information about this Notice, please contact: Michael G. Henry (Technical Information), Office of Energy Policy and Innovation, (202) 502–8583, Michael.Henry@ferc.gov Lewis Taylor (Legal Information), Office of the General Counsel, (202) 502– 8624, Lewis.Taylor@ferc.gov Dated: September 12, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–21289 Filed 9–18–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12757–008] BOST4 Hydroelectric, LLC; Notice of Application for Amendment of License Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Non-capacity amendment of license. 2 See PO 00000 18 CFR 385.2001(a)(1)(iii) (2023). Frm 00039 Fmt 4703 Sfmt 4703 b. Project No: 12757–008. c. Date Filed: August 16, 2024. d. Applicant: BOST4 Hydroelectric, LLC. e. Name of Project: Red River Lock & Dam #4 Hydroelectric Project. f. Location: The project is located on the Red River in Catahoula, Louisiana. The project occupies federal lands managed by the U.S. Army Corps of Engineers (Corps). g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Douglas Spaulding, 1030 Tyrol Trail, Suite 101, Minneapolis, MN 55416, doug@ nelsonenergy.us, 612–599–8493. i. FERC Contact: Rebecca Martin, (202) 502–6012, Rebecca.martin@ ferc.gov. j. Cooperating agencies: With this notice, the Commission is inviting federal, state, local, and Tribal agencies with jurisdiction and/or special expertise with respect to environmental issues affected by the proposal, that wish to cooperate in the preparation of any environmental document, if applicable, to follow the instructions for filing such requests described in item k below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of any environmental document cannot also intervene. See 94 FERC ¶ 61,076 (2001). k. Deadline for filing comments, motions to intervene, and protests: October 14, 2024. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The first page of any filing should include the docket number P–12757–008. Comments emailed to Commission staff E:\FR\FM\19SEN1.SGM 19SEN1

Agencies

[Federal Register Volume 89, Number 182 (Thursday, September 19, 2024)]
[Notices]
[Page 76824]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-21289]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. AD24-9-000]


Innovations and Efficiencies in Generator Interconnection; Notice 
Requesting Post-Workshop Comment

    On September 10 and 11, 2024, Federal Energy Regulatory Commission 
(Commission) convened a staff-led workshop to discuss innovations and 
efficiencies in generator interconnection processes.
    All interested persons are invited to file post-workshop comments 
on issues raised during the workshop that they believe would benefit 
from further discussion. Parties are also invited to provide comments 
on the questions presented in the workshop agenda.\1\ Commenters need 
not respond to all topics or questions asked.
---------------------------------------------------------------------------

    \1\ See Second Supplemental Notice of Staff-Led Workshop, Docket 
No. AD24-9-000 (Aug. 14, 2024).
---------------------------------------------------------------------------

    Commenters may reference material previously filed in this docket 
but are encouraged to avoid repetition or replication of previous 
material. To facilitate the processing of comments, we urge commenters 
to organize their comments by panel topic and question presented at the 
workshop and to be brief. In addition, commenters are encouraged, when 
possible, to provide examples and quantitative data in support of their 
answers. Comments must be submitted on or before October 15, 2024.
    Comments may be filed electronically via the internet.\2\ 
Instructions are available on the Commission's website https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact 
FERC Online Support at [email protected] or toll free at 1-
866-208-3676, or for TTY, (202) 502-8659. Although the Commission 
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, submissions sent via the U.S. Postal Service must 
be addressed to: Federal Energy Regulatory Commission, Office of the 
Secretary, 888 First Street NE, Washington, DC 20426. Submissions sent 
via any other carrier must be addressed to: Federal Energy Regulatory 
Commission, Office of the Secretary, 12225 Wilkins Avenue, Rockville, 
MD 20852.
---------------------------------------------------------------------------

    \2\ See 18 CFR 385.2001(a)(1)(iii) (2023).
---------------------------------------------------------------------------

    For more information about this Notice, please contact:

Michael G. Henry (Technical Information), Office of Energy Policy and 
Innovation, (202) 502-8583, [email protected]
Lewis Taylor (Legal Information), Office of the General Counsel, (202) 
502-8624, [email protected]

    Dated: September 12, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-21289 Filed 9-18-24; 8:45 am]
BILLING CODE 6717-01-P