Pacific Gas and Electric Company, Pacific Generation LLC; Notice of Effectiveness of Withdrawal of Joint Application for Approval of Transfer of Licenses, 74933 [2024-20766]
Download as PDF
Federal Register / Vol. 89, No. 178 / Friday, September 13, 2024 / Notices
Milestone
Request Additional Information ..
Issue Acceptance Letter .............
Issue Scoping Document 1 for
Comments.
Issue Scoping Document 2 (if
necessary).
Target date
November 2024.
February 2025.
March 2025.
June 2025.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: September 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RM01–5–000]
[Project Nos. 77–316, 96–050, 137–216, 175–
030, 233–245, 606–041, 619–175, 803–119,
1061–105, 1121–137, 1354–133, 1962–221,
1988–102, 2105–129, 2106–077, 2107–051,
2130–125, 2310–252, 2661–094, 2687–189,
2735–102, and 14531–002]
khammond on DSKJM1Z7X2PROD with NOTICES
Pacific Gas and Electric Company,
Pacific Generation LLC; Notice of
Effectiveness of Withdrawal of Joint
Application for Approval of Transfer of
Licenses
On December 13, 2022, Pacific Gas
and Electric Company and Pacific
Generation LLC (applicants) filed a joint
application for approval to transfer the
following licenses:
Potter Valley Project No. 77,
Kerckhoff Project No. 96,
Mokelumne River Project No. 137,
Balch Project No. 175,
Pit 3, 4, and 5 Project No. 233,
Kilarc-Cow Creek Project No. 606,
Bucks Creek Project No. 619,
DeSabla-Centerville Project No. 803,
Phoenix Project No. 1061,
Battle Creek Project No. 1121,
Crane Valley Project No. 1354,
Rock Creek-Cresta Project No. 1962,
Haas-Kings River Project No. 1988,
Upper North Fork Feather River Project
No. 2105,
McCloud-Pit Project No. 2106,
Poe Project No. 2107,
Spring Gap-Stanislaus Project No. 2130,
Upper Drum-Spaulding Project No.
2310,
Hat Creek Project No. 2661,
Pit No. 1 Project No. 2687,
Helms Pumped Storage Project No.
2735, and
Lower Drum Project No. 14531
On August 12, 2024, applicants filed
a notice of withdrawal of their
application.
17:53 Sep 12, 2024
Jkt 262001
Electronic Tariff Filings; Notice of
Change to Implementation Date for
Revisions to eTariff
Take notice that based on requests at
the meeting on July 23, 2024, hosted by
the North American Energy Standards
Board (NAESB), the implementation of
a revised version of eTariff will be
delayed until November 25, 2024. As
requested at the meeting, this delay will
permit a single deployment of the
revisions to eTariff to include the lead
applicant name, as detailed in the June
11, 2024, Notice, along with additional
revisions to the Type of Filing and
Validation Error Codes. The Type of
Filing and Validation Error Codes
revisions will ensure that parties
differentiate between (1) compliance
filings in a current proceeding for which
the filer has a filing identifier, which are
assigned a subdocket, and (2)
compliance filings, such as compliance
with complaint orders and rulemakings,
where the filer has no existing filing
identifier and therefore must establish a
new docket. New filing codes also will
be assigned to allow utilities to
distinguish baseline rate change filings
from baseline initial rate filings.
Starting on September 30, 2024, the
currently deployed test sandbox will
include the revised filing type and
validation error codes. A subsequent
notice will be issued with the revised
filing type and validation codes to be
used in the sandbox testing.
Questions on these changes should be
directed to: Michael Goldenberg at
Michael.Goldenberg@ferc.gov or James
Sarikas at James.Sarikas@ferc.gov.
1 18
PO 00000
CFR 385.216(b) (2023).
