66098
Federal Register / Vol. 89, No. 157 / Wednesday, August 14, 2024 / Notices
ddrumheller on DSK120RN23PROD with NOTICES1
deadline. Any person wishing to
comment on ANR’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (NGA) (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for NGA facilities
when such requests are contested before
order issuance. For those extension
requests that are contested,1 the
Commission will aim to issue an order
acting on the request within 45 days.2
The Commission will address all
arguments relating to whether the
applicant has demonstrated there is
good cause to grant the extension.3 The
Commission will not consider
arguments that re-litigate the issuance of
the certificate order, including whether
the Commission properly found the
project to be in the public convenience
and necessity and whether the
Commission’s environmental analysis
for the certificate complied with the
National Environmental Policy Act
(NEPA).4 At the time a pipeline requests
an extension of time, orders on
certificates of public convenience and
necessity are final and the Commission
will not re-litigate their issuance.5 The
Director of the Office of Energy Projects,
or his or her designee, will act on all of
those extension requests that are
uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov). From the Commission’s
Home Page on the internet, this
information is available on eLibrary.
The full text of this document is
1 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1).
2 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
3 Id. at P 40.
4 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
5 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
VerDate Sep<11>2014
18:22 Aug 13, 2024
Jkt 262001
available on eLibrary in PDF and
Microsoft Word format for viewing,
printing, and/or downloading. To access
this document in eLibrary, type the
docket number excluding the last three
digits of this document in the docket
number field.
User assistance is available for
eLibrary and the Commission’s website
during normal business hours from
FERC Online Support at (202) 502–6652
(toll free at 1–866–208–3676) or email at
ferconlinesupport@ferc.gov, or the
Public Reference Room at (202) 502–
8371, TTY (202) 502–8659. Email the
Public Reference Room at
public.referenceroom@ferc.gov.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy which
must reference the Project docket
number.
To file via USPS: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First
Street NE, Washington, DC 20426
To file via any other courier: DebbieAnne A. Reese, Acting Secretary,
Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on August 19, 2024.
Dated: August 2, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–18058 Filed 8–13–24; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–41–001]
Eagle LNG Partners Jacksonville LLC;
Notice of Request for Extension of
Time
Take notice that on July 29, 2024,
Eagle LNG Partners Jacksonville LLC
(Eagle LNG) requested that the
Commission grant an extension of time,
until September 19, 2029, to construct
and place into service its Jacksonville
Project (Project) located in Jacksonville,
Florida as authorized by the
Commission in Docket No. CP17–41–
000.1 The Order required Eagle LNG to
complete construction of the Project and
make it available for service within five
years of the date of the Order, or by
September 19, 2024.
Eagle LNG states that the Jacksonville
Project has been impacted substantially
by the COVID–19 pandemic, which
began only six months after the issuance
of the Order. The COVID–19 pandemic
created an extremely challenging
environment for the negotiation and
execution of contracts. Those
impediments continued for some time
after the effects of the pandemic had
begun to subside in 2022.
Eagle LNG affirms that inflation and
supply chain issues brought on by the
COVID–19 pandemic have increased the
total installed cost of the Jacksonville
Project from what was forecast when
Eagle LNG first submitted the
Jacksonville Project application to the
Commission. Since many construction
companies are focused on larger scale
projects, and those willing to take on a
more modestly sized project are finding
it virtually impossible to hire skilled
tradesmen, Eagle LNG has found it
difficult to secure the services of a
contractor that will devote time to the
Jacksonville Project. Eagle LNG
anticipates that the construction of the
Jacksonville Project will take 24 to 36
months, with construction commencing
following a final investment decision to
be made. In order to make that final
investment decision, Eagle LNG and its
investors must be able to conclude that
the project’s FERC authorization
provides enough time to complete
construction of the Jacksonville Project.
This is the reason why Eagle LNG
requests that the FERC construction
completion deadline be extended to
September 19, 2029.
1 Eagle LNG Partners Jacksonville LLC, 168 FERC
¶ 61,181 (2019) (Order).
