Alabama Power Company; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense, 74937 [2024-20833]

Download as PDF 74937 Federal Register / Vol. 89, No. 178 / Friday, September 13, 2024 / Notices khammond on DSKJM1Z7X2PROD with NOTICES Filings Instituting Proceedings Docket Numbers: RP24–1054–000. Applicants: Eastern Shore Natural Gas Company. Description: § 4(d) Rate Filing: Negotiated Rate Filing—CUC–MD to be effective 9/20/2024. Filed Date: 9/5/24. Accession Number: 20240905–5125. Comment Date: 5 p.m. ET 9/17/24. Docket Numbers: RP24–1055–000. Applicants: Southern Star Central Gas Pipeline, Inc. Description: § 4(d) Rate Filing: Correction to Tariff Sheet No. 245 to be effective 10/7/2024. Filed Date: 9/5/24. Accession Number: 20240905–5129. Comment Date: 5 p.m. ET 9/17/24. Docket Numbers: RP24–1056–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: Negotiated Rates—Total K911051 and K911252 eff 9–1–24 to be effective 9/1/ 2024. Filed Date: 9/5/24. Accession Number: 20240905–5172. Comment Date: 5 p.m. ET 9/17/24. Docket Numbers: RP24–1057–000. Applicants: MountainWest Pipeline, LLC. Description: § 4(d) Rate Filing: System Map Update to be effective 10/7/2024. Filed Date: 9/6/24. Accession Number: 20240906–5079. Comment Date: 5 p.m. ET 9/18/24. Docket Numbers: RP24–1058–000. Applicants: MountainWest Overthrust Pipeline, LLC. Description: § 4(d) Rate Filing: System Map Link to be effective 10/7/2024. Filed Date: 9/6/24. Accession Number: 20240906–5082. Comment Date: 5 p.m. ET 9/18/24. Docket Numbers: RP24–1059–000. Applicants: White River Hub, LLC. Description: § 4(d) Rate Filing: System Map Update to be effective 10/7/2024. Filed Date: 9/6/24. Accession Number: 20240906–5083. Comment Date: 5 p.m. ET 9/18/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Description: Amendment Filing: Amendment of Five-Year Review and Amended Statement of Operating Conditions to be effective 9/1/2024. Filed Date: 9/5/24. Accession Number: 20240905–5174. Comment Date: 5 p.m. ET 9/26/24. Protest Date: 5 p.m. ET 9/26/24. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: September 6, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–20765 Filed 9–12–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2628–066] Alabama Power Company; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense Filings in Existing Proceedings On November 23, 2021, as supplemented,1 the Alabama Power Company filed an application for a new major license for the 135-megawatt R.L. Harris Hydroelectric Project No. 2628 Docket Numbers: PR24–86–001. Applicants: Ameren Illinois Company. 1 The final license application filed November 23, 2021, was supplemented on March 23, 2022, June 15, 2022, and December 27, 2022. VerDate Sep<11>2014 17:53 Sep 12, 2024 Jkt 262001 PO 00000 Frm 00071 Fmt 4703 Sfmt 4703 (Harris Project or project). On March 31, 2023, Commission staff issued a notice of intent to prepare an Environmental Impact Statement (EIS) to evaluate the effects of relicensing the Harris Project. The notice included an anticipated schedule for issuing the draft and final EIS. On April 18, 2024, staff issued a notice of revised procedural schedule for preparing a draft and final EIS. By this notice, Commission staff is updating the procedural schedule for completing the draft EIS. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate. Milestone Issue draft EIS .......... Target date November 2024. Any questions regarding this notice may be directed to Sarah Salazar at (202) 502–6863 or sarah.salazar@ ferc.gov. Dated: September 9, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–20833 Filed 9–12–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG24–273–000. Applicants: BRP Avila BESS LLC. Description: BRP Avila BESS LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 9/5/24. Accession Number: 20240905–5156. Comment Date: 5 p.m. ET 9/26/24. Docket Numbers: EG24–274–000. Applicants: BRP Cachi BESS LLC. Description: BRP Cachi BESS LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 9/5/24. Accession Number: 20240905–5159. Comment Date: 5 p.m. ET 9/26/24. Docket Numbers: EG24–275–000. Applicants: BRP Castor BESS LLC. Description: BRP Castor BESS LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 9/5/24. Accession Number: 20240905–5160. Comment Date: 5 p.m. ET 9/26/24. Docket Numbers: EG24–276–000. Applicants: BRP Desna BESS LLC. E:\FR\FM\13SEN1.SGM 13SEN1

Agencies

[Federal Register Volume 89, Number 178 (Friday, September 13, 2024)]
[Notices]
[Page 74937]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-20833]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2628-066]


Alabama Power Company; Notice of Revised Procedural Schedule for 
Environmental Impact Statement for the Proposed Project Relicense

    On November 23, 2021, as supplemented,\1\ the Alabama Power Company 
filed an application for a new major license for the 135-megawatt R.L. 
Harris Hydroelectric Project No. 2628 (Harris Project or project). On 
March 31, 2023, Commission staff issued a notice of intent to prepare 
an Environmental Impact Statement (EIS) to evaluate the effects of 
relicensing the Harris Project. The notice included an anticipated 
schedule for issuing the draft and final EIS. On April 18, 2024, staff 
issued a notice of revised procedural schedule for preparing a draft 
and final EIS.
---------------------------------------------------------------------------

    \1\ The final license application filed November 23, 2021, was 
supplemented on March 23, 2022, June 15, 2022, and December 27, 
2022.
---------------------------------------------------------------------------

    By this notice, Commission staff is updating the procedural 
schedule for completing the draft EIS. The revised schedule is shown 
below. Further revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Issue draft EIS...........................  November 2024.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Sarah 
Salazar at (202) 502-6863 or [email protected].

    Dated: September 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-20833 Filed 9-12-24; 8:45 am]
BILLING CODE 6717-01-P