Frm 00067
Fmt 4703
Sfmt 4703
[FR Doc. 2024–20771 Filed 9–12–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Combined Notice of Filings
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
Dated: September 6, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
Federal Energy Regulatory
Commission
Dated: September 6, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–20766 Filed 9–12–24; 8:45 am]
[FR Doc. 2024–20832 Filed 9–12–24; 8:45 am]
VerDate Sep<11>2014
No motion in opposition to the notice
of withdrawal has been filed, and the
Commission has taken no action to
disallow the withdrawal. Pursuant to
Rule 216(b) of the Commission’s Rules
of Practice and Procedure,1 the
withdrawal of the application became
effective on August 27, 2024, and this
proceeding is hereby terminated.
74933
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: PR24–95–000.
Applicants: ONEOK WesTex
Transmission, L.L.C.
Description: § 284.123(g) Rate Filing:
2024 Updated Statement of Current
Effective Rates to be effective 11/1/2024.
Filed Date: 9/6/24.
Accession Number: 20240906–5097.
Comment Date: 5 p.m. ET 9/27/24.
§ 284.123(g) Protest: 5 p.m. ET 11/5/
24.
Docket Numbers: PR24–96–000.
Applicants: DCP Raptor Pipeline,
LLC.
Description: § 284.123(g) Rate Filing:
2024 Rate Case to be effective 9/1/2024.
Filed Date: 9/6/24.
Accession Number: 20240906–5152.
Comment Date: 5 p.m. ET 9/27/24.
§ 284.123(g) Protest: 5 p.m. ET 11/5/
24.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
Filings in Existing Proceedings
Docket Numbers: RP24–514–003.
Applicants: Great Basin Gas
Transmission Company.
Description: Compliance filing: 2024
Rate Case Motion Rates to be effective
9/6/2024.
Filed Date: 9/6/24.
Accession Number: 20240906–5149.
Comment Date: 5 p.m. ET 9/18/24.
Any person desiring to protest in any
the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system (https://
E:\FR\FM\13SEN1.SGM
13SEN1
Agencies
[Federal Register Volume 89, Number 178 (Friday, September 13, 2024)]
[Notices]
[Page 74933]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-20766]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. 77-316, 96-050, 137-216, 175-030, 233-245, 606-041, 619-
175, 803-119, 1061-105, 1121-137, 1354-133, 1962-221, 1988-102, 2105-
129, 2106-077, 2107-051, 2130-125, 2310-252, 2661-094, 2687-189, 2735-
102, and 14531-002]
Pacific Gas and Electric Company, Pacific Generation LLC; Notice
of Effectiveness of Withdrawal of Joint Application for Approval of
Transfer of Licenses
On December 13, 2022, Pacific Gas and Electric Company and Pacific
Generation LLC (applicants) filed a joint application for approval to
transfer the following licenses:
Potter Valley Project No. 77,
Kerckhoff Project No. 96,
Mokelumne River Project No. 137,
Balch Project No. 175,
Pit 3, 4, and 5 Project No. 233,
Kilarc-Cow Creek Project No. 606,
Bucks Creek Project No. 619,
DeSabla-Centerville Project No. 803,
Phoenix Project No. 1061,
Battle Creek Project No. 1121,
Crane Valley Project No. 1354,
Rock Creek-Cresta Project No. 1962,
Haas-Kings River Project No. 1988,
Upper North Fork Feather River Project No. 2105,
McCloud-Pit Project No. 2106,
Poe Project No. 2107,
Spring Gap-Stanislaus Project No. 2130,
Upper Drum-Spaulding Project No. 2310,
Hat Creek Project No. 2661,
Pit No. 1 Project No. 2687,
Helms Pumped Storage Project No. 2735, and
Lower Drum Project No. 14531
On August 12, 2024, applicants filed a notice of withdrawal of
their application.
No motion in opposition to the notice of withdrawal has been filed,
and the Commission has taken no action to disallow the withdrawal.
Pursuant to Rule 216(b) of the Commission's Rules of Practice and
Procedure,\1\ the withdrawal of the application became effective on
August 27, 2024, and this proceeding is hereby terminated.
---------------------------------------------------------------------------
\1\ 18 CFR 385.216(b) (2023).
Dated: September 6, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-20766 Filed 9-12-24; 8:45 am]
BILLING CODE 6717-01-P