Frm 00069
Fmt 4703
Sfmt 4703
E:\FR\FM\14AUN1.SGM
14AUN1
Federal Register / Vol. 89, No. 157 / Wednesday, August 14, 2024 / Notices
ddrumheller on DSK120RN23PROD with NOTICES1
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Eagle LNG’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (NGA) (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for NGA facilities
when such requests are contested before
order issuance. For those extension
requests that are contested,2 the
Commission will aim to issue an order
acting on the request within 45 days.3
The Commission will address all
arguments relating to whether the
applicant has demonstrated there is
good cause to grant the extension.4 The
Commission will not consider
arguments that re-litigate the issuance of
the certificate order, including whether
the Commission properly found the
project to be in the public convenience
and necessity and whether the
Commission’s environmental analysis
for the certificate complied with the
National Environmental Policy Act
(NEPA).5 At the time a pipeline requests
an extension of time, orders on
certificates of public convenience and
necessity are final and the Commission
will not re-litigate their issuance.6 The
Director of the Office of Energy Projects,
or his or her designee, will act on all of
those extension requests that are
uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov). From the Commission’s
Home Page on the internet, this
information is available on eLibrary.
2 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2023).
3 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
4 Id.
5 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
6 Algonquin, 170 FERC ¶ 61,144, at P 40.
VerDate Sep<11>2014
18:22 Aug 13, 2024
Jkt 262001
The full text of this document is
available on eLibrary in PDF and
Microsoft Word format for viewing,
printing, and/or downloading. To access
this document in eLibrary, type the
docket number excluding the last three
digits of this document in the docket
number field.
User assistance is available for
eLibrary and the Commission’s website
during normal business hours from
FERC Online Support at (202) 502–6652
(toll free at 1–866–208–3676) or email at
ferconlinesupport@ferc.gov, or the
Public Reference Room at (202) 502–
8371, TTY (202) 502–8659. Email the
Public Reference Room at
public.referenceroom@ferc.gov.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy which
must reference the Project docket
number.
To file via USPS: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First
Street NE, Washington, DC 20426
To file via any other courier: DebbieAnne A. Reese, Acting Secretary,
Federal Energy Regulatory
Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on August 20, 2024.
Dated: August 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–18057 Filed 8–13–24; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
66099
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC24–19–000]
Commission Information Collection
Activities (FERC–566); Comment
Request; Extension
Federal Energy Regulatory
Commission.
ACTION: Notice of information collection
and request for comments.
AGENCY:
In compliance with the
requirements of the Paperwork
Reduction Act of 1995, the Federal
Energy Regulatory Commission
(Commission or FERC) is soliciting
public comment on the currently
approved information collections,
FERC–566 (Annual Report of a Utility’s
20 Largest Purchasers) in OMB Control
No. 1902–0114, which will be submitted
to the Office of Management and Budget
(OMB) for review.
DATES: Comments on the collections of
information are due September 13,
2024.
ADDRESSES: You may submit copies of
your comments (identified by Docket
No. IC24–19–000) on FERC–566 by one
of the following methods:
Electronic filing through https://
www.ferc.gov is preferred.
• Electronic Filing: Documents must
be filed in acceptable native
applications and print-to-PDF, but not
in scanned or picture format.
• For those unable to file
electronically, comments may be filed
by USPS mail or by hand (including
courier) delivery:
Æ Mail via U.S. Postal Service Only:
Addressed to: Federal Energy
Regulatory Commission, Secretary of the
Commission, 888 First Street NE,
Washington, DC 20426.
Æ Hand (including courier) Delivery:
Deliver to: Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852.
Instructions: OMB submissions must
be formatted and filed in accordance
with submission guidelines at
www.reginfo.gov/public/do/PRAMain.
Using the search function under the
‘‘Currently Under Review’’ field, select
Federal Energy Regulatory Commission;
click ‘‘submit,’’ and select ‘‘comment’’
to the right of the subject collection.
FERC submissions must be formatted
and filed in accordance with submission
guidelines at: https://www.ferc.gov. For
user assistance, contact FERC Online
Support by email at ferconlinesupport@
ferc.gov, or by phone at: (866) 208–3676
(toll-free).
SUMMARY:
E:\FR\FM\14AUN1.SGM
14AUN1
Agencies
[Federal Register Volume 89, Number 157 (Wednesday, August 14, 2024)]
[Notices]
[Pages 66098-66099]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-18057]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-41-001]
Eagle LNG Partners Jacksonville LLC; Notice of Request for
Extension of Time
Take notice that on July 29, 2024, Eagle LNG Partners Jacksonville
LLC (Eagle LNG) requested that the Commission grant an extension of
time, until September 19, 2029, to construct and place into service its
Jacksonville Project (Project) located in Jacksonville, Florida as
authorized by the Commission in Docket No. CP17-41-000.\1\ The Order
required Eagle LNG to complete construction of the Project and make it
available for service within five years of the date of the Order, or by
September 19, 2024.
---------------------------------------------------------------------------
\1\ Eagle LNG Partners Jacksonville LLC, 168 FERC ] 61,181
(2019) (Order).
---------------------------------------------------------------------------
Eagle LNG states that the Jacksonville Project has been impacted
substantially by the COVID-19 pandemic, which began only six months
after the issuance of the Order. The COVID-19 pandemic created an
extremely challenging environment for the negotiation and execution of
contracts. Those impediments continued for some time after the effects
of the pandemic had begun to subside in 2022.
Eagle LNG affirms that inflation and supply chain issues brought on
by the COVID-19 pandemic have increased the total installed cost of the
Jacksonville Project from what was forecast when Eagle LNG first
submitted the Jacksonville Project application to the Commission. Since
many construction companies are focused on larger scale projects, and
those willing to take on a more modestly sized project are finding it
virtually impossible to hire skilled tradesmen, Eagle LNG has found it
difficult to secure the services of a contractor that will devote time
to the Jacksonville Project. Eagle LNG anticipates that the
construction of the Jacksonville Project will take 24 to 36 months,
with construction commencing following a final investment decision to
be made. In order to make that final investment decision, Eagle LNG and
its investors must be able to conclude that the project's FERC
authorization provides enough time to complete construction of the
Jacksonville Project. This is the reason why Eagle LNG requests that
the FERC construction completion deadline be extended to September 19,
2029.
[[Page 66099]]
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on Eagle LNG's request
for an extension of time may do so. No reply comments or answers will
be considered. If you wish to obtain legal status by becoming a party
to the proceedings for this request, you should, on or before the
comment date stated below, file a motion to intervene in accordance
with the requirements of the Commission's Rules of Practice and
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (NGA) (18 CFR 157.10).
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for NGA
facilities when such requests are contested before order issuance. For
those extension requests that are contested,\2\ the Commission will aim
to issue an order acting on the request within 45 days.\3\ The
Commission will address all arguments relating to whether the applicant
has demonstrated there is good cause to grant the extension.\4\ The
Commission will not consider arguments that re-litigate the issuance of
the certificate order, including whether the Commission properly found
the project to be in the public convenience and necessity and whether
the Commission's environmental analysis for the certificate complied
with the National Environmental Policy Act (NEPA).\5\ At the time a
pipeline requests an extension of time, orders on certificates of
public convenience and necessity are final and the Commission will not
re-litigate their issuance.\6\ The Director of the Office of Energy
Projects, or his or her designee, will act on all of those extension
requests that are uncontested.
---------------------------------------------------------------------------
\2\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2023).
\3\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\4\ Id.
\5\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\6\ Algonquin, 170 FERC ] 61,144, at P 40.
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov).
From the Commission's Home Page on the internet, this information is
available on eLibrary. The full text of this document is available on
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or
downloading. To access this document in eLibrary, type the docket
number excluding the last three digits of this document in the docket
number field.
User assistance is available for eLibrary and the Commission's
website during normal business hours from FERC Online Support at (202)
502-6652 (toll free at 1-866-208-3676) or email at
[email protected], or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
[email protected].
The Commission strongly encourages electronic filings of comments
in lieu of paper using the ``eFile'' link at https://www.ferc.gov. In
lieu of electronic filing, you may submit a paper copy which must
reference the Project docket number.
To file via USPS: Debbie-Anne A. Reese, Acting Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426
To file via any other courier: Debbie-Anne A. Reese, Acting Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Comment Date: 5:00 p.m. Eastern Time on August 20, 2024.
Dated: August 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-18057 Filed 8-13-24; 8:45 